Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 742-08-0007 | |
| Parish: Bossier | |
| Routes: | |
| Description: STOCKWELL ROAD (2.1 MILES NORTH FROM US 80 INTERSECTION) | |
| Type Const: GRADING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CEMENT TREATED BASE COURSE, LIME TREATMENT, AND RELATED WORK | |
| Estimated Construction Cost: $1,657,504.76 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, LLC | $1,466,145.50 |
| 2 | 17464 | Benton & Brown, LLC. | $1,530,728.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, LLC |
- 2 - Benton & Brown, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 125.33 | SQYD | 10.00 | 1,253.30 | 50.00 | 6,266.50 |
| 0002 | 202-02-38500 | Removal of Surfacing and Stablized Base | 29,428.3 | SQYD | 3.00 | 88,284.90 | 5.00 | 147,141.50 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,800 | CUYD | 12.00 | 21,600.00 | 15.00 | 27,000.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 800 | CUYD | 12.00 | 9,600.00 | 20.00 | 16,000.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 60 | EACH | 10.00 | 600.00 | 20.00 | 1,200.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 500 | LNFT | 2.50 | 1,250.00 | 2.75 | 1,375.00 |
| 0007 | 303-01-00300 | In-Place Cement Stabilzed Base Course (10" Thick) | 30,753 | SQYD | 8.00 | 246,024.00 | 9.75 | 299,841.75 |
| 0008 | 304-05-00100 | Lime Treatment (Type E) | 30 | TON | 200.00 | 6,000.00 | 500.00 | 15,000.00 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 13 | CUYD | 100.00 | 1,300.00 | 70.00 | 910.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 10,272.1 | TON | 92.00 | 945,033.20 | 83.00 | 852,584.30 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 55.2 | TON | 100.00 | 5,520.00 | 165.00 | 9,108.00 |
| 0012 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 62.5 | LNFT | 40.00 | 2,500.00 | 42.00 | 2,625.00 |
| 0013 | 704-03-00100 | Blocked Out Guard Rail | 100 | LNFT | 22.00 | 2,200.00 | 23.00 | 2,300.00 |
| 0014 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 12.5 | LNFT | 110.00 | 1,375.00 | 115.00 | 1,437.50 |
| 0015 | 704-11-00100 | Guard Rail End Treatment (Flared) | 2 | EACH | 2,300.00 | 4,600.00 | 2,400.00 | 4,800.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 40,000.00 | 40,000.00 |
| 0017 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,000 | LNFT | 0.25 | 250.00 | 0.27 | 270.00 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.311 | MILE | 400.00 | 2,524.40 | 420.00 | 2,650.62 |
| 0019 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 3 | EACH | 25.00 | 75.00 | 26.00 | 78.00 |
| 0020 | 713-05-00200 | Temporary Pavement Legends & Symbols (Double Arrow) | 3 | EACH | 35.00 | 105.00 | 37.00 | 111.00 |
| 0021 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 3 | EACH | 30.00 | 90.00 | 32.00 | 96.00 |
| 0022 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 100.00 | 200.00 | 105.00 | 210.00 |
| 0023 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 262 | EACH | 1.35 | 353.70 | 1.50 | 393.00 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 7.6 | TON | 900.00 | 6,840.00 | 1,235.00 | 9,386.00 |
| 0025 | 717-01-00100 | Seeding | 114 | LB | 8.00 | 912.00 | 10.00 | 1,140.00 |
| 0026 | 718-01-00100 | Fertilizer | 3,800 | LB | 0.50 | 1,900.00 | 0.55 | 2,090.00 |
| 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 40,000.00 | 40,000.00 |
| 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 262 | EACH | 4.85 | 1,270.70 | 5.35 | 1,401.70 |
| 0029 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,000 | LNFT | 0.85 | 850.00 | 0.95 | 950.00 |
| 0030 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 50 | LNFT | 5.00 | 250.00 | 5.50 | 275.00 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 6.311 | MILE | 2,300.00 | 14,515.30 | 2,530.00 | 15,966.83 |
| 0032 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 3 | EACH | 205.00 | 615.00 | 225.00 | 675.00 |
| 0033 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 150.00 | 450.00 | 165.00 | 495.00 |
| 0034 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 150.00 | 450.00 | 165.00 | 495.00 |
| 0035 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 400.00 | 800.00 | 440.00 | 880.00 |
| 0036 | 735-01-00100 | Mailboxes | 50 | EACH | 50.00 | 2,500.00 | 1.10 | 55.00 |
| 0037 | 735-02-00100 | Mailbox Supports (Single) | 50 | EACH | 75.00 | 3,750.00 | 120.00 | 6,000.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 7,000.00 | 7,000.00 |
| 0039 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 6,768 | INLF | 3.00 | 20,304.00 | 1.85 | 12,520.80 |
| CONTRACTOR TOTAL | 1,466,145.50 | 1,530,728.50 | ||||||