Bid Tabulations
Letting of
06/15/2011
LA DOTD Headquarters
| Lead Project: 742-17-0149 | |
| Parish: East Baton Rouge | |
| Routes: | |
| Description: C.T. Paving (Frenchtown to Greenwell Springs Road) | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $4,634,992.18 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $3,238,737.16 |
| 2 | 39462 | Jb James Construction Llc | $3,405,681.22 |
| 3 | 34567 | James Construction Group LLC | $3,501,741.79 |
| 4 | 12198 | Byron E. Talbot Contractor, Inc. | $3,694,699.97 |
| 5 | 52306 | Cecil Perry Improvements Llc | $3,859,738.00 |
| 6 | 48896 | Command Construction Industries LLC | $3,894,403.80 |
| 7 | 00046 | Barber Bros. Contracting Co., L.L.C | $3,947,656.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Jb James Construction Llc |
- 3 - James Construction Group LLC |
- 4 - Byron E. Talbot Contractor, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 34,000.00 | 34,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 203-01-00100 | General Excavation | 4,457 | CUYD | 3.15 | 14,039.55 | 6.00 | 26,742.00 | 7.00 | 31,199.00 | 7.00 | 31,199.00 |
| 0003 | 203-03-00100 | Embankment | 5,122 | CUYD | 8.30 | 42,512.60 | 11.00 | 56,342.00 | 8.30 | 42,512.60 | 7.50 | 38,415.00 |
| 0004 | 203-04-00300 | Nonplastic Embankment (Stone) | 395 | CUYD | 120.00 | 47,400.00 | 50.00 | 19,750.00 | 110.00 | 43,450.00 | 104.00 | 41,080.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 100 | EACH | 14.00 | 1,400.00 | 10.00 | 1,000.00 | 13.00 | 1,300.00 | 10.75 | 1,075.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 240.00 | 3,840.00 | 100.00 | 1,600.00 | 118.29 | 1,892.64 | 106.00 | 1,696.00 |
| 0007 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 4 | EACH | 300.00 | 1,200.00 | 400.00 | 1,600.00 | 240.00 | 960.00 | 450.00 | 1,800.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 830 | LNFT | 1.40 | 1,162.00 | 2.00 | 1,660.00 | 2.23 | 1,850.90 | 2.20 | 1,826.00 |
| 0009 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 3,000.00 | 6,000.00 | 2,500.00 | 5,000.00 | 1,500.00 | 3,000.00 | 2,300.00 | 4,600.00 |
| 0010 | 302-02-01060 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete) (Stone Only) | 34,063.5 | SQYD | 9.40 | 320,196.90 | 11.50 | 391,730.25 | 15.00 | 510,952.50 | 10.05 | 342,338.18 |
| 0011 | 302-02-01560 | Class II Base Course (5" Thick) (Stone or Recycled Portland Cement Concrete) (Stone Only) | 6,945.8 | SQYD | 12.00 | 83,349.60 | 9.00 | 62,512.20 | 15.00 | 104,187.00 | 13.25 | 92,031.85 |
| 0012 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 39,808.4 | SQYD | 10.20 | 406,045.68 | 8.50 | 338,371.40 | 9.50 | 378,179.80 | 11.95 | 475,710.38 |
| 0013 | 304-05-00100 | Lime Treatment (Type E) | 564.27 | TON | 65.00 | 36,677.55 | 1.00 | 564.27 | 225.00 | 126,960.75 | 250.00 | 141,067.50 |
| 0014 | 401-01-00100 | Aggregate Surface Course (Net Section) | 56.1 | CUYD | 80.00 | 4,488.00 | 70.00 | 3,927.00 | 45.00 | 2,524.50 | 76.00 | 4,263.60 |
| 0015 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 45.00 | 22,500.00 | 50.00 | 25,000.00 | 33.00 | 16,500.00 | 70.00 | 35,000.00 |
| 0016 | 502-01-00100 | Superpave Asphaltic Concrete | 1,546.4 | TON | 120.00 | 185,568.00 | 90.00 | 139,176.00 | 95.00 | 146,908.00 | 95.00 | 146,908.00 |
| 0017 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 6.6 | TON | 300.00 | 1,980.00 | 200.00 | 1,320.00 | 150.00 | 990.00 | 500.00 | 3,300.00 |
| 0018 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 31,913.4 | SQYD | 42.00 | 1,340,362.80 | 44.00 | 1,404,189.60 | 42.00 | 1,340,362.80 | 52.50 | 1,675,453.50 |
