Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 742-09-0109 | |
| Parish: Caddo | |
| Routes: | |
| Description: WOOLWORTH ROAD OVERLAY | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $880,095.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 17464 | Benton & Brown, LLC. | $742,644.30 |
| 2 | 36374 | Best-Yet Builders, LLC | $832,195.65 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Benton & Brown, LLC. |
- 2 - Best-Yet Builders, LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 401-01-00100 | Aggregate Surface Course (Net Section) (RAP material only) | 217 | CUYD | 70.00 | 15,190.00 | 160.00 | 34,720.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 5,394 | TON | 90.00 | 485,460.00 | 90.00 | 485,460.00 |
| 0003 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,083 | SQYD | 6.00 | 12,498.00 | 2.50 | 5,207.50 |
| 0004 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 2,900 | SQYD | 52.00 | 150,800.00 | 75.00 | 217,500.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 7,500.00 | 7,500.00 |
| 0006 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1 | MILE | 500.00 | 500.00 | 800.00 | 800.00 |
| 0007 | 727-01-00100 | Mobilization | 1 | LUMP | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 |
| 0008 | 731-02-00100 | Reflectorized Raised Pavement Markers | 619 | EACH | 5.10 | 3,156.90 | 4.85 | 3,002.15 |
| 0009 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 14 | LNFT | 10.50 | 147.00 | 10.00 | 140.00 |
| 0010 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 11.71 | MILE | 1,680.00 | 19,672.80 | 1,600.00 | 18,736.00 |
| 0011 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 1.24 | MILE | 790.00 | 979.60 | 750.00 | 930.00 |
| 0012 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 160.00 | 160.00 | 150.00 | 150.00 |
| 0013 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 160.00 | 160.00 | 150.00 | 150.00 |
| 0014 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 210.00 | 420.00 | 200.00 | 400.00 |
| 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,500.00 | 3,500.00 | 10,000.00 | 10,000.00 |
| 0016 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 12,500.00 | 12,500.00 |
| CONTRACTOR TOTAL | 742,644.30 | 832,195.65 | ||||||