Bid Tabulations
Letting of
01/26/2011
LA DOTD Headquarters
| Lead Project: 713-35-0118 | |
| Parish: Natchitoches | |
| Routes: | |
| Description: QUICK ROAD BRIDGE OVER DEMERY CREEK | |
| Type Const: GRADING, PAVING, AND RELATED WORK | |
| Estimated Construction Cost: $155,321.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 40439 | Ronald G. Carlson Inc. | $86,837.90 |
| 2 | 51413 | Iverstine & Campbell LLC | $97,135.69 |
| 3 | 39580 | Gerace Construction Llc | $106,460.00 |
| 4 | 35849 | T.L. Construction LLC | $107,277.60 |
| 5 | 41947 | M & M Enterprises of Bastrop, LLC | $111,054.00 |
| 6 | 40615 | Specialty Trackhoe & Dozer Serv.Inc | $111,964.00 |
| 7 | 49239 | W L Bass Construction Inc. | $117,732.00 |
| 8 | 44289 | Jeff Mercer LLC | $124,385.00 |
| 9 | 45004 | Bondco LLC | $134,850.00 |
| 10 | 32044 | Quality Design & Construction, LLC | $144,148.00 |
| 11 | 36384 | John Bailey, Inc. | $149,768.00 |
| 12 | 12312 | Gilchrist Construction Co. LLC | $152,253.62 |
| 13 | 12135 | Blount Bros. Construction, Inc. | $153,592.00 |
| 14 | 18546 | C W & W Contractors, Inc. | $158,055.00 |
| 15 | 09090 | Guinn Brothers, LLC. | $158,437.00 |
| 16 | 39001 | Jd's Rebar & Construction Inc. | $159,019.20 |
| 17 | 32563 | The Mabry Company, Inc. | $162,013.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Ronald G. Carlson Inc. |
- 2 - Iverstine & Campbell LLC |
- 3 - Gerace Construction Llc |
- 4 - T.L. Construction LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,000.00 | 1,000.00 | 3,139.50 | 3,139.50 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 18.4'X 39.0' TIMBER BRIDGE) (WITH WINGWALLS) | 1 | EACH | 2,000.00 | 2,000.00 | 2,866.50 | 2,866.50 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 6,961.50 | 6,961.50 | 8,000.00 | 8,000.00 | 14,000.00 | 14,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | EACH | 10.00 | 100.00 | 16.38 | 163.80 | 20.00 | 200.00 | 20.00 | 200.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 100.00 | 400.00 | 61.43 | 245.72 | 50.00 | 200.00 | 150.00 | 600.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 125 | LNFT | 2.50 | 312.50 | 3.41 | 426.25 | 2.00 | 250.00 | 4.00 | 500.00 |
| 0007 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 47.2 | CUYD | 65.00 | 3,068.00 | 90.09 | 4,252.25 | 100.00 | 4,720.00 | 143.00 | 6,749.60 |
| 0008 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 144 | LNFT | 325.00 | 46,800.00 | 322.14 | 46,388.16 | 300.00 | 43,200.00 | 275.00 | 39,600.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 60 | LNFT | 5.00 | 300.00 | 5.46 | 327.60 | 10.00 | 600.00 | 20.00 | 1,200.00 |
| 0010 | 712-02-00100 | Sacked Concrete Revetment | 125 | SQYD | 70.00 | 8,750.00 | 66.89 | 8,361.25 | 100.00 | 12,500.00 | 75.00 | 9,375.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,000.00 | 2,000.00 | 7,371.00 | 7,371.00 | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 1,500.00 | 450.00 | 887.25 | 266.18 | 4,000.00 | 1,200.00 | 2,300.00 | 690.00 |
| 0013 | 717-01-00100 | Seeding | 6 | LB | 70.00 | 420.00 | 13.65 | 81.90 | 50.00 | 300.00 | 30.00 | 180.00 |
| 0014 | 718-01-00100 | Fertilizer | 142 | LB | 1.50 | 213.00 | 4.10 | 582.20 | 5.00 | 710.00 | 1.50 | 213.00 |
| 0015 | 726-01-00100 | Bedding Material | 107.6 | CUYD | 69.00 | 7,424.40 | 72.35 | 7,784.86 | 100.00 | 10,760.00 | 75.00 | 8,070.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 2,000.00 | 2,000.00 | 3,412.50 | 3,412.50 | 9,500.00 | 9,500.00 | 10,000.00 | 10,000.00 |
| 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 150.00 | 600.00 | 102.38 | 409.52 | 80.00 | 320.00 | 100.00 | 400.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 4,095.00 | 4,095.00 | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 |
| CONTRACTOR TOTAL | 86,837.90 | 97,135.69 | 106,460.00 | 107,277.60 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - M & M Enterprises of Bastrop, LLC |
- 6 - Specialty Trackhoe & Dozer Serv.Inc |
- 7 - W L Bass Construction Inc. |
