Bid Tabulations
Letting of
10/27/2010
LA DOTD Headquarters
| Lead Project: 737-99-1102 | |
| Parish: St. John, Lincoln, Richland, Statewide, St. Charles, Ascension, Jefferson, Iberville, Avoyelles | |
| Routes: | |
| Description: INTERSTATE SURFACE ABRASION | |
| Type Const: SURFACE ABRASION AND ALL RELATED WORK | |
| Estimated Construction Cost: $3,734,495.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 27043 | Jack B. Harper Contractor, Inc. | $4,159,495.00 |
| 2 | 35849 | T.L. Construction Inc | $5,376,950.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Jack B. Harper Contractor, Inc. |
- 2 - T.L. Construction Inc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 300,000.00 | 300,000.00 | 500,000.00 | 500,000.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 775,000.00 | 775,000.00 |
| 0003 | NS-507-00002 | Flexible Pavement Surface Abrasion | 23,091 | SQYD | 1.25 | 28,863.75 | 2.00 | 46,182.00 |
| 0004 | NS-602-00007 | Rigid Pavement Surface Abrasion | 1,524,725 | SQYD | 2.25 | 3,430,631.25 | 2.66 | 4,055,768.50 |
| CONTRACTOR TOTAL | 4,159,495.00 | 5,376,950.50 | ||||||