Bid Tabulations
Letting of
08/25/2010
LA DOTD Headquarters
| Lead Project: 713-42-0135 | |
| Parish: Richland | |
| Routes: | |
| Description: CAREY SMITH ROAD BRIDGE OVER UNNAMED CREEK | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $269,299.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49239 | W L Bass Construction Inc. | $168,244.50 |
| 2 | 45004 | Bondco LLC | $195,792.00 |
| 3 | 32563 | The Mabry Company, Inc. | $217,388.00 |
| 4 | 38936 | Southern Industrial Contractors Llc | $221,824.50 |
| 5 | 41947 | M & M Enterprises of Bastrop, LLC | $242,979.00 |
| 6 | 18546 | C W & W Contractors, Inc. | $243,650.50 |
| 7 | 48925 | David V. Temple | $245,190.00 |
| 8 | 44289 | Jeff Mercer LLC | $249,462.50 |
| 9 | 43371 | RMD Holdings Ltd | $287,507.04 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W L Bass Construction Inc. |
- 2 - Bondco LLC |
- 3 - The Mabry Company, Inc. |
- 4 - Southern Industrial Contractors Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 6,500.00 | 6,500.00 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 100.00 | 100.00 | 2,500.00 | 2,500.00 | 2,000.00 | 2,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 24 | EACH | 0.00 | 0.00 | 10.00 | 240.00 | 15.00 | 360.00 | 50.00 | 1,200.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 0.00 | 0.00 | 150.00 | 600.00 | 125.00 | 500.00 | 150.00 | 600.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 365 | LNFT | 0.00 | 0.00 | 2.00 | 730.00 | 2.00 | 730.00 | 2.00 | 730.00 |
| 0007 | 302-01-00100 | Class II Base Course | 122.3 | CUYD | 125.00 | 15,287.50 | 75.00 | 9,172.50 | 80.00 | 9,784.00 | 100.00 | 12,230.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 12 | CUYD | 100.00 | 1,200.00 | 50.00 | 600.00 | 100.00 | 1,200.00 | 125.00 | 1,500.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 95.2 | TON | 155.00 | 14,756.00 | 180.00 | 17,136.00 | 250.00 | 23,800.00 | 250.00 | 23,800.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,000.00 | 4,000.00 | 5,500.00 | 5,500.00 | 5,000.00 | 5,000.00 | 7,500.00 | 7,500.00 |
| 0011 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 1,500.00 | 900.00 | 500.00 | 300.00 | 2,000.00 | 1,200.00 | 3,000.00 | 1,800.00 |
| 0012 | 717-01-00100 | Seeding | 14 | LB | 5.00 | 70.00 | 10.00 | 140.00 | 10.00 | 140.00 | 25.00 | 350.00 |
| 0013 | 718-01-00100 | Fertilizer | 300 | LB | 2.00 | 600.00 | 0.50 | 150.00 | 2.00 | 600.00 | 3.25 | 975.00 |
| 0014 | 726-01-00100 | Bedding Material | 138.7 | CUYD | 85.00 | 11,789.50 | 100.00 | 13,870.00 | 100.00 | 13,870.00 | 125.00 | 17,337.50 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 16,000.00 | 16,000.00 | 9,000.00 | 9,000.00 | 27,500.00 | 27,500.00 | 10,000.00 | 10,000.00 |
| 0016 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 75.00 | 300.00 | 100.00 | 400.00 | 100.00 | 400.00 | 100.00 | 400.00 |
| 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,500.00 | 1,500.00 | 11,000.00 | 11,000.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 |
| 0018 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 27.5 | CUYD | 1,125.00 | 30,937.50 | 800.00 | 22,000.00 | 1,200.00 | 33,000.00 | 1,000.00 | 27,500.00 |
| 0019 | 805-12-01000 | Reinforced Concrete Box Culverts (4' x 4') | 300 | LNFT | 175.00 | 52,500.00 | 300.00 | 90,000.00 | 260.00 | 78,000.00 | 250.00 | 75,000.00 |
| 0020 | 806-01-00100 | Deformed Reinforcing Steel | 3,402 | LB | 2.00 | 6,804.00 | 1.75 | 5,953.50 | 2.00 | 6,804.00 | 1.00 | 3,402.00 |
| CONTRACTOR TOTAL | 168,244.50 | 195,792.00 | 217,388.00 | 221,824.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - M & M Enterprises of Bastrop, LLC |
- 6 - C W & W Contractors, Inc. |
- 7 - David V. Temple |
