Bid Tabulations
Letting of
08/31/2011
LA DOTD Headquarters
| Lead Project: 742-17-0151 | |
| Parish: East Baton Rouge | |
| Routes: | |
| Description: C.T. Paving (N End of Sullivan Bridge to Frenchtown Rd) | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $4,940,232.45 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 39462 | Jb James Construction Llc | $4,594,094.50 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $4,793,936.40 |
| 3 | 48896 | Command Construction Industries LLC | $4,945,593.35 |
| 4 | 34567 | James Construction Group LLC | $4,998,804.49 |
| 5 | 29595 | Boone Services Inc. | $5,201,659.73 |
| 6 | 14422 | T. L. Wallace Construction, Inc. | $5,382,338.79 |
| 7 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $5,799,573.35 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Jb James Construction Llc |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Command Construction Industries LLC |
- 4 - James Construction Group LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 40,000.00 | 40,000.00 | 42,000.00 | 42,000.00 | 100,000.00 | 100,000.00 | 30,000.00 | 30,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 2,000.00 | 2,000.00 | 100,000.00 | 100,000.00 | 9,000.00 | 9,000.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 199.2 | SQYD | 10.00 | 1,992.00 | 9.00 | 1,792.80 | 1.00 | 199.20 | 7.80 | 1,553.76 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,711.1 | SQYD | 5.00 | 8,555.50 | 7.00 | 11,977.70 | 5.00 | 8,555.50 | 2.25 | 3,849.98 |
| 0005 | 203-01-00100 | General Excavation | 6,967 | CUYD | 7.00 | 48,769.00 | 8.00 | 55,736.00 | 10.00 | 69,670.00 | 1.80 | 12,540.60 |
| 0006 | 203-03-00100 | Embankment | 8,914 | CUYD | 17.00 | 151,538.00 | 15.00 | 133,710.00 | 10.00 | 89,140.00 | 10.00 | 89,140.00 |
| 0007 | 203-04-00300 | Nonplastic Embankment (Stone) | 858.5 | CUYD | 50.00 | 42,925.00 | 100.00 | 85,850.00 | 100.00 | 85,850.00 | 75.00 | 64,387.50 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 217 | EACH | 10.00 | 2,170.00 | 15.00 | 3,255.00 | 10.00 | 2,170.00 | 13.00 | 2,821.00 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 23 | EACH | 130.00 | 2,990.00 | 250.00 | 5,750.00 | 125.00 | 2,875.00 | 145.00 | 3,335.00 |
| 0010 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 8 | EACH | 800.00 | 6,400.00 | 500.00 | 4,000.00 | 225.00 | 1,800.00 | 250.00 | 2,000.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 4,000 | LNFT | 2.00 | 8,000.00 | 1.50 | 6,000.00 | 5.00 | 20,000.00 | 2.00 | 8,000.00 |
| 0012 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 3,000.00 | 6,000.00 | 3,000.00 | 6,000.00 | 2,000.00 | 4,000.00 | 3,000.00 | 6,000.00 |
| 0013 | 302-02-01040 | Class II Base Course (4" Thick) (Stone) | 38,359.5 | SQYD | 9.00 | 345,235.50 | 9.40 | 360,579.30 | 10.00 | 383,595.00 | 9.00 | 345,235.50 |
| 0014 | 302-02-01561 | Class II Base Course (5" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone Only) | 7,508.4 | SQYD | 7.00 | 52,558.80 | 12.00 | 90,100.80 | 10.00 | 75,084.00 | 11.00 | 82,592.40 |
| 0015 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 51,268.2 | SQYD | 8.50 | 435,779.70 | 12.00 | 615,218.40 | 10.00 | 512,682.00 | 11.00 | 563,950.20 |
| 0016 | 304-05-00100 | Lime Treatment (Type E) | 727 | TON | 150.00 | 109,050.00 | 30.00 | 21,810.00 | 10.00 | 7,270.00 | 225.00 | 163,575.00 |