| 0019 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 100 | EACH | 80.00 | 8,000.00 | 100.00 | 10,000.00 | 100.00 | 10,000.00 | 140.00 | 14,000.00 |
| 0020 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 1,913 | LNFT | 42.00 | 80,346.00 | 50.00 | 95,650.00 | 39.00 | 74,607.00 | 40.00 | 76,520.00 |
| 0021 | 701-03-02000 | Storm Drain Pipe (Outfall) (15" PP or 18" CMP) | 164 | LNFT | 53.00 | 8,692.00 | 60.00 | 9,840.00 | 48.00 | 7,872.00 | 106.00 | 17,384.00 |
| 0022 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 30 | LNFT | 34.00 | 1,020.00 | 60.00 | 1,800.00 | 52.00 | 1,560.00 | 63.00 | 1,890.00 |
| 0023 | 702-03-00500 | Catch Basins (CB-06) | 33 | EACH | 3,500.00 | 115,500.00 | 3,400.00 | 112,200.00 | 2,500.00 | 82,500.00 | 2,500.00 | 82,500.00 |
| 0024 | 702-03-00600 | Catch Basins (CB-07) | 4 | EACH | 5,200.00 | 20,800.00 | 4,200.00 | 16,800.00 | 3,650.00 | 14,600.00 | 3,500.00 | 14,000.00 |
| 0025 | 702-03-00700 | Catch Basins (CB-08) | 2 | EACH | 6,800.00 | 13,600.00 | 5,600.00 | 11,200.00 | 6,300.00 | 12,600.00 | 6,500.00 | 13,000.00 |
| 0026 | 703-03-00100 | Perforated Pipe Underdrains | 2,220 | LNFT | 12.00 | 26,640.00 | 10.00 | 22,200.00 | 8.00 | 17,760.00 | 11.50 | 25,530.00 |
| 0027 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 20.00 | 5,000.00 | 18.00 | 4,500.00 | 19.50 | 4,875.00 | 18.00 | 4,500.00 |
| 0028 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 40.00 | 4,000.00 | 65.00 | 6,500.00 | 36.50 | 3,650.00 | 70.00 | 7,000.00 |
| 0029 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,300.00 | 9,200.00 | 2,000.00 | 8,000.00 | 2,080.00 | 8,320.00 | 2,100.00 | 8,400.00 |
| 0030 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 170.4 | SQYD | 64.00 | 10,905.60 | 44.00 | 7,497.60 | 52.00 | 8,860.80 | 50.00 | 8,520.00 |
| 0031 | 707-01-00300 | Concrete Curb (Mountable) | 9,936 | LNFT | 3.40 | 33,782.40 | 3.50 | 34,776.00 | 3.20 | 31,795.20 | 6.00 | 59,616.00 |
| 0032 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 80,000.00 | 80,000.00 | 8,300.00 | 8,300.00 | 5,000.00 | 5,000.00 |
| 0033 | 717-01-00100 | Seeding | 1,000 | LB | 7.50 | 7,500.00 | 7.00 | 7,000.00 | 7.00 | 7,000.00 | 7.50 | 7,500.00 |
| 0034 | 718-01-00100 | Fertilizer | 10,000 | LB | 0.45 | 4,500.00 | 0.65 | 6,500.00 | 0.65 | 6,500.00 | 0.70 | 7,000.00 |
| 0035 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5,000.00 | 5,000.00 | 7,000.00 | 7,000.00 | 10,000.00 | 10,000.00 | 8,500.00 | 8,500.00 |
| 0036 | 726-01-00100 | Bedding Material | 422 | CUYD | 60.00 | 25,320.00 | 55.00 | 23,210.00 | 75.00 | 31,650.00 | 65.00 | 27,430.00 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 270,000.00 | 270,000.00 | 340,000.00 | 340,000.00 | 350,000.00 | 350,000.00 | 190,000.00 | 190,000.00 |
| 0038 | 729-16-00100 | Object Marker Assembly (Type 1) | 4 | EACH | 83.00 | 332.00 | 70.00 | 280.00 | 65.00 | 260.00 | 125.00 | 500.00 |
| 0039 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 700 | EACH | 11.00 | 7,700.00 | 10.00 | 7,000.00 | 10.00 | 7,000.00 | 11.00 | 7,700.00 |
| 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 437 | EACH | 5.80 | 2,534.60 | 5.00 | 2,185.00 | 5.00 | 2,185.00 | 5.30 | 2,316.10 |
| 0041 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 235 | LNFT | 1.50 | 352.50 | 1.00 | 235.00 | 1.00 | 235.00 | 1.05 | 246.75 |
| 0042 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 39 | LNFT | 5.50 | 214.50 | 5.00 | 195.00 | 5.00 | 195.00 | 5.30 | 206.70 |
| 0043 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.345 | MILE | 2,800.00 | 12,166.00 | 2,900.00 | 12,600.50 | 2,900.00 | 12,600.50 | 3,075.00 | 13,360.88 |
| 0044 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.172 | MILE | 940.00 | 2,041.68 | 1,000.00 | 2,172.00 | 1,000.00 | 2,172.00 | 1,050.00 | 2,280.60 |
