Bid Tabulations
Letting of
03/30/2011
LA DOTD Headquarters
| Lead Project: 713-46-0111 | |
| Parish: St. Helena | |
| Routes: | |
| Description: STONE ROAD BRIDGE OVER HOFFMAN CREEK | |
| Type Const: GRADING, BRIDGE REMOVAL, DRAINAGE STRUCTURE, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK | |
| Estimated Construction Cost: $221,706.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 41947 | M & M Enterprises of Bastrop, LLC | $197,900.75 |
| 2 | 51413 | Iverstine & Campbell LLC | $198,258.21 |
| 3 | 25088 | RCS Contractors, Inc. | $216,026.06 |
| 4 | 09090 | Guinn Brothers, LLC. | $216,767.50 |
| 5 | 16724 | Stranco, Inc. | $226,505.00 |
| 6 | 05693 | Industrial Enterprises, Inc. | $233,940.69 |
| 7 | 45004 | Bondco LLC | $248,764.00 |
| 8 | 12198 | Byron E. Talbot Contractor, Inc. | $254,516.25 |
| 9 | 42466 | Beard Construction Group LLC | $255,063.50 |
| 10 | 01012 | Cecil D. Gassiott, LLC | $340,160.20 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - M & M Enterprises of Bastrop, LLC |
- 2 - Iverstine & Campbell LLC |
- 3 - RCS Contractors, Inc. |
- 4 - Guinn Brothers, LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,000.00 | 3,000.00 | 4,600.00 | 4,600.00 | 3,600.00 | 3,600.00 | 8,000.00 | 8,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 14+95; 22' X 39' TIMBER BRIDGE) | 1 | EACH | 3,000.00 | 3,000.00 | 2,100.00 | 2,100.00 | 15,000.00 | 15,000.00 | 4,000.00 | 4,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 8,500.00 | 8,500.00 | 2,300.00 | 2,300.00 | 19,450.00 | 19,450.00 | 5,000.00 | 5,000.00 |
| 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 100.00 | 400.00 | 236.00 | 944.00 | 220.00 | 880.00 | 100.00 | 400.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 1.00 | 300.00 | 4.00 | 1,200.00 | 3.85 | 1,155.00 | 3.00 | 900.00 |
| 0006 | 302-01-00100 | Class II Base Course | 81.6 | CUYD | 100.00 | 8,160.00 | 117.00 | 9,547.20 | 167.00 | 13,627.20 | 95.00 | 7,752.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 80.00 | 720.00 | 96.00 | 864.00 | 167.00 | 1,503.00 | 100.00 | 900.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 63.1 | TON | 300.00 | 18,930.00 | 265.50 | 16,753.05 | 250.00 | 15,775.00 | 250.00 | 15,775.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 300 | LNFT | 6.00 | 1,800.00 | 13.00 | 3,900.00 | 13.20 | 3,960.00 | 10.00 | 3,000.00 |
| 0010 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 69 | SQYD | 60.00 | 4,140.00 | 90.00 | 6,210.00 | 45.00 | 3,105.00 | 75.00 | 5,175.00 |
| 0011 | 711-04-00100 | Geotextile Fabric | 69 | SQYD | 0.75 | 51.75 | 2.95 | 203.55 | 1.00 | 69.00 | 5.00 | 345.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,300.00 | 4,300.00 | 3,500.00 | 3,500.00 | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 |
| 0013 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 2,500.00 | 750.00 | 4,700.00 | 1,410.00 | 4,400.00 | 1,320.00 | 3,500.00 | 1,050.00 |
| 0014 | 717-01-00100 | Seeding | 7 | LB | 30.00 | 210.00 | 23.00 | 161.00 | 22.00 | 154.00 | 15.00 | 105.00 |
| 0015 | 718-01-00100 | Fertilizer | 150 | LB | 2.00 | 300.00 | 5.00 | 750.00 | 5.00 | 750.00 | 1.00 | 150.00 |