| 0017 | 401-01-00100 | Aggregate Surface Course (Net Section) | 344.2 | CUYD | 85.00 | 29,257.00 | 80.00 | 27,536.00 | 80.00 | 27,536.00 | 50.00 | 17,210.00 |
| 0018 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 45.00 | 22,500.00 | 35.00 | 17,500.00 | 1.00 | 500.00 | 90.00 | 45,000.00 |
| 0019 | 502-01-00100 | Superpave Asphaltic Concrete | 3,001.6 | TON | 90.00 | 270,144.00 | 105.00 | 315,168.00 | 100.00 | 300,160.00 | 98.00 | 294,156.80 |
| 0020 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 42.31 | TON | 150.00 | 6,346.50 | 275.00 | 11,635.25 | 175.00 | 7,404.25 | 150.00 | 6,346.50 |
| 0021 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 33,838.5 | SQYD | 45.00 | 1,522,732.50 | 42.00 | 1,421,217.00 | 47.00 | 1,590,409.50 | 47.00 | 1,590,409.50 |
| 0022 | 601-02-01100 | Portland Cement Concrete Pavement (10" Thick) (Crossovers & Turnouts) | 2,520.4 | SQYD | 54.00 | 136,101.60 | 65.00 | 163,826.00 | 50.00 | 126,020.00 | 75.00 | 189,030.00 |
| 0023 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 100 | EACH | 100.00 | 10,000.00 | 100.00 | 10,000.00 | 100.00 | 10,000.00 | 90.00 | 9,000.00 |
| 0024 | 701-01-01040 | Cross Drain Pipe (36" RCP/PP) | 200 | LNFT | 120.00 | 24,000.00 | 155.00 | 31,000.00 | 150.00 | 30,000.00 | 125.00 | 25,000.00 |
| 0025 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 2,093 | LNFT | 50.00 | 104,650.00 | 45.00 | 94,185.00 | 60.00 | 125,580.00 | 48.00 | 100,464.00 |
| 0026 | 701-03-02000 | Storm Drain Pipe (Outfall) (15" PP or 18" CMP) | 215 | LNFT | 50.00 | 10,750.00 | 62.00 | 13,330.00 | 100.00 | 21,500.00 | 49.00 | 10,535.00 |
| 0027 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 298 | LNFT | 52.00 | 15,496.00 | 55.00 | 16,390.00 | 45.00 | 13,410.00 | 53.00 | 15,794.00 |
| 0028 | 701-05-02040 | Side Drain Pipe (Erosion) (18" PP/CMP) | 160 | LNFT | 55.00 | 8,800.00 | 65.00 | 10,400.00 | 45.00 | 7,200.00 | 52.00 | 8,320.00 |
| 0029 | 702-03-00100 | Catch Basins (CB-01) | 18 | EACH | 2,000.00 | 36,000.00 | 2,300.00 | 41,400.00 | 3,000.00 | 54,000.00 | 1,950.00 | 35,100.00 |
| 0030 | 702-03-00500 | Catch Basins (CB-06) | 24 | EACH | 2,800.00 | 67,200.00 | 3,600.00 | 86,400.00 | 3,500.00 | 84,000.00 | 2,560.00 | 61,440.00 |
| 0031 | 702-03-00600 | Catch Basins (CB-07) | 1 | EACH | 4,000.00 | 4,000.00 | 5,200.00 | 5,200.00 | 4,000.00 | 4,000.00 | 3,630.00 | 3,630.00 |
| 0032 | 703-03-00100 | Perforated Pipe Underdrains | 1,640 | LNFT | 10.00 | 16,400.00 | 13.00 | 21,320.00 | 10.00 | 16,400.00 | 10.00 | 16,400.00 |
| 0033 | 704-03-00100 | Blocked Out Guard Rail | 581.3 | LNFT | 17.00 | 9,882.10 | 23.00 | 13,369.90 | 16.00 | 9,300.80 | 16.00 | 9,300.80 |
| 0034 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 175 | LNFT | 50.00 | 8,750.00 | 65.00 | 11,375.00 | 50.00 | 8,750.00 | 50.00 | 8,750.00 |
| 0035 | 704-11-00100 | Guard Rail End Treatment (Flared) | 7 | EACH | 2,300.00 | 16,100.00 | 2,400.00 | 16,800.00 | 2,200.00 | 15,400.00 | 2,200.00 | 15,400.00 |
| 0036 | 705-06-00100 | Chain Link Fence (4-Foot Height) | 74 | LNFT | 40.00 | 2,960.00 | 55.00 | 4,070.00 | 25.00 | 1,850.00 | 24.00 | 1,776.00 |
| 0037 | 706-02-00200 | Concrete Drive (6" Thick) | 342.2 | SQYD | 48.00 | 16,425.60 | 63.00 | 21,558.60 | 50.00 | 17,110.00 | 50.00 | 17,110.00 |
