LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 713-43-0112
Parish: Sabine
Routes:
Description: MARTHAVILLE ROAD BRIDGE OVER BAYOU DUPONT
Type Const: CLEARING AND GRUBBING, GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost: $375,761.50


RankLicenseBidderConstruction Bid
1 48925 David V. Temple $358,336.06
2 09090 Guinn Brothers, LLC. $375,653.50
3 08815 W. E. Mcdonald & Son, LLC. $377,953.51
4 18546 C W & W Contractors, Inc. $390,756.00
5 01012 Cecil D. Gassiott, LLC $396,121.00
6 49239 W L Bass Construction Inc. $397,277.75


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
David V. Temple
- 2 -
Guinn Brothers, LLC.
- 3 -
W. E. Mcdonald & Son, LLC.
- 4 -
C W & W Contractors, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 6,015.00 6,015.00 15,000.00 15,000.00 25,000.00 25,000.00 15,000.00 15,000.00
0002 202-02-04000 Removal of Bridge STA 35+00;19.75' X 96.33' TIMBER BRIDGE) 1      EACH 5,000.00 5,000.00 10,000.00 10,000.00 8,000.00 8,000.00 9,600.00 9,600.00
0003 203-05-00100 Excavation and Embankment 1      LUMP 20,050.00 20,050.00 15,000.00 15,000.00 10,000.00 10,000.00 40,000.00 40,000.00
0004 204-02-00100 Temporary Hay or Straw Bales 7      EACH 15.00 105.00 10.00 70.00 10.00 70.00 50.00 350.00
0005 204-03-00100 Temporary Slope Drains 40      LNFT 6.50 260.00 0.00 0.00 25.00 1,000.00 10.00 400.00
0006 204-05-00100 Temporary Sediment Check Dams (Hay) 4      EACH 150.00 600.00 100.00 400.00 250.00 1,000.00 150.00 600.00
0007 204-06-00100 Temporary Silt Fencing 528      LNFT 3.00 1,584.00 3.00 1,584.00 3.00 1,584.00 3.00 1,584.00
0008 302-01-00100 Class II Base Course 163.1    CUYD 69.95 11,408.85 85.00 13,863.50 115.00 18,756.50 100.00 16,310.00
0009 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 62.30 6,230.00 0.00 0.00 1.00 100.00 25.00 2,500.00
0010 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 7.7    CUYD 62.30 479.71 200.00 1,540.00 500.00 3,850.00 100.00 770.00
0011 502-01-00100 Superpave Asphaltic Concrete 127.2    TON 225.00 28,620.00 250.00 31,800.00 245.00 31,164.00 200.00 25,440.00
0012 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 59.00 5,900.00 65.00 6,500.00 59.00 5,900.00 75.00 7,500.00
0013 704-09-00100 Guard Rail Anchor Sections (Turndown) 100      LNFT 29.00 2,900.00 33.00 3,300.00 29.00 2,900.00 50.00 5,000.00
0014 705-01-00100 Barbed Wire Fence 265      LNFT 8.50 2,252.50 10.00 2,650.00 10.00 2,650.00 10.00 2,650.00
0015 711-01-04000 Riprap (55 lb, 18" Thick) 182      SQYD 58.50 10,647.00 75.00 13,650.00 65.00 11,830.00 65.00 11,830.00
0016 711-04-00100 Geotextile Fabric 182      SQYD 3.00 546.00 5.00 910.00 3.00 546.00 1.00 182.00
0017 713-01-00100 Temporary Signs and Barricades 1      LUMP 5,000.00 5,000.00 6,000.00 6,000.00 10,000.00 10,000.00 10,000.00 10,000.00
0018 716-01-00100 Mulch (Vegetative) 0.4    TON 2,500.00 1,000.00 2,500.00 1,000.00 2,500.00 1,000.00 2,500.00 1,000.00
0019 717-01-00100 Seeding 9      LB 50.00 450.00 25.00 225.00 75.00 675.00 20.00 180.00
0020 718-01-00100 Fertilizer 180      LB 4.00 720.00 2.00 360.00 2.00 360.00 1.00 180.00
0021 727-01-00100 Mobilization 1      LUMP 26,000.00 26,000.00 35,000.00 35,000.00 25,000.00 25,000.00 45,000.00 45,000.00
0022 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 71.00 568.00 100.00 800.00 71.00 568.00 85.00 680.00
0023 740-01-00100 Construction Layout 1      LUMP 5,000.00 5,000.00 4,000.00 4,000.00 5,000.00 5,000.00 9,000.00 9,000.00
0024 804-01-00200 Precast Concrete Piles (14") 900      LNFT 65.00 58,500.00 60.00 54,000.00 60.00 54,000.00 65.00 58,500.00
0025 804-12-00100 Loading Permanent Piles 1      EACH 1,000.00 1,000.00 1.00 1.00 0.01 0.01 1,500.00 1,500.00
0026 805-10-01300 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) 5      SPAN 28,500.00 142,500.00 28,000.00 140,000.00 28,000.00 140,000.00 21,000.00 105,000.00
0027 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 7,500.00 15,000.00 9,000.00 18,000.00 8,500.00 17,000.00 10,000.00 20,000.00
                         