- 8 - Jeff Mercer LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 5,500.00 | 5,500.00 | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 2,500.00 | 2,500.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 18.4'X 39.0' TIMBER BRIDGE) (WITH WINGWALLS) | 1 | EACH | 2,500.00 | 2,500.00 | 3,500.00 | 3,500.00 | 8,500.00 | 8,500.00 | 5,000.00 | 5,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 4,000.00 | 4,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | EACH | 1.00 | 10.00 | 30.00 | 300.00 | 1.00 | 10.00 | 5.00 | 50.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 85.00 | 340.00 | 145.00 | 580.00 | 1.00 | 4.00 | 25.00 | 100.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 125 | LNFT | 2.00 | 250.00 | 2.00 | 250.00 | 1.00 | 125.00 | 1.00 | 125.00 |
| 0007 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 47.2 | CUYD | 95.00 | 4,484.00 | 130.00 | 6,136.00 | 100.00 | 4,720.00 | 65.00 | 3,068.00 |
| 0008 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 144 | LNFT | 310.00 | 44,640.00 | 356.00 | 51,264.00 | 300.00 | 43,200.00 | 370.00 | 53,280.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 60 | LNFT | 6.00 | 360.00 | 12.00 | 720.00 | 5.00 | 300.00 | 5.00 | 300.00 |
| 0010 | 712-02-00100 | Sacked Concrete Revetment | 125 | SQYD | 100.00 | 12,500.00 | 116.00 | 14,500.00 | 85.00 | 10,625.00 | 175.00 | 21,875.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,000.00 | 4,000.00 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 | 5,000.00 | 5,000.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 2,700.00 | 810.00 | 3,000.00 | 900.00 | 2,000.00 | 600.00 | 1,050.00 | 315.00 |
| 0013 | 717-01-00100 | Seeding | 6 | LB | 25.00 | 150.00 | 10.00 | 60.00 | 10.00 | 60.00 | 5.00 | 30.00 |
| 0014 | 718-01-00100 | Fertilizer | 142 | LB | 3.00 | 426.00 | 1.00 | 142.00 | 1.00 | 142.00 | 10.00 | 1,420.00 |
| 0015 | 726-01-00100 | Bedding Material | 107.6 | CUYD | 90.00 | 9,684.00 | 120.00 | 12,912.00 | 85.00 | 9,146.00 | 95.00 | 10,222.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 12,000.00 | 12,000.00 | 8,000.00 | 8,000.00 | 15,000.00 | 15,000.00 | 8,000.00 | 8,000.00 |
| 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 | 100.00 | 400.00 | 75.00 | 300.00 | 150.00 | 600.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 1,800.00 | 1,800.00 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 |
| CONTRACTOR TOTAL | 111,054.00 | 111,964.00 | 117,732.00 | 124,385.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Bondco LLC |
- 10 - Quality Design & Construction, LLC |
- 11 - John Bailey, Inc. |
- 12 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,500.00 | 1,500.00 | 5,100.00 | 5,100.00 | 2,500.00 | 2,500.00 | 6,000.00 | 6,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 18.4'X 39.0' TIMBER BRIDGE) (WITH WINGWALLS) | 1 | EACH | 5,000.00 | 5,000.00 | 7,200.00 | 7,200.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 5,600.00 | 5,600.00 | 15,500.00 | 15,500.00 | 7,500.00 | 7,500.00 | 16,000.00 | 16,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | EACH | 10.00 | 100.00 | 13.60 | 136.00 | 25.00 | 250.00 | 40.00 | 400.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 150.00 | 600.00 | 181.00 | 724.00 | 250.00 | 1,000.00 | 300.00 | 1,200.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 125 | LNFT | 3.00 | 375.00 | 2.00 | 250.00 | 4.00 | 500.00 | 4.50 | 562.50 |
| 0007 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 47.2 | CUYD | 105.00 | 4,956.00 | 120.00 | 5,664.00 | 125.00 | 5,900.00 | 110.00 | 5,192.00 |
| 0008 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 144 | LNFT | 480.00 | 69,120.00 | 360.00 | 51,840.00 | 500.00 | 72,000.00 | 389.83 | 56,135.52 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 60 | LNFT | 10.00 | 600.00 | 1.80 | 108.00 | 15.00 | 900.00 | 7.00 | 420.00 |
| 0010 | 712-02-00100 | Sacked Concrete Revetment | 125 | SQYD | 95.00 | 11,875.00 | 108.00 | 13,500.00 | 125.00 | 15,625.00 | 80.00 | 10,000.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,203.00 | 3,203.00 | 11,500.00 | 11,500.00 | 2,500.00 | 2,500.00 | 10,000.00 | 10,000.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 3,300.00 | 990.00 | 4,000.00 | 1,200.00 | 700.00 | 210.00 | 3,500.00 | 1,050.00 |
| 0013 | 717-01-00100 | Seeding | 6 | LB | 20.00 | 120.00 | 6.30 | 37.80 | 20.00 | 120.00 | 55.00 | 330.00 |
| 0014 | 718-01-00100 | Fertilizer | 142 | LB | 5.00 | 710.00 | 2.10 | 298.20 | 1.50 | 213.00 | 5.80 | 823.60 |
| 0015 | 726-01-00100 | Bedding Material | 107.6 | CUYD | 85.50 | 9,199.80 | 130.00 | 13,988.00 | 125.00 | 13,450.00 | 100.00 | 10,760.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 15,553.20 | 15,553.20 | 10,900.00 | 10,900.00 | 15,000.00 | 15,000.00 | 13,000.00 | 13,000.00 |