| 0038 | 706-02-00300 | Concrete Drive (8" Thick) | 533.9 | SQYD | 54.00 | 28,830.60 | 72.00 | 38,440.80 | 55.00 | 29,364.50 | 65.00 | 34,703.50 |
| 0039 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 326.3 | SQYD | 38.00 | 12,399.40 | 65.00 | 21,209.50 | 45.00 | 14,683.50 | 38.00 | 12,399.40 |
| 0040 | 707-01-00300 | Concrete Curb (Mountable) | 9,140 | LNFT | 5.00 | 45,700.00 | 4.45 | 40,673.00 | 3.00 | 27,420.00 | 3.00 | 27,420.00 |
| 0041 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 1,000.00 | 1,000.00 | 10,000.00 | 10,000.00 |
| 0042 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.94 | MILE | 1,000.00 | 940.00 | 475.00 | 446.50 | 550.00 | 517.00 | 550.00 | 517.00 |
| 0043 | 716-01-00100 | Mulch (Vegetative) | 0.26 | TON | 2,500.00 | 650.00 | 2,800.00 | 728.00 | 3,000.00 | 780.00 | 2,500.00 | 650.00 |
| 0044 | 717-01-00100 | Seeding | 342 | LB | 9.00 | 3,078.00 | 9.00 | 3,078.00 | 5.00 | 1,710.00 | 8.50 | 2,907.00 |
| 0045 | 718-01-00100 | Fertilizer | 11,390 | LB | 0.55 | 6,264.50 | 0.45 | 5,125.50 | 0.10 | 1,139.00 | 0.55 | 6,264.50 |
| 0046 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 928 | SQYD | 1.50 | 1,392.00 | 1.65 | 1,531.20 | 1.50 | 1,392.00 | 1.40 | 1,299.20 |
| 0047 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 434 | SQYD | 1.70 | 737.80 | 1.65 | 716.10 | 1.75 | 759.50 | 1.60 | 694.40 |
| 0048 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 128 | SQYD | 2.00 | 256.00 | 2.25 | 288.00 | 2.00 | 256.00 | 1.85 | 236.80 |
| 0049 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5,000.00 | 5,000.00 | 3,500.00 | 3,500.00 | 5,000.00 | 5,000.00 | 9,000.00 | 9,000.00 |
| 0050 | 725-01-00100 | Temporary Detour Roads | 3,236.5 | SQYD | 38.00 | 122,987.00 | 55.00 | 178,007.50 | 1.00 | 3,236.50 | 75.00 | 242,737.50 |
| 0051 | 726-01-00100 | Bedding Material | 495 | CUYD | 38.00 | 18,810.00 | 80.00 | 39,600.00 | 75.00 | 37,125.00 | 36.00 | 17,820.00 |
| 0052 | 727-01-00100 | Mobilization | 1 | LUMP | 440,000.00 | 440,000.00 | 340,000.00 | 340,000.00 | 500,000.00 | 500,000.00 | 475,000.00 | 475,000.00 |
| 0053 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 100.00 | 1,000.00 | 90.00 | 900.00 | 100.00 | 1,000.00 | 100.00 | 1,000.00 |
| 0054 | 729-19-00200 | Dead End Road Installations (Type B) | 4 | EACH | 1,300.00 | 5,200.00 | 1,800.00 | 7,200.00 | 1,250.00 | 5,000.00 | 1,250.00 | 5,000.00 |
| 0055 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 3,350 | EACH | 8.50 | 28,475.00 | 9.50 | 31,825.00 | 10.00 | 33,500.00 | 8.50 | 28,475.00 |
| 0056 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,947 | EACH | 4.50 | 8,761.50 | 4.75 | 9,248.25 | 5.00 | 9,735.00 | 4.25 | 8,274.75 |
| 0057 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 418 | LNFT | 1.00 | 418.00 | 1.15 | 480.70 | 1.50 | 627.00 | 1.00 | 418.00 |
| 0058 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 100 | LNFT | 5.00 | 500.00 | 5.65 | 565.00 | 5.00 | 500.00 | 5.00 | 500.00 |
| 0059 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.968 | MILE | 2,600.00 | 23,316.80 | 2,800.00 | 25,110.40 | 3,000.00 | 26,904.00 | 2,600.00 | 23,316.80 |
| 0060 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.539 | MILE | 900.00 | 4,085.10 | 1,000.00 | 4,539.00 | 900.00 | 4,085.10 | 900.00 | 4,085.10 |