| 0016 | 726-01-00100 | Bedding Material | 232.3 | CUYD | 90.00 | 20,907.00 | 41.30 | 9,593.99 | 0.01 | 2.32 | 90.00 | 20,907.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 12,500.00 | 12,500.00 |
| 0018 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 | 90.00 | 360.00 | 50.00 | 200.00 | 100.00 | 400.00 |
| 0019 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,750.00 | 4,750.00 | 4,000.00 | 4,000.00 | 3,000.00 | 3,000.00 | 4,000.00 | 4,000.00 |
| 0020 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 28.53 | CUYD | 850.00 | 24,250.50 | 950.00 | 27,103.50 | 1,350.00 | 38,515.50 | 1,200.00 | 34,236.00 |
| 0021 | 805-12-03040 | Reinforced Concrete Box Culverts (8' x 6') | 152 | LNFT | 510.00 | 77,520.00 | 593.00 | 90,136.00 | 520.52 | 79,119.04 | 535.00 | 81,320.00 |
| 0022 | 806-01-00100 | Deformed Reinforcing Steel | 2,341 | LB | 1.50 | 3,511.50 | 1.12 | 2,621.92 | 1.00 | 2,341.00 | 2.50 | 5,852.50 |
| CONTRACTOR TOTAL | 197,900.75 | 198,258.21 | 216,026.06 | 216,767.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Stranco, Inc. |
- 6 - Industrial Enterprises, Inc. |
- 7 - Bondco LLC |
- 8 - Byron E. Talbot Contractor, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 2,500.00 | 2,500.00 | 5,750.00 | 5,750.00 | 2,500.00 | 2,500.00 | 4,000.00 | 4,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 14+95; 22' X 39' TIMBER BRIDGE) | 1 | EACH | 2,500.00 | 2,500.00 | 5,750.00 | 5,750.00 | 3,000.00 | 3,000.00 | 4,500.00 | 4,500.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 3,500.00 | 3,500.00 | 23,000.00 | 23,000.00 | 6,000.00 | 6,000.00 | 10,000.00 | 10,000.00 |
| 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 100.00 | 400.00 | 200.00 | 800.00 | 125.00 | 500.00 | 215.00 | 860.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 2.00 | 600.00 | 1.73 | 519.00 | 3.00 | 900.00 | 3.25 | 975.00 |
| 0006 | 302-01-00100 | Class II Base Course | 81.6 | CUYD | 100.00 | 8,160.00 | 132.25 | 10,791.60 | 90.00 | 7,344.00 | 88.00 | 7,180.80 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 60.00 | 540.00 | 138.00 | 1,242.00 | 85.00 | 765.00 | 100.00 | 900.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 63.1 | TON | 275.00 | 17,352.50 | 178.25 | 11,247.58 | 250.00 | 15,775.00 | 265.00 | 16,721.50 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 300 | LNFT | 11.00 | 3,300.00 | 6.50 | 1,950.00 | 8.00 | 2,400.00 | 12.75 | 3,825.00 |
| 0010 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 69 | SQYD | 75.00 | 5,175.00 | 69.00 | 4,761.00 | 80.00 | 5,520.00 | 67.00 | 4,623.00 |
| 0011 | 711-04-00100 | Geotextile Fabric | 69 | SQYD | 2.00 | 138.00 | 2.88 | 198.72 | 7.00 | 483.00 | 10.00 | 690.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,500.00 | 5,500.00 | 4,600.00 | 4,600.00 | 7,000.00 | 7,000.00 | 3,750.00 | 3,750.00 |
| 0013 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 1,000.00 | 300.00 | 2,000.00 | 600.00 | 2,000.00 | 600.00 | 4,250.00 | 1,275.00 |
| 0014 | 717-01-00100 | Seeding | 7 | LB | 10.00 | 70.00 | 30.00 | 210.00 | 20.00 | 140.00 | 21.25 | 148.75 |
| 0015 | 718-01-00100 | Fertilizer | 150 | LB | 3.00 | 450.00 | 2.00 | 300.00 | 4.00 | 600.00 | 4.80 | 720.00 |
