LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 713-01-0119
Parish: Acadia
Routes:
Description: PERCHVILLE, FOURNERAT, AND SONNIER ROAD BRIDGES
Type Const: CLEARING AND GRUBBING, GRADING, TIMBER BRIDGE REMOVAL, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, SLAB SPAN BRIDGES, AND RELATED WORK
Estimated Construction Cost: $1,920,946.00


RankLicenseBidderConstruction Bid
1 08815 W. E. Mcdonald & Son, LLC. $1,329,214.10
2 01012 Cecil D. Gassiott, LLC $1,509,659.50
3 09090 Guinn Brothers, LLC. $1,518,741.60
4 12312 Gilchrist Construction Co. LLC $1,584,693.20
5 40312 Gray Construction Corp. $1,752,717.84
6 39462 Jb James Construction Llc $1,799,869.93
7 34567 James Construction Group LLC $2,108,146.95


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
W. E. Mcdonald & Son, LLC.
- 2 -
Cecil D. Gassiott, LLC
- 3 -
Guinn Brothers, LLC.
- 4 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 42,000.00 42,000.00 40,000.00 40,000.00 26,000.00 26,000.00 20,000.00 20,000.00
0002 202-02-04000 Removal of Bridge (STA 100+00;18.1' X 117.7.' TIMBER BR) 1      EACH 5,000.00 5,000.00 25,000.00 25,000.00 8,500.00 8,500.00 12,000.00 12,000.00
0003 202-02-04000 Removal of Bridge (STA 200+00;22.7' X 67.5.' TIMBER BR) 1      EACH 5,000.00 5,000.00 12,500.00 12,500.00 8,000.00 8,000.00 12,000.00 12,000.00
0004 202-02-04000 Removal of Bridge (STA 300+00;18.1' X 80.0' TIMBER BR) 1      EACH 5,000.00 5,000.00 10,000.00 10,000.00 8,000.00 8,000.00 12,000.00 12,000.00
0005 202-02-38500 Removal of Surfacing and Stablized Base 1,631.9    SQYD 5.00 8,159.50 5.00 8,159.50 4.00 6,527.60 7.79 12,712.50
0006 203-05-00100 Excavation and Embankment 1      LUMP 43,000.00 43,000.00 80,000.00 80,000.00 65,000.00 65,000.00 75,000.00 75,000.00
0007 204-02-00100 Temporary Hay or Straw Bales 60      EACH 3.00 180.00 10.00 600.00 10.00 600.00 16.00 960.00
0008 204-03-00100 Temporary Slope Drains 360      LNFT 1.00 360.00 20.00 7,200.00 0.00 0.00 10.00 3,600.00
0009 204-05-00100 Temporary Sediment Check Dams (Hay) 7      EACH 250.00 1,750.00 200.00 1,400.00 100.00 700.00 145.00 1,015.00
0010 204-06-00100 Temporary Silt Fencing 2,885      LNFT 2.00 5,770.00 2.50 7,212.50 0.00 0.00 2.00 5,770.00
0011 302-01-00700 Class II Base Course (Stone) 458.5    CUYD 84.00 38,514.00 80.00 36,680.00 85.00 38,972.50 98.00 44,933.00
0012 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 23      CUYD 100.00 2,300.00 100.00 2,300.00 100.00 2,300.00 140.00 3,220.00
0013 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 57.1    CUYD 80.00 4,568.00 75.00 4,282.50 90.00 5,139.00 100.00 5,710.00
0014 502-01-00100 Superpave Asphaltic Concrete 375.6    TON 191.00 71,739.60 195.00 73,242.00 200.00 75,120.00 200.00 75,120.00
0015 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 12      LNFT 45.00 540.00 100.00 1,200.00 75.00 900.00 105.00 1,260.00