| 0061 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.27 | MILE | 2,200.00 | 594.00 | 2,400.00 | 648.00 | 3,000.00 | 810.00 | 2,200.00 | 594.00 |
| 0062 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 180.00 | 2,160.00 | 190.00 | 2,280.00 | 250.00 | 3,000.00 | 170.00 | 2,040.00 |
| 0063 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 200.00 | 1,200.00 | 215.00 | 1,290.00 | 250.00 | 1,500.00 | 195.00 | 1,170.00 |
| 0064 | 735-01-00100 | Mailboxes | 8 | EACH | 10.00 | 80.00 | 5.65 | 45.20 | 1.00 | 8.00 | 1.00 | 8.00 |
| 0065 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 100.00 | 800.00 | 250.00 | 2,000.00 | 140.00 | 1,120.00 | 140.00 | 1,120.00 |
| 0066 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | 50,000.00 | 50,000.00 |
| 0067 | NS-P17-00001 | NS Traffic Signal System | 1 | LUMP | 160,000.00 | 160,000.00 | 180,000.00 | 180,000.00 | 200,000.00 | 200,000.00 | 163,000.00 | 163,000.00 |
| CONTRACTOR TOTAL | 4,594,094.50 | 4,793,936.40 | 4,945,593.35 | 4,998,804.49 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Boone Services Inc. |
- 6 - T. L. Wallace Construction, Inc. |
- 7 - F.G. Sullivan, Jr. Contractor LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,500.00 | 1,500.00 | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,500.00 | 1,500.00 | 10,000.00 | 10,000.00 | 2,000.00 | 2,000.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 199.2 | SQYD | 7.01 | 1,396.39 | 9.90 | 1,972.08 | 12.00 | 2,390.40 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,711.1 | SQYD | 8.12 | 13,894.13 | 6.80 | 11,635.48 | 5.00 | 8,555.50 |
| 0005 | 203-01-00100 | General Excavation | 6,967 | CUYD | 9.33 | 65,002.11 | 4.90 | 34,138.30 | 11.00 | 76,637.00 |
| 0006 | 203-03-00100 | Embankment | 8,914 | CUYD | 14.92 | 132,996.88 | 15.00 | 133,710.00 | 24.00 | 213,936.00 |
| 0007 | 203-04-00300 | Nonplastic Embankment (Stone) | 858.5 | CUYD | 99.54 | 85,455.09 | 101.50 | 87,137.75 | 85.00 | 72,972.50 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 217 | EACH | 10.50 | 2,278.50 | 10.53 | 2,285.01 | 10.00 | 2,170.00 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 23 | EACH | 131.25 | 3,018.75 | 131.58 | 3,026.34 | 125.00 | 2,875.00 |
| 0010 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 8 | EACH | 522.76 | 4,182.08 | 410.00 | 3,280.00 | 500.00 | 4,000.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 4,000 | LNFT | 1.87 | 7,480.00 | 1.74 | 6,960.00 | 1.65 | 6,600.00 |
| 0012 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 12,954.00 | 25,908.00 | 3,100.00 | 6,200.00 | 3,000.00 | 6,000.00 |
| 0013 | 302-02-01040 | Class II Base Course (4" Thick) (Stone) | 38,359.5 | SQYD | 11.36 | 435,763.92 | 9.50 | 364,415.25 | 12.00 | 460,314.00 |
| 0014 | 302-02-01561 | Class II Base Course (5" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone Only) | 7,508.4 | SQYD | 13.39 | 100,537.48 | 12.50 | 93,855.00 | 15.00 | 112,626.00 |
| 0015 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 51,268.2 | SQYD | 8.57 | 439,368.47 | 8.25 | 422,962.65 | 12.00 | 615,218.40 |
| 0016 | 304-05-00100 | Lime Treatment (Type E) | 727 | TON | 303.43 | 220,593.61 | 300.00 | 218,100.00 | 300.00 | 218,100.00 |
| 0017 | 401-01-00100 | Aggregate Surface Course (Net Section) | 344.2 | CUYD | 106.32 | 36,595.34 | 87.50 | 30,117.50 | 75.00 | 25,815.00 |