| 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 85.00 | 340.00 | 83.00 | 332.00 | 150.00 | 600.00 | 95.00 | 380.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,008.00 | 5,008.00 | 5,870.00 | 5,870.00 | 1,500.00 | 1,500.00 | 10,000.00 | 10,000.00 |
| CONTRACTOR TOTAL | 134,850.00 | 144,148.00 | 149,768.00 | 152,253.62 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 13 - Blount Bros. Construction, Inc. |
- 14 - C W & W Contractors, Inc. |
- 15 - Guinn Brothers, LLC. |
- 16 - Jd's Rebar & Construction Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 5,800.00 | 5,800.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 18.4'X 39.0' TIMBER BRIDGE) (WITH WINGWALLS) | 1 | EACH | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 | 9,300.00 | 9,300.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 12,500.00 | 12,500.00 | 17,500.00 | 17,500.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | EACH | 10.00 | 100.00 | 10.00 | 100.00 | 10.00 | 100.00 | 30.00 | 300.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 300.00 | 1,200.00 | 125.00 | 500.00 | 100.00 | 400.00 | 230.00 | 920.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 125 | LNFT | 4.00 | 500.00 | 3.00 | 375.00 | 3.00 | 375.00 | 9.00 | 1,125.00 |
| 0007 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 47.2 | CUYD | 85.00 | 4,012.00 | 100.00 | 4,720.00 | 100.00 | 4,720.00 | 205.00 | 9,676.00 |
| 0008 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 144 | LNFT | 350.00 | 50,400.00 | 500.00 | 72,000.00 | 460.00 | 66,240.00 | 245.00 | 35,280.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 60 | LNFT | 10.00 | 600.00 | 20.00 | 1,200.00 | 15.00 | 900.00 | 38.00 | 2,280.00 |
| 0010 | 712-02-00100 | Sacked Concrete Revetment | 125 | SQYD | 150.00 | 18,750.00 | 100.00 | 12,500.00 | 100.00 | 12,500.00 | 95.00 | 11,875.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 | 5,100.00 | 5,100.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 2,000.00 | 600.00 | 5,000.00 | 1,500.00 | 2,500.00 | 750.00 | 3,800.00 | 1,140.00 |
| 0013 | 717-01-00100 | Seeding | 6 | LB | 20.00 | 120.00 | 100.00 | 600.00 | 25.00 | 150.00 | 80.00 | 480.00 |
| 0014 | 718-01-00100 | Fertilizer | 142 | LB | 20.00 | 2,840.00 | 5.00 | 710.00 | 1.00 | 142.00 | 7.60 | 1,079.20 |
| 0015 | 726-01-00100 | Bedding Material | 107.6 | CUYD | 75.00 | 8,070.00 | 125.00 | 13,450.00 | 100.00 | 10,760.00 | 190.00 | 20,444.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 |
| 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 | 100.00 | 400.00 | 100.00 | 400.00 | 430.00 | 1,720.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 | 3,500.00 | 3,500.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 153,592.00 | 158,055.00 | 158,437.00 | 159,019.20 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 17 - The Mabry Company, Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 2,000.00 | 2,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 18.4'X 39.0' TIMBER BRIDGE) (WITH WINGWALLS) | 1 | EACH | 2,500.00 | 2,500.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 6,500.00 | 6,500.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | EACH | 15.00 | 150.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 200.00 | 800.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 125 | LNFT | 3.00 | 375.00 |
| 0007 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 47.2 | CUYD | 65.00 | 3,068.00 |
| 0008 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 144 | LNFT | 625.00 | 90,000.00 |
| 0009 | 705-01-00100 | Barbed Wire Fence | 60 | LNFT | 30.00 | 1,800.00 |
| 0010 | 712-02-00100 | Sacked Concrete Revetment | 125 | SQYD | 100.00 | 12,500.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,500.00 | 2,500.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.3 | TON | 1,000.00 | 300.00 |
| 0013 | 717-01-00100 | Seeding | 6 | LB | 25.00 | 150.00 |
| 0014 | 718-01-00100 | Fertilizer | 142 | LB | 5.00 | 710.00 |
| 0015 | 726-01-00100 | Bedding Material | 107.6 | CUYD | 100.00 | 10,760.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 24,500.00 | 24,500.00 |
| 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 |
| CONTRACTOR TOTAL | 162,013.00 | |||||