| 0045 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.134 | MILE | 3,300.00 | 442.20 | 3,100.00 | 415.40 | 3,200.00 | 428.80 | 3,395.00 | 454.93 |
| 0046 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 235.00 | 705.00 | 180.00 | 540.00 | 180.00 | 540.00 | 190.00 | 570.00 |
| 0047 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 235.00 | 470.00 | 180.00 | 360.00 | 180.00 | 360.00 | 190.00 | 380.00 |
| 0048 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 250.00 | 750.00 | 180.00 | 540.00 | 195.00 | 585.00 | 210.00 | 630.00 |
| 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 60,000.00 | 60,000.00 | 24,000.00 | 24,000.00 | 40,000.00 | 40,000.00 |
| CONTRACTOR TOTAL | 3,238,737.16 | 3,405,681.22 | 3,501,741.79 | 3,694,699.97 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Cecil Perry Improvements Llc |
- 6 - Command Construction Industries LLC |
- 7 - Barber Bros. Contracting Co., L.L.C |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 7,000.00 | 7,000.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 |
| 0002 | 203-01-00100 | General Excavation | 4,457 | CUYD | 8.64 | 38,508.48 | 5.00 | 22,285.00 | 8.00 | 35,656.00 |
| 0003 | 203-03-00100 | Embankment | 5,122 | CUYD | 19.75 | 101,159.50 | 10.00 | 51,220.00 | 10.00 | 51,220.00 |
| 0004 | 203-04-00300 | Nonplastic Embankment (Stone) | 395 | CUYD | 93.16 | 36,798.20 | 80.00 | 31,600.00 | 125.00 | 49,375.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 100 | EACH | 12.00 | 1,200.00 | 15.00 | 1,500.00 | 20.00 | 2,000.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 116.00 | 1,856.00 | 150.00 | 2,400.00 | 150.00 | 2,400.00 |
| 0007 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 4 | EACH | 610.00 | 2,440.00 | 250.00 | 1,000.00 | 800.00 | 3,200.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 830 | LNFT | 2.04 | 1,693.20 | 3.00 | 2,490.00 | 2.00 | 1,660.00 |
| 0009 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 2,964.00 | 5,928.00 | 2,500.00 | 5,000.00 | 5,000.00 | 10,000.00 |
| 0010 | 302-02-01060 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete) (Stone Only) | 34,063.5 | SQYD | 10.50 | 357,666.75 | 8.00 | 272,508.00 | 12.00 | 408,762.00 |
| 0011 | 302-02-01560 | Class II Base Course (5" Thick) (Stone or Recycled Portland Cement Concrete) (Stone Only) | 6,945.8 | SQYD | 13.20 | 91,684.56 | 8.00 | 55,566.40 | 17.50 | 121,551.50 |
| 0012 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 39,808.4 | SQYD | 6.45 | 256,764.18 | 10.00 | 398,084.00 | 12.00 | 477,700.80 |
| 0013 | 304-05-00100 | Lime Treatment (Type E) | 564.27 | TON | 278.00 | 156,867.06 | 100.00 | 56,427.00 | 260.00 | 146,710.20 |
| 0014 | 401-01-00100 | Aggregate Surface Course (Net Section) | 56.1 | CUYD | 87.00 | 4,880.70 | 100.00 | 5,610.00 | 100.00 | 5,610.00 |
| 0015 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 69.92 | 34,960.00 | 10.00 | 5,000.00 | 0.00 | 0.00 |
| 0016 | 502-01-00100 | Superpave Asphaltic Concrete | 1,546.4 | TON | 120.00 | 185,568.00 | 125.00 | 193,300.00 | 90.00 | 139,176.00 |
| 0017 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 6.6 | TON | 260.00 | 1,716.00 | 400.00 | 2,640.00 | 360.00 | 2,376.00 |
| 0018 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 31,913.4 | SQYD | 57.00 | 1,819,063.80 | 60.00 | 1,914,804.00 | 50.00 | 1,595,670.00 |
| 0019 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 100 | EACH | 81.00 | 8,100.00 | 250.00 | 25,000.00 | 120.00 | 12,000.00 |
| 0020 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 1,913 | LNFT | 38.00 | 72,694.00 | 50.00 | 95,650.00 | 30.00 | 57,390.00 |