| 0018 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 61.33 | 30,665.00 | 32.00 | 16,000.00 | 40.00 | 20,000.00 |
| 0019 | 502-01-00100 | Superpave Asphaltic Concrete | 3,001.6 | TON | 106.05 | 318,319.68 | 103.15 | 309,615.04 | 130.00 | 390,208.00 |
| 0020 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 42.31 | TON | 165.38 | 6,997.23 | 157.89 | 6,680.33 | 200.00 | 8,462.00 |
| 0021 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 33,838.5 | SQYD | 53.46 | 1,809,006.21 | 61.00 | 2,064,148.50 | 68.00 | 2,301,018.00 |
| 0022 | 601-02-01100 | Portland Cement Concrete Pavement (10" Thick) (Crossovers & Turnouts) | 2,520.4 | SQYD | 63.56 | 160,196.62 | 110.00 | 277,244.00 | 73.00 | 183,989.20 |
| 0023 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 100 | EACH | 367.50 | 36,750.00 | 96.00 | 9,600.00 | 100.00 | 10,000.00 |
| 0024 | 701-01-01040 | Cross Drain Pipe (36" RCP/PP) | 200 | LNFT | 71.95 | 14,390.00 | 93.00 | 18,600.00 | 115.00 | 23,000.00 |
| 0025 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 2,093 | LNFT | 25.49 | 53,350.57 | 36.00 | 75,348.00 | 53.00 | 110,929.00 |
| 0026 | 701-03-02000 | Storm Drain Pipe (Outfall) (15" PP or 18" CMP) | 215 | LNFT | 25.74 | 5,534.10 | 32.00 | 6,880.00 | 50.00 | 10,750.00 |
| 0027 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 298 | LNFT | 30.06 | 8,957.88 | 53.00 | 15,794.00 | 58.00 | 17,284.00 |
| 0028 | 701-05-02040 | Side Drain Pipe (Erosion) (18" PP/CMP) | 160 | LNFT | 26.79 | 4,286.40 | 43.00 | 6,880.00 | 55.00 | 8,800.00 |
| 0029 | 702-03-00100 | Catch Basins (CB-01) | 18 | EACH | 3,371.00 | 60,678.00 | 2,400.00 | 43,200.00 | 2,500.00 | 45,000.00 |
| 0030 | 702-03-00500 | Catch Basins (CB-06) | 24 | EACH | 3,324.00 | 79,776.00 | 4,100.00 | 98,400.00 | 2,800.00 | 67,200.00 |
| 0031 | 702-03-00600 | Catch Basins (CB-07) | 1 | EACH | 3,858.00 | 3,858.00 | 5,800.00 | 5,800.00 | 3,300.00 | 3,300.00 |
| 0032 | 703-03-00100 | Perforated Pipe Underdrains | 1,640 | LNFT | 12.50 | 20,500.00 | 15.00 | 24,600.00 | 10.00 | 16,400.00 |
| 0033 | 704-03-00100 | Blocked Out Guard Rail | 581.3 | LNFT | 16.80 | 9,765.84 | 21.05 | 12,236.37 | 16.00 | 9,300.80 |
| 0034 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 175 | LNFT | 52.50 | 9,187.50 | 73.68 | 12,894.00 | 50.00 | 8,750.00 |
| 0035 | 704-11-00100 | Guard Rail End Treatment (Flared) | 7 | EACH | 2,310.00 | 16,170.00 | 2,315.72 | 16,210.04 | 2,200.00 | 15,400.00 |
| 0036 | 705-06-00100 | Chain Link Fence (4-Foot Height) | 74 | LNFT | 32.55 | 2,408.70 | 31.58 | 2,336.92 | 18.00 | 1,332.00 |
| 0037 | 706-02-00200 | Concrete Drive (6" Thick) | 342.2 | SQYD | 44.02 | 15,063.64 | 65.00 | 22,243.00 | 65.00 | 22,243.00 |
| 0038 | 706-02-00300 | Concrete Drive (8" Thick) | 533.9 | SQYD | 44.28 | 23,641.09 | 73.00 | 38,974.70 | 70.00 | 37,373.00 |
| 0039 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 326.3 | SQYD | 43.93 | 14,334.36 | 41.00 | 13,378.30 | 50.00 | 16,315.00 |
| 0040 | 707-01-00300 | Concrete Curb (Mountable) | 9,140 | LNFT | 6.84 | 62,517.60 | 6.70 | 61,238.00 | 7.00 | 63,980.00 |
| 0041 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 13,369.00 | 13,369.00 | 32,000.00 | 32,000.00 | 49,000.00 | 49,000.00 |