0016 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 240      LNFT 53.00 12,720.00 70.00 16,800.00 60.00 14,400.00 65.00 15,600.00
0017 701-05-01080 Side Drain Pipe (30" RCP/PP/CMP) 72      LNFT 66.00 4,752.00 115.00 8,280.00 90.00 6,480.00 93.00 6,696.00
0018 701-05-02040 Side Drain Pipe (Erosion) (18" PP/CMP) 270      LNFT 45.00 12,150.00 55.00 14,850.00 48.00 12,960.00 45.00 12,150.00
0019 701-05-02060 Side Drain Pipe (Erosion) (24" PP/CMP) 552      LNFT 53.00 29,256.00 65.00 35,880.00 60.00 33,120.00 55.00 30,360.00
0020 701-05-02080 Side Drain Pipe (Erosion) (30" PP/CMP) 188      LNFT 66.00 12,408.00 115.00 21,620.00 90.00 16,920.00 75.00 14,100.00
0021 702-03-00100 Catch Basins (CB-01) 4      EACH 2,500.00 10,000.00 2,000.00 8,000.00 3,500.00 14,000.00 3,500.00 14,000.00
0022 704-03-00100 Blocked Out Guard Rail 225      LNFT 45.00 10,125.00 20.00 4,500.00 22.50 5,062.50 20.00 4,500.00
0023 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 50      LNFT 65.00 3,250.00 60.00 3,000.00 65.00 3,250.00 64.00 3,200.00
0024 704-09-00100 Guard Rail Anchor Sections (Turndown) 200      LNFT 48.00 9,600.00 30.00 6,000.00 33.00 6,600.00 33.00 6,600.00
0025 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,100.00 8,400.00 2,200.00 8,800.00 2,500.00 10,000.00 2,400.00 9,600.00
0026 705-01-00100 Barbed Wire Fence 530      LNFT 10.00 5,300.00 10.00 5,300.00 10.00 5,300.00 8.50 4,505.00
0027 705-09-00100 Rebuilt Fence 66      LNFT 25.00 1,650.00 10.00 660.00 25.00 1,650.00 5.70 376.20
0028 711-01-03000 Riprap (30 lb, 14" Thick) 2,285      SQYD 63.00 143,955.00 60.00 137,100.00 60.00 137,100.00 57.00 130,245.00
0029 711-04-00100 Geotextile Fabric 2,285      SQYD 3.00 6,855.00 3.00 6,855.00 5.00 11,425.00 2.70 6,169.50
0030 713-01-00100 Temporary Signs and Barricades 1      LUMP 20,000.00 20,000.00 35,000.00 35,000.00 16,000.00 16,000.00 12,000.00 12,000.00
0031 716-01-00100 Mulch (Vegetative) 1.5    TON 1,200.00 1,800.00 1,000.00 1,500.00 2,000.00 3,000.00 680.00 1,020.00
0032 717-01-00100 Seeding 34      LB 15.00 510.00 20.00 680.00 25.00 850.00 11.30 384.20
0033 718-01-00100 Fertilizer 752      LB 0.50 376.00 1.00 752.00 1.00 752.00 1.15 864.80
0034 726-01-00100 Bedding Material 13.2    CUYD 100.00 1,320.00 80.00 1,056.00 100.00 1,320.00 135.00 1,782.00
0035 727-01-00100 Mobilization 1      LUMP 30,000.00 30,000.00 75,000.00 75,000.00 75,000.00 75,000.00 149,000.00 149,000.00
0036 729-16-00300 Object Marker Assembly (Type 3) 20      EACH 95.00 1,900.00 80.00 1,600.00 100.00 2,000.00 85.00 1,700.00
0037 735-01-00100 Mailboxes 3      EACH 1.00 3.00 10.00 30.00 100.00 300.00 10.00 30.00
0038 735-02-00100 Mailbox Supports (Single) 3      EACH 350.00 1,050.00 150.00 450.00 100.00 300.00 145.00 435.00
0039 740-01-00100 Construction Layout 1      LUMP 7,000.00 7,000.00 15,000.00 15,000.00 14,000.00 14,000.00 15,000.00 15,000.00
