LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 713-52-0104
Parish: St. Tammany
Routes:
Description: FITZGERALD CHURCH ROAD BRIDGE
Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGE AND RELATED WORK
Estimated Construction Cost: $405,385.60


RankLicenseBidderConstruction Bid
1 09090 Guinn Brothers, LLC. $386,489.30
2 55564 Coastal Industries Llc $451,291.90
3 51413 Iverstine & Campbell LLC $459,449.70
4 39462 Jb James Construction Llc $514,139.50
5 52550 Gibbs & Register Inc $585,479.50
6 12069 B & K Construction Co. $596,659.40


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Guinn Brothers, LLC.
- 2 -
Coastal Industries Llc
- 3 -
Iverstine & Campbell LLC
- 4 -
Jb James Construction Llc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 10,000.00 10,000.00 15,000.00 15,000.00 2,223.00 2,223.00 70,000.00 70,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 4,000.00 4,000.00 8,500.00 8,500.00 250.00 250.00 3,000.00 3,000.00
0003 202-02-04000 Removal of Bridge (STA 105+18.87;26' X 40' TIMBER BRIDGE) 1      EACH 6,000.00 6,000.00 20,000.00 20,000.00 7,125.00 7,125.00 10,000.00 10,000.00
0004 202-02-38500 Removal of Surfacing and Stablized Base 825.7    SQYD 4.00 3,302.80 7.00 5,779.90 5.00 4,128.50 5.00 4,128.50
0005 203-05-00100 Excavation and Embankment 1      LUMP 28,000.00 28,000.00 25,000.00 25,000.00 18,250.00 18,250.00 50,000.00 50,000.00
0006 204-02-00100 Temporary Hay or Straw Bales 15      EACH 10.00 150.00 15.00 225.00 25.00 375.00 12.00 180.00
0007 204-03-00100 Temporary Slope Drains 180      LNFT 0.00 0.00 15.00 2,700.00 15.00 2,700.00 15.00 2,700.00
0008 204-05-00100 Temporary Sediment Check Dams (Hay) 3      EACH 100.00 300.00 175.00 525.00 186.00 558.00 120.00 360.00
0009 204-06-00100 Temporary Silt Fencing 760      LNFT 3.00 2,280.00 2.50 1,900.00 2.50 1,900.00 2.00 1,520.00
0010 302-01-00100 Class II Base Course 235.3    CUYD 85.00 20,000.50 100.00 23,530.00 99.00 23,294.70 80.00 18,824.00
0011 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 11      CUYD 100.00 1,100.00 40.00 440.00 105.00 1,155.00 100.00 1,100.00
0012 502-01-00100 Superpave Asphaltic Concrete 184.3    TON 200.00 36,860.00 170.00 31,331.00 272.00 50,129.60 200.00 36,860.00
0013 704-03-00100 Blocked Out Guard Rail 50      LNFT 22.00 1,100.00 18.00 900.00 22.50 1,125.00 18.00 900.00
0014 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 75.00 7,500.00 70.00 7,000.00 80.30 8,030.00 60.00 6,000.00
0015 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,500.00 10,000.00 2,250.00 9,000.00 2,409.00 9,636.00 2,000.00 8,000.00
0016 711-01-04000 Riprap (55 lb, 18" Thick) 316      SQYD 80.00 25,280.00 60.00 18,960.00 101.50 32,074.00 65.00 20,540.00
0017 711-04-00100 Geotextile Fabric 316      SQYD 5.00 1,580.00 3.00 948.00 2.50 790.00 2.00 632.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 6,500.00 6,500.00 10,000.00 10,000.00 7,657.00 7,657.00 20,000.00 20,000.00
0019 716-01-00100 Mulch (Vegetative) 0.8    TON 1,500.00 1,200.00 900.00 720.00 988.00 790.40 1,500.00 1,200.00
0020 717-01-00100 Seeding 17      LB 15.00 255.00 15.00 255.00 12.50 212.50 15.00 255.00
0021 718-01-00100 Fertilizer 380      LB 1.00 380.00 2.10 798.00 1.30 494.00 1.00 380.00
0022 727-01-00100 Mobilization 1      LUMP 25,000.00 25,000.00 40,000.00 40,000.00 24,083.00 24,083.00 50,000.00 50,000.00
0023 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 100.00 400.00 95.00 380.00 93.00 372.00 80.00 320.00
0024 740-01-00100 Construction Layout 1      LUMP 4,000.00 4,000.00 12,000.00 12,000.00 4,125.00 4,125.00 8,000.00 8,000.00
0025 804-01-00200 Precast Concrete Piles (14") 855      LNFT 60.00 51,300.00 60.00 51,300.00 91.00 77,805.00 68.00 58,140.00
0026 804-12-00100 Loading Permanent Piles 1      EACH 1.00 1.00 100.00 100.00 6,175.00 6,175.00 100.00 100.00
0027 805-10-02360 Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Precast) 4      SPAN 30,000.00 120,000.00 35,000.00 140,000.00 37,693.00 150,772.00 32,000.00 128,000.00
0028 NS-800-00040 Concrete Approach Slabs (28' CLR RDWY, 90DEG CROSSING) 2      EACH 10,000.00 20,000.00 12,000.00 24,000.00 11,610.00 23,220.00 6,500.00 13,000.00
                         