| 0021 | 701-03-02000 | Storm Drain Pipe (Outfall) (15" PP or 18" CMP) | 164 | LNFT | 41.00 | 6,724.00 | 70.00 | 11,480.00 | 45.00 | 7,380.00 |
| 0022 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 30 | LNFT | 34.00 | 1,020.00 | 50.00 | 1,500.00 | 50.00 | 1,500.00 |
| 0023 | 702-03-00500 | Catch Basins (CB-06) | 33 | EACH | 3,757.00 | 123,981.00 | 3,250.00 | 107,250.00 | 3,000.00 | 99,000.00 |
| 0024 | 702-03-00600 | Catch Basins (CB-07) | 4 | EACH | 4,690.00 | 18,760.00 | 4,000.00 | 16,000.00 | 4,600.00 | 18,400.00 |
| 0025 | 702-03-00700 | Catch Basins (CB-08) | 2 | EACH | 7,760.00 | 15,520.00 | 7,500.00 | 15,000.00 | 7,500.00 | 15,000.00 |
| 0026 | 703-03-00100 | Perforated Pipe Underdrains | 2,220 | LNFT | 11.50 | 25,530.00 | 10.00 | 22,200.00 | 10.00 | 22,200.00 |
| 0027 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 18.50 | 4,625.00 | 17.00 | 4,250.00 | 30.00 | 7,500.00 |
| 0028 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 70.00 | 7,000.00 | 65.00 | 6,500.00 | 75.00 | 7,500.00 |
| 0029 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 1,950.00 | 7,800.00 | 3,000.00 | 12,000.00 |
| 0030 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 170.4 | SQYD | 47.62 | 8,114.45 | 45.00 | 7,668.00 | 90.00 | 15,336.00 |
| 0031 | 707-01-00300 | Concrete Curb (Mountable) | 9,936 | LNFT | 7.25 | 72,036.00 | 5.00 | 49,680.00 | 7.00 | 69,552.00 |
| 0032 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,990.00 | 9,990.00 | 1,000.00 | 1,000.00 | 25,000.00 | 25,000.00 |
| 0033 | 717-01-00100 | Seeding | 1,000 | LB | 8.00 | 8,000.00 | 2.00 | 2,000.00 | 12.00 | 12,000.00 |
| 0034 | 718-01-00100 | Fertilizer | 10,000 | LB | 0.75 | 7,500.00 | 2.00 | 20,000.00 | 1.00 | 10,000.00 |
| 0035 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 14,943.00 | 14,943.00 | 1,000.00 | 1,000.00 | 10,000.00 | 10,000.00 |
| 0036 | 726-01-00100 | Bedding Material | 422 | CUYD | 90.26 | 38,089.72 | 75.00 | 31,650.00 | 30.00 | 12,660.00 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 250,999.70 | 250,999.70 | 400,000.00 | 400,000.00 | 390,000.00 | 390,000.00 |
| 0038 | 729-16-00100 | Object Marker Assembly (Type 1) | 4 | EACH | 72.00 | 288.00 | 65.00 | 260.00 | 100.00 | 400.00 |
| 0039 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 700 | EACH | 10.50 | 7,350.00 | 10.00 | 7,000.00 | 12.00 | 8,400.00 |
| 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 437 | EACH | 5.50 | 2,403.50 | 5.00 | 2,185.00 | 6.50 | 2,840.50 |
| 0041 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 235 | LNFT | 1.10 | 258.50 | 1.00 | 235.00 | 2.00 | 470.00 |
| 0042 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 39 | LNFT | 5.50 | 214.50 | 5.00 | 195.00 | 6.00 | 234.00 |
| 0043 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.345 | MILE | 3,200.00 | 13,904.00 | 3,000.00 | 13,035.00 | 3,000.00 | 13,035.00 |
| 0044 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.172 | MILE | 1,100.00 | 2,389.20 | 1,100.00 | 2,389.20 | 1,000.00 | 2,172.00 |
| 0045 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.134 | MILE | 3,500.00 | 469.00 | 3,300.00 | 442.20 | 3,500.00 | 469.00 |
| 0046 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 190.00 | 570.00 | 200.00 | 600.00 | 250.00 | 750.00 |
| 0047 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 190.00 | 380.00 | 200.00 | 400.00 | 250.00 | 500.00 |
| 0048 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 210.00 | 630.00 | 200.00 | 600.00 | 300.00 | 900.00 |
| 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 22,700.00 | 22,700.00 | 10,000.00 | 10,000.00 | 40,000.00 | 40,000.00 |
| CONTRACTOR TOTAL | 3,859,738.00 | 3,894,403.80 | 3,947,656.00 | |||||||