0040 804-01-00200 Precast Concrete Piles (14") 4,485      LNFT 50.00 224,250.00 50.00 224,250.00 55.00 246,675.00 55.00 246,675.00
0041 804-12-00100 Loading Permanent Piles 3      EACH 1.00 3.00 1,500.00 4,500.00 1.00 3.00 1,000.00 3,000.00
0042 805-10-01200 Bridge Superstructure and Substructure (24' Clear Roadway; 75 Degree Crossing) 6      SPAN 25,000.00 150,000.00 22,500.00 135,000.00 30,000.00 180,000.00 24,000.00 144,000.00
0043 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 7      SPAN 25,000.00 175,000.00 35,000.00 245,000.00 30,000.00 210,000.00 30,000.00 210,000.00
0044 805-10-02200 Bridge Superstructure and Substructure (28' Clear Roadway; 75 Degree Crossing) 5      SPAN 30,000.00 150,000.00 23,500.00 117,500.00 32,500.00 162,500.00 24,000.00 120,000.00
0045 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 8,000.00 16,000.00 8,000.00 16,000.00 8,500.00 17,000.00 18,000.00 36,000.00
0046 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 75 DEG CROSSING) (W/O ASPHALT) 2      EACH 8,000.00 16,000.00 8,000.00 16,000.00 8,500.00 17,000.00 18,000.00 36,000.00
0047 NS-800-00040 Concrete Approach Slabs (28' CLR RDWY, 75 DEG CROSSING) (W/O ASPHALT) 2      EACH 8,000.00 16,000.00 8,000.00 16,000.00 9,000.00 18,000.00 18,000.00 36,000.00
0048 NS-804-00001 Vibration Monitoring 39      EACH 300.00 11,700.00 280.00 10,920.00 385.00 15,015.00 600.00 23,400.00
0049 NS-727-00002 Temporary Construction Matting 1      LUMP 2,000.00 2,000.00 6,000.00 6,000.00 15,000.00 15,000.00 4,000.00 4,000.00
                         
    CONTRACTOR TOTAL       1,329,214.10   1,509,659.50   1,518,741.60   1,584,693.20



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Gray Construction Corp.
- 6 -
Jb James Construction Llc
- 7 -
James Construction Group LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 40,000.00 40,000.00 100,000.00 100,000.00 60,000.00 60,000.00
0002 202-02-04000 Removal of Bridge (STA 100+00;18.1' X 117.7.' TIMBER BR) 1      EACH 12,250.00 12,250.00 35,000.00 35,000.00 20,000.00 20,000.00
0003 202-02-04000 Removal of Bridge (STA 200+00;22.7' X 67.5.' TIMBER BR) 1      EACH 10,000.00 10,000.00 25,000.00 25,000.00 15,000.00 15,000.00
0004 202-02-04000 Removal of Bridge (STA 300+00;18.1' X 80.0' TIMBER BR) 1      EACH 10,000.00 10,000.00 25,000.00 25,000.00 15,000.00 15,000.00
0005 202-02-38500 Removal of Surfacing and Stablized Base 1,631.9    SQYD 3.10 5,058.89 6.00 9,791.40 4.00 6,527.60
0006 203-05-00100 Excavation and Embankment 1      LUMP 46,000.00 46,000.00 160,000.00 160,000.00 155,000.00 155,000.00
0007 204-02-00100 Temporary Hay or Straw Bales 60      EACH 15.00 900.00 12.00 720.00 34.00 2,040.00
0008 204-03-00100 Temporary Slope Drains 360      LNFT 5.00 1,800.00 8.00 2,880.00 20.00 7,200.00
0009 204-05-00100 Temporary Sediment Check Dams (Hay) 7      EACH 153.00 1,071.00 125.00 875.00 440.00 3,080.00