    CONTRACTOR TOTAL       386,489.30   451,291.90   459,449.70   514,139.50



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Gibbs & Register Inc
- 6 -
B & K Construction Co.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 8,000.00 8,000.00 25,000.00 25,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 100.00 100.00 25,000.00 25,000.00
0003 202-02-04000 Removal of Bridge (STA 105+18.87;26' X 40' TIMBER BRIDGE) 1      EACH 64,800.00 64,800.00 61,500.00 61,500.00
0004 202-02-38500 Removal of Surfacing and Stablized Base 825.7    SQYD 10.00 8,257.00 12.00 9,908.40
0005 203-05-00100 Excavation and Embankment 1      LUMP 6,000.00 6,000.00 40,000.00 40,000.00
0006 204-02-00100 Temporary Hay or Straw Bales 15      EACH 25.00 375.00 50.00 750.00
0007 204-03-00100 Temporary Slope Drains 180      LNFT 10.00 1,800.00 12.00 2,160.00
0008 204-05-00100 Temporary Sediment Check Dams (Hay) 3      EACH 200.00 600.00 200.00 600.00
0009 204-06-00100 Temporary Silt Fencing 760      LNFT 2.00 1,520.00 3.00 2,280.00
0010 302-01-00100 Class II Base Course 235.3    CUYD 85.00 20,000.50 70.00 16,471.00
0011 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 11      CUYD 250.00 2,750.00 100.00 1,100.00
0012 502-01-00100 Superpave Asphaltic Concrete 184.3    TON 200.00 36,860.00 190.00 35,017.00
0013 704-03-00100 Blocked Out Guard Rail 50      LNFT 20.00 1,000.00 30.00 1,500.00
0014 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 65.00 6,500.00 70.00 7,000.00
0015 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,100.00 8,400.00 2,000.00 8,000.00
0016 711-01-04000 Riprap (55 lb, 18" Thick) 316      SQYD 85.00 26,860.00 80.00 25,280.00
0017 711-04-00100 Geotextile Fabric 316      SQYD 5.00 1,580.00 3.00 948.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 7,500.00 7,500.00 40,000.00 40,000.00
0019 716-01-00100 Mulch (Vegetative) 0.8    TON 1,500.00 1,200.00 1,500.00 1,200.00
0020 717-01-00100 Seeding 17      LB 16.00 272.00 15.00 255.00
0021 718-01-00100 Fertilizer 380      LB 1.00 380.00 1.00 380.00
0022 727-01-00100 Mobilization 1      LUMP 55,000.00 55,000.00 25,000.00 25,000.00
0023 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 100.00 400.00 75.00 300.00
0024 740-01-00100 Construction Layout 1      LUMP 15,000.00 15,000.00 40,000.00 40,000.00
0025 804-01-00200 Precast Concrete Piles (14") 855      LNFT 115.00 98,325.00 62.00 53,010.00
0026 804-12-00100 Loading Permanent Piles 1      EACH 22,000.00 22,000.00 40,000.00 40,000.00
0027 805-10-02360 Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Precast) 4      SPAN 40,000.00 160,000.00 30,000.00 120,000.00
0028 NS-800-00040 Concrete Approach Slabs (28' CLR RDWY, 90DEG CROSSING) 2      EACH 15,000.00 30,000.00 7,000.00 14,000.00
                 
    CONTRACTOR TOTAL       585,479.50   596,659.40