- 8 - Jeff Mercer LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,000.00 | 3,000.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 7,500.00 | 7,500.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 17,000.00 | 17,000.00 | 6,500.00 | 6,500.00 | 9,500.00 | 9,500.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 24 | EACH | 4.00 | 96.00 | 10.00 | 240.00 | 16.50 | 396.00 | 3.00 | 72.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 50.00 | 200.00 | 50.00 | 200.00 | 165.00 | 660.00 | 30.00 | 120.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 365 | LNFT | 2.50 | 912.50 | 3.00 | 1,095.00 | 3.50 | 1,277.50 | 2.00 | 730.00 |
| 0007 | 302-01-00100 | Class II Base Course | 122.3 | CUYD | 120.00 | 14,676.00 | 100.00 | 12,230.00 | 45.00 | 5,503.50 | 125.00 | 15,287.50 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 12 | CUYD | 65.00 | 780.00 | 55.00 | 660.00 | 150.00 | 1,800.00 | 50.00 | 600.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 95.2 | TON | 225.00 | 21,420.00 | 300.00 | 28,560.00 | 325.00 | 30,940.00 | 180.00 | 17,136.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,600.00 | 6,600.00 | 11,000.00 | 11,000.00 | 7,500.00 | 7,500.00 | 4,200.00 | 4,200.00 |
| 0011 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 2,000.00 | 1,200.00 | 2,500.00 | 1,500.00 | 2,750.00 | 1,650.00 | 200.00 | 120.00 |
| 0012 | 717-01-00100 | Seeding | 14 | LB | 45.00 | 630.00 | 20.00 | 280.00 | 25.00 | 350.00 | 2.00 | 28.00 |
| 0013 | 718-01-00100 | Fertilizer | 300 | LB | 2.00 | 600.00 | 1.00 | 300.00 | 3.00 | 900.00 | 0.15 | 45.00 |
| 0014 | 726-01-00100 | Bedding Material | 138.7 | CUYD | 115.00 | 15,950.50 | 85.00 | 11,789.50 | 50.00 | 6,935.00 | 350.00 | 48,545.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 | 55,000.00 | 55,000.00 | 15,000.00 | 15,000.00 |
| 0016 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 90.00 | 360.00 | 85.00 | 340.00 | 75.00 | 300.00 | 100.00 | 400.00 |
| 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 8,000.00 | 8,000.00 | 6,500.00 | 6,500.00 | 6,500.00 | 6,500.00 |
| 0018 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 27.5 | CUYD | 900.00 | 24,750.00 | 1,100.00 | 30,250.00 | 1,050.00 | 28,875.00 | 1,050.00 | 28,875.00 |
| 0019 | 805-12-01000 | Reinforced Concrete Box Culverts (4' x 4') | 300 | LNFT | 370.00 | 111,000.00 | 260.00 | 78,000.00 | 250.00 | 75,000.00 | 285.00 | 85,500.00 |
| 0020 | 806-01-00100 | Deformed Reinforcing Steel | 3,402 | LB | 2.00 | 6,804.00 | 3.00 | 10,206.00 | 1.50 | 5,103.00 | 2.00 | 6,804.00 |
| CONTRACTOR TOTAL | 242,979.00 | 243,650.50 | 245,190.00 | 249,462.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - RMD Holdings Ltd |
|
| Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,816.00 | 3,816.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 913.20 | 913.20 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 33,168.00 | 33,168.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 24 | EACH | 16.10 | 386.50 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 168.00 | 672.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 365 | LNFT | 4.32 | 1,576.80 |
| 0007 | 302-01-00100 | Class II Base Course | 122.3 | CUYD | 111.28 | 13,609.54 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 12 | CUYD | 111.28 | 1,335.36 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 95.2 | TON | 270.94 | 25,793.49 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,336.00 | 9,336.00 |
| 0011 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 1,971.06 | 1,182.64 |
| 0012 | 717-01-00100 | Seeding | 14 | LB | 24.00 | 336.00 |
| 0013 | 718-01-00100 | Fertilizer | 300 | LB | 3.00 | 900.00 |
| 0014 | 726-01-00100 | Bedding Material | 138.7 | CUYD | 184.66 | 25,612.34 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 39,213.29 | 39,213.29 |
| 0016 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 82.89 | 331.56 |
| 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,420.00 | 3,420.00 |
| 0018 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 27.5 | CUYD | 1,296.09 | 35,642.48 |
| 0019 | 805-12-01000 | Reinforced Concrete Box Culverts (4' x 4') | 300 | LNFT | 256.42 | 76,926.00 |
| 0020 | 806-01-00100 | Deformed Reinforcing Steel | 3,402 | LB | 3.92 | 13,335.84 |
| CONTRACTOR TOTAL | 287,507.04 | |||||