    CONTRACTOR TOTAL       358,336.06   375,653.50   377,953.51   390,756.00



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Cecil D. Gassiott, LLC
- 6 -
W L Bass Construction Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 5,000.00 5,000.00 10,000.00 10,000.00
0002 202-02-04000 Removal of Bridge STA 35+00;19.75' X 96.33' TIMBER BRIDGE) 1      EACH 9,000.00 9,000.00 4,000.00 4,000.00
0003 203-05-00100 Excavation and Embankment 1      LUMP 15,000.00 15,000.00 15,000.00 15,000.00
0004 204-02-00100 Temporary Hay or Straw Bales 7      EACH 20.00 140.00 0.00 0.00
0005 204-03-00100 Temporary Slope Drains 40      LNFT 30.00 1,200.00 0.00 0.00
0006 204-05-00100 Temporary Sediment Check Dams (Hay) 4      EACH 175.00 700.00 0.00 0.00
0007 204-06-00100 Temporary Silt Fencing 528      LNFT 3.50 1,848.00 0.00 0.00
0008 302-01-00100 Class II Base Course 163.1    CUYD 130.00 21,203.00 100.00 16,310.00
0009 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 100.00 10,000.00 0.00 0.00
0010 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 7.7    CUYD 160.00 1,232.00 85.00 654.50
0011 502-01-00100 Superpave Asphaltic Concrete 127.2    TON 275.00 34,980.00 135.00 17,172.00
0012 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 60.00 6,000.00 75.00 7,500.00
0013 704-09-00100 Guard Rail Anchor Sections (Turndown) 100      LNFT 34.00 3,400.00 30.00 3,000.00
0014 705-01-00100 Barbed Wire Fence 265      LNFT 9.00 2,385.00 8.25 2,186.25
0015 711-01-04000 Riprap (55 lb, 18" Thick) 182      SQYD 60.00 10,920.00 60.00 10,920.00
0016 711-04-00100 Geotextile Fabric 182      SQYD 4.00 728.00 2.00 364.00
0017 713-01-00100 Temporary Signs and Barricades 1      LUMP 10,000.00 10,000.00 4,500.00 4,500.00
0018 716-01-00100 Mulch (Vegetative) 0.4    TON 2,600.00 1,040.00 2,000.00 800.00
0019 717-01-00100 Seeding 9      LB 55.00 495.00 10.00 90.00
0020 718-01-00100 Fertilizer 180      LB 4.50 810.00 1.00 180.00
0021 727-01-00100 Mobilization 1      LUMP 50,000.00 50,000.00 39,000.00 39,000.00
0022 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 80.00 640.00 75.00 600.00
0023 740-01-00100 Construction Layout 1      LUMP 10,000.00 10,000.00 8,000.00 8,000.00
0024 804-01-00200 Precast Concrete Piles (14") 900      LNFT 66.00 59,400.00 100.00 90,000.00
0025 804-12-00100 Loading Permanent Piles 1      EACH 1,000.00 1,000.00 1.00 1.00
0026 805-10-01300 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) 5      SPAN 25,000.00 125,000.00 30,000.00 150,000.00
0027 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 7,000.00 14,000.00 8,500.00 17,000.00
                 
    CONTRACTOR TOTAL       396,121.00   397,277.75
 Free Tourist Map  
The La DOTD Headquarters Building is located at 1201 Capitol Access Road, Baton Rouge, LA, 70802. Telephone: (225) 379-1232.
Please send us your Comments or Suggestions.