Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 742-29-0004 | |
| Parish: Lafourche | |
| Routes: | |
| Description: Urban Systems Project - Tiger Drive Ext. & Thibodaux Overlay | |
| Type Const: GRADING, PAVEMENT PATCHING, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $1,458,178.26 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,340,433.21 |
| 2 | 06487 | Huey Stockstill, Inc. | $1,387,731.16 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $1,640,917.81 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Huey Stockstill, Inc. |
- 3 - Coastal Bridge Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 14,000.00 | 14,000.00 | 2,000.00 | 2,000.00 | 7,500.00 | 7,500.00 |
| 0002 | 202-02-02000 | Removal of Asphalt Drives | 75 | SQYD | 20.00 | 1,500.00 | 25.00 | 1,875.00 | 20.00 | 1,500.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 65 | LNFT | 10.00 | 650.00 | 15.00 | 975.00 | 50.00 | 3,250.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 30 | SQYD | 20.00 | 600.00 | 32.00 | 960.00 | 20.00 | 600.00 |
| 0005 | 203-01-00100 | General Excavation | 10 | CUYD | 1.00 | 10.00 | 14.00 | 140.00 | 20.00 | 200.00 |
| 0006 | 203-03-00100 | Embankment | 10 | CUYD | 1.00 | 10.00 | 35.00 | 350.00 | 30.00 | 300.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 50 | LNFT | 1.00 | 50.00 | 1.00 | 50.00 | 2.00 | 100.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 200 | CUYD | 50.00 | 10,000.00 | 121.00 | 24,200.00 | 40.00 | 8,000.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 9,302 | TON | 82.00 | 762,764.00 | 81.00 | 753,462.00 | 85.00 | 790,670.00 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 178.6 | TON | 82.00 | 14,645.20 | 175.00 | 31,255.00 | 135.00 | 24,111.00 |
| 0011 | 509-01-00100 | Cold Planing Asphaltic Pavement | 51,933 | SQYD | 1.00 | 51,933.00 | 2.75 | 142,815.75 | 2.75 | 142,815.75 |
| 0012 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,509 | CUYD | 10.00 | -25,090.00 | 15.00 | -37,635.00 | 0.01 | -25.09 |
| 0013 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 4,080 | SQYD | 50.00 | 204,000.00 | 75.00 | 306,000.00 | 90.00 | 367,200.00 |
| 0014 | 702-04-00100 | Adjusting Manholes | 34 | EACH | 50.00 | 1,700.00 | 400.00 | 13,600.00 | 175.00 | 5,950.00 |
| 0015 | 706-01-00100 | Concrete Walk (4" Thick) | 10 | SQYD | 50.00 | 500.00 | 58.00 | 580.00 | 65.00 | 650.00 |
| 0016 | 706-02-00200 | Concrete Drive (6" Thick) | 20 | SQYD | 50.00 | 1,000.00 | 70.00 | 1,400.00 | 65.00 | 1,300.00 |
| 0017 | 707-03-00100 | Combination Concrete Curb and Gutter | 65 | LNFT | 50.00 | 3,250.00 | 35.00 | 2,275.00 | 65.00 | 4,225.00 |
| 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 |
| 0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.131 | MILE | 200.00 | 2,026.20 | 10.00 | 101.31 | 400.00 | 4,052.40 |
| 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.38 | MILE | 0.10 | 0.34 | 10.00 | 33.80 | 300.00 | 1,014.00 |
| 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.68 | MILE | 0.10 | 0.17 | 10.00 | 16.80 | 665.00 | 1,117.20 |
| 0022 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5.00 | 5.00 | 1,000.00 | 1,000.00 | 7,500.00 | 7,500.00 |
| 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 130,000.00 | 130,000.00 | 90,000.00 | 90,000.00 | 190,000.00 | 190,000.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 424 | EACH | 5.00 | 2,120.00 | 5.50 | 2,332.00 | 4.85 | 2,056.40 |
| 0025 | 732-01-04080 | Plastic Pavement Striping (24" Width) (Preformed Retroreflective Thermoplastic) (Heat Applied) (125 mil) | 144 | LNFT | 3.00 | 432.00 | 17.00 | 2,448.00 | 3.70 | 532.80 |
| 0026 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 6.97 | MILE | 1,500.00 | 10,455.00 | 1,650.00 | 11,500.50 | 1,600.00 | 11,152.00 |
| 0027 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.095 | MILE | 5,000.00 | 475.00 | 8,000.00 | 760.00 | 5,280.00 | 501.60 |
| 0028 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 3.31 | MILE | 425.00 | 1,406.75 | 700.00 | 2,317.00 | 425.00 | 1,406.75 |
| 0029 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 195.00 | 195.00 | 300.00 | 300.00 | 195.00 | 195.00 |
| 0030 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 185.00 | 185.00 | 250.00 | 250.00 | 185.00 | 185.00 |
| 0031 | 736-09-00100 | Loop Detector | 80 | LNFT | 15.00 | 1,200.00 | 18.00 | 1,440.00 | 25.00 | 2,000.00 |
| 0032 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 0.01 | 0.01 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 500.00 | 500.00 | 12,500.00 | 12,500.00 |
| 0034 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,554 | INLF | 0.01 | 15.54 | 1.00 | 1,554.00 | 2.00 | 3,108.00 |
| 0035 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 50 | INLF | 1.00 | 50.00 | 2.50 | 125.00 | 10.00 | 500.00 |
| 0036 | NS-ENH-01040 | Adjusting Utility Boxes At various locations as described in the plans | 69 | EACH | 5.00 | 345.00 | 250.00 | 17,250.00 | 250.00 | 17,250.00 |
| CONTRACTOR TOTAL | 1,340,433.21 | 1,387,731.16 | 1,640,917.81 | |||||||