| 0016 | 726-01-00100 | Bedding Material | 232.3 | CUYD | 25.00 | 5,807.50 | 111.55 | 25,913.07 | 80.00 | 18,584.00 | 100.00 | 23,230.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 8,500.00 | 8,500.00 | 5,750.00 | 5,750.00 | 14,000.00 | 14,000.00 | 25,000.00 | 25,000.00 |
| 0018 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 150.00 | 600.00 | 143.75 | 575.00 | 125.00 | 500.00 | 132.00 | 528.00 |
| 0019 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 5,750.00 | 5,750.00 | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 |
| 0020 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 28.53 | CUYD | 1,000.00 | 28,530.00 | 1,700.43 | 48,513.27 | 1,000.00 | 28,530.00 | 1,030.00 | 29,385.90 |
| 0021 | 805-12-03040 | Reinforced Concrete Box Culverts (8' x 6') | 152 | LNFT | 825.00 | 125,400.00 | 471.51 | 71,669.52 | 800.00 | 121,600.00 | 705.00 | 107,160.00 |
| 0022 | 806-01-00100 | Deformed Reinforcing Steel | 2,341 | LB | 2.00 | 4,682.00 | 1.73 | 4,049.93 | 3.00 | 7,023.00 | 1.30 | 3,043.30 |
| CONTRACTOR TOTAL | 226,505.00 | 233,940.69 | 248,764.00 | 254,516.25 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Beard Construction Group LLC |
- 10 - Cecil D. Gassiott, LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 5,000.00 | 5,000.00 | 25,000.00 | 25,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 14+95; 22' X 39' TIMBER BRIDGE) | 1 | EACH | 10,000.00 | 10,000.00 | 18,000.00 | 18,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 60.00 | 240.00 | 350.00 | 1,400.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 3.50 | 1,050.00 | 7.50 | 2,250.00 |
| 0006 | 302-01-00100 | Class II Base Course | 81.6 | CUYD | 100.00 | 8,160.00 | 100.00 | 8,160.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 39.00 | 351.00 | 85.00 | 765.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 63.1 | TON | 300.00 | 18,930.00 | 400.00 | 25,240.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 300 | LNFT | 13.00 | 3,900.00 | 18.50 | 5,550.00 |
| 0010 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 69 | SQYD | 60.00 | 4,140.00 | 70.00 | 4,830.00 |
| 0011 | 711-04-00100 | Geotextile Fabric | 69 | SQYD | 2.00 | 138.00 | 6.00 | 414.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 4,000.00 | 4,000.00 |
| 0013 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 5,000.00 | 1,500.00 | 1,800.00 | 540.00 |
| 0014 | 717-01-00100 | Seeding | 7 | LB | 100.00 | 700.00 | 25.00 | 175.00 |
| 0015 | 718-01-00100 | Fertilizer | 150 | LB | 10.00 | 1,500.00 | 2.00 | 300.00 |
| 0016 | 726-01-00100 | Bedding Material | 232.3 | CUYD | 90.00 | 20,907.00 | 100.00 | 23,230.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 48,000.00 | 48,000.00 |
| 0018 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 300.00 | 1,200.00 | 125.00 | 500.00 |
| 0019 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 |
| 0020 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 28.53 | CUYD | 1,500.00 | 42,795.00 | 1,860.00 | 53,065.80 |
| 0021 | 805-12-03040 | Reinforced Concrete Box Culverts (8' x 6') | 152 | LNFT | 600.00 | 91,200.00 | 651.70 | 99,058.40 |
| 0022 | 806-01-00100 | Deformed Reinforcing Steel | 2,341 | LB | 2.50 | 5,852.50 | 2.00 | 4,682.00 |
| CONTRACTOR TOTAL | 255,063.50 | 340,160.20 | ||||||