| 0042 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.94 | MILE | 1,050.00 | 987.00 | 315.78 | 296.83 | 400.00 | 376.00 |
| 0043 | 716-01-00100 | Mulch (Vegetative) | 0.26 | TON | 2,625.00 | 682.50 | 2,631.50 | 684.19 | 2,500.00 | 650.00 |
| 0044 | 717-01-00100 | Seeding | 342 | LB | 8.93 | 3,054.06 | 8.95 | 3,060.90 | 8.50 | 2,907.00 |
| 0045 | 718-01-00100 | Fertilizer | 11,390 | LB | 0.58 | 6,606.20 | 0.58 | 6,606.20 | 0.55 | 6,264.50 |
| 0046 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 928 | SQYD | 1.47 | 1,364.16 | 1.47 | 1,364.16 | 1.40 | 1,299.20 |
| 0047 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 434 | SQYD | 1.68 | 729.12 | 1.68 | 729.12 | 1.60 | 694.40 |
| 0048 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 128 | SQYD | 1.94 | 248.32 | 1.95 | 249.60 | 1.85 | 236.80 |
| 0049 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 8,177.00 | 8,177.00 | 13,400.00 | 13,400.00 | 5,000.00 | 5,000.00 |
| 0050 | 725-01-00100 | Temporary Detour Roads | 3,236.5 | SQYD | 63.85 | 206,650.53 | 37.75 | 122,177.88 | 50.00 | 161,825.00 |
| 0051 | 726-01-00100 | Bedding Material | 495 | CUYD | 29.29 | 14,498.55 | 35.00 | 17,325.00 | 50.00 | 24,750.00 |
| 0052 | 727-01-00100 | Mobilization | 1 | LUMP | 271,751.00 | 271,751.00 | 202,000.00 | 202,000.00 | 48,000.00 | 48,000.00 |
| 0053 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 105.00 | 1,050.00 | 78.95 | 789.50 | 100.00 | 1,000.00 |
| 0054 | 729-19-00200 | Dead End Road Installations (Type B) | 4 | EACH | 1,313.00 | 5,252.00 | 1,526.27 | 6,105.08 | 1,250.00 | 5,000.00 |
| 0055 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 3,350 | EACH | 8.93 | 29,915.50 | 8.42 | 28,207.00 | 8.00 | 26,800.00 |
| 0056 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,947 | EACH | 4.46 | 8,683.62 | 5.26 | 10,241.22 | 4.25 | 8,274.75 |
| 0057 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 418 | LNFT | 1.05 | 438.90 | 3.16 | 1,320.88 | 1.00 | 418.00 |
| 0058 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 100 | LNFT | 5.25 | 525.00 | 5.26 | 526.00 | 5.00 | 500.00 |
| 0059 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.968 | MILE | 2,730.00 | 24,482.64 | 2,736.76 | 24,543.26 | 2,600.00 | 23,316.80 |
| 0060 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.539 | MILE | 945.00 | 4,289.36 | 789.45 | 3,583.31 | 900.00 | 4,085.10 |
| 0061 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.27 | MILE | 2,310.00 | 623.70 | 4,736.70 | 1,278.91 | 2,200.00 | 594.00 |
| 0062 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 178.50 | 2,142.00 | 342.10 | 4,105.20 | 170.00 | 2,040.00 |
| 0063 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 205.00 | 1,230.00 | 421.04 | 2,526.24 | 195.00 | 1,170.00 |
| 0064 | 735-01-00100 | Mailboxes | 8 | EACH | 1.05 | 8.40 | 12.00 | 96.00 | 1.00 | 8.00 |
| 0065 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 147.00 | 1,176.00 | 180.00 | 1,440.00 | 140.00 | 1,120.00 |
| 0066 | 740-01-00100 | Construction Layout | 1 | LUMP | 78,750.00 | 78,750.00 | 94,207.70 | 94,207.70 | 35,000.00 | 35,000.00 |
| 0067 | NS-P17-00001 | NS Traffic Signal System | 1 | LUMP | 171,150.00 | 171,150.00 | 205,378.05 | 205,378.05 | 163,000.00 | 163,000.00 |
| CONTRACTOR TOTAL | 5,201,659.73 | 5,382,338.79 | 5,799,573.35 | |||||||