Bid Tabulations
Letting of
09/22/2010
LA DOTD Headquarters
| Lead Project: 713-42-0147 | |
| Parish: Richland | |
| Routes: | |
| Description: THOMAS ROAD BRIDGE OVER EAST FORK CREEK | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $230,301.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 41947 | M & M Enterprises of Bastrop, LLC | $171,401.75 |
| 2 | 48925 | David V. Temple | $187,367.50 |
| 3 | 49239 | W L Bass Construction Inc. | $187,915.50 |
| 4 | 18546 | C W & W Contractors, Inc. | $224,851.00 |
| 5 | 01012 | Cecil D. Gassiott, LLC | $231,793.25 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - M & M Enterprises of Bastrop, LLC |
- 2 - David V. Temple |
- 3 - W L Bass Construction Inc. |
- 4 - C W & W Contractors, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 7,000.00 | 7,000.00 | 7,500.00 | 7,500.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 6 | EACH | 10.00 | 60.00 | 22.00 | 132.00 | 0.00 | 0.00 | 10.00 | 60.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 75.00 | 300.00 | 550.00 | 2,200.00 | 0.00 | 0.00 | 125.00 | 500.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 600 | LNFT | 2.50 | 1,500.00 | 5.50 | 3,300.00 | 0.00 | 0.00 | 3.00 | 1,800.00 |
| 0007 | 302-01-00800 | Class II Base Course (Stone or Recycled Portland Cement Concrete) | 130.3 | CUYD | 110.00 | 14,333.00 | 50.00 | 6,515.00 | 125.00 | 16,287.50 | 100.00 | 13,030.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 16 | CUYD | 50.00 | 800.00 | 50.00 | 800.00 | 90.00 | 1,440.00 | 100.00 | 1,600.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 100.6 | TON | 225.00 | 22,635.00 | 210.00 | 21,126.00 | 215.00 | 21,629.00 | 250.00 | 25,150.00 |
| 0010 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 100 | LNFT | 40.00 | 4,000.00 | 60.00 | 6,000.00 | 50.00 | 5,000.00 | 50.00 | 5,000.00 |
| 0011 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 200 | LNFT | 50.00 | 10,000.00 | 80.00 | 16,000.00 | 50.00 | 10,000.00 | 55.00 | 11,000.00 |
| 0012 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 125 | LNFT | 8.00 | 1,000.00 | 10.00 | 1,250.00 | 5.00 | 625.00 | 20.00 | 2,500.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,100.00 | 3,100.00 | 5,000.00 | 5,000.00 | 3,250.00 | 3,250.00 | 9,000.00 | 9,000.00 |
| 0014 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 1,000.00 | 300.00 | 5,500.00 | 1,650.00 | 2,000.00 | 600.00 | 3,000.00 | 900.00 |
| 0015 | 717-01-00100 | Seeding | 7 | LB | 25.00 | 175.00 | 110.00 | 770.00 | 15.00 | 105.00 | 100.00 | 700.00 |
| 0016 | 718-01-00100 | Fertilizer | 156 | LB | 3.00 | 468.00 | 5.50 | 858.00 | 2.00 | 312.00 | 3.00 | 468.00 |
| 0017 | 726-01-00100 | Bedding Material | 109 | CUYD | 100.00 | 10,900.00 | 50.00 | 5,450.00 | 100.00 | 10,900.00 | 125.00 | 13,625.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 8,000.00 | 8,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 24,000.00 | 24,000.00 |
| 0019 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 90.00 | 360.00 | 75.00 | 300.00 | 75.00 | 300.00 | 100.00 | 400.00 |
| 0020 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,300.00 | 2,300.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 | 8,000.00 | 8,000.00 |
| 0021 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 20.33 | CUYD | 900.00 | 18,297.00 | 1,050.00 | 21,346.50 | 900.00 | 18,297.00 | 1,100.00 | 22,363.00 |
| 0022 | 805-12-02040 | Reinforced Concrete Box Culverts (7' x 5') | 120 | LNFT | 480.00 | 57,600.00 | 450.00 | 54,000.00 | 400.00 | 48,000.00 | 500.00 | 60,000.00 |
| 0023 | 806-01-00100 | Deformed Reinforcing Steel | 1,585 | LB | 1.75 | 2,773.75 | 2.00 | 3,170.00 | 2.00 | 3,170.00 | 3.00 | 4,755.00 |
| 0024 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 | 500.00 | 500.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 171,401.75 | 187,367.50 | 187,915.50 | 224,851.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Cecil D. Gassiott, LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 2,500.00 | 2,500.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 6 | EACH | 10.00 | 60.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 250.00 | 1,000.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 600 | LNFT | 2.00 | 1,200.00 |
| 0007 | 302-01-00800 | Class II Base Course (Stone or Recycled Portland Cement Concrete) | 130.3 | CUYD | 120.00 | 15,636.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 16 | CUYD | 120.00 | 1,920.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 100.6 | TON | 300.00 | 30,180.00 |
| 0010 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 100 | LNFT | 60.00 | 6,000.00 |
| 0011 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 200 | LNFT | 70.00 | 14,000.00 |
| 0012 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 125 | LNFT | 10.00 | 1,250.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,500.00 | 3,500.00 |
| 0014 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 3,000.00 | 900.00 |
| 0015 | 717-01-00100 | Seeding | 7 | LB | 30.00 | 210.00 |
| 0016 | 718-01-00100 | Fertilizer | 156 | LB | 2.00 | 312.00 |
| 0017 | 726-01-00100 | Bedding Material | 109 | CUYD | 95.00 | 10,355.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 37,000.00 | 37,000.00 |
| 0019 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 90.00 | 360.00 |
| 0020 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 |
| 0021 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 20.33 | CUYD | 1,300.00 | 26,429.00 |
| 0022 | 805-12-02040 | Reinforced Concrete Box Culverts (7' x 5') | 120 | LNFT | 500.00 | 60,000.00 |
| 0023 | 806-01-00100 | Deformed Reinforcing Steel | 1,585 | LB | 1.25 | 1,981.25 |
| 0024 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,000.00 | 4,000.00 |