0010 204-06-00100 Temporary Silt Fencing 2,885      LNFT 1.50 4,327.50 2.00 5,770.00 2.25 6,491.25
0011 302-01-00700 Class II Base Course (Stone) 458.5    CUYD 136.00 62,356.00 115.00 52,727.50 125.00 57,312.50
0012 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 23      CUYD 200.00 4,600.00 110.00 2,530.00 100.00 2,300.00
0013 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 57.1    CUYD 174.00 9,935.40 100.00 5,710.00 95.00 5,424.50
0014 502-01-00100 Superpave Asphaltic Concrete 375.6    TON 200.00 75,120.00 180.00 67,608.00 180.00 67,608.00
0015 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 12      LNFT 66.70 800.40 70.00 840.00 116.00 1,392.00
0016 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 240      LNFT 38.80 9,312.00 75.00 18,000.00 57.00 13,680.00
0017 701-05-01080 Side Drain Pipe (30" RCP/PP/CMP) 72      LNFT 55.30 3,981.60 110.00 7,920.00 83.00 5,976.00
0018 701-05-02040 Side Drain Pipe (Erosion) (18" PP/CMP) 270      LNFT 31.60 8,532.00 45.00 12,150.00 46.00 12,420.00
0019 701-05-02060 Side Drain Pipe (Erosion) (24" PP/CMP) 552      LNFT 38.80 21,417.60 55.00 30,360.00 54.00 29,808.00
0020 701-05-02080 Side Drain Pipe (Erosion) (30" PP/CMP) 188      LNFT 55.30 10,396.40 65.00 12,220.00 72.00 13,536.00
0021 702-03-00100 Catch Basins (CB-01) 4      EACH 2,700.00 10,800.00 2,800.00 11,200.00 4,800.00 19,200.00
0022 704-03-00100 Blocked Out Guard Rail 225      LNFT 20.00 4,500.00 18.50 4,162.50 18.50 4,162.50
0023 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 50      LNFT 60.00 3,000.00 57.00 2,850.00 57.00 2,850.00
0024 704-09-00100 Guard Rail Anchor Sections (Turndown) 200      LNFT 30.00 6,000.00 29.00 5,800.00 29.00 5,800.00
0025 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,100.00 8,400.00 2,100.00 8,400.00 2,100.00 8,400.00
0026 705-01-00100 Barbed Wire Fence 530      LNFT 8.50 4,505.00 7.00 3,710.00 15.00 7,950.00
0027 705-09-00100 Rebuilt Fence 66      LNFT 24.50 1,617.00 50.00 3,300.00 30.00 1,980.00
0028 711-01-03000 Riprap (30 lb, 14" Thick) 2,285      SQYD 64.50 147,382.50 52.00 118,820.00 52.00 118,820.00
0029 711-04-00100 Geotextile Fabric 2,285      SQYD 3.05 6,969.25 3.00 6,855.00 5.00 11,425.00
0030 713-01-00100 Temporary Signs and Barricades 1      LUMP 18,300.00 18,300.00 38,000.00 38,000.00 18,000.00 18,000.00
0031 716-01-00100 Mulch (Vegetative) 1.5    TON 650.00 975.00 650.00 975.00 3,500.00 5,250.00
0032 717-01-00100 Seeding 34      LB 11.00 374.00 10.00 340.00 25.00 850.00
0033 718-01-00100 Fertilizer 752      LB 1.00 752.00 1.00 752.00 3.00 2,256.00
0034 726-01-00100 Bedding Material 13.2    CUYD 164.00 2,164.80 62.01 818.53 68.00 897.60
0035 727-01-00100 Mobilization 1      LUMP 117,500.00 117,500.00 175,000.00 175,000.00 210,000.00 210,000.00
0036 729-16-00300 Object Marker Assembly (Type 3) 20      EACH 80.00 1,600.00 75.00 1,500.00 75.00 1,500.00
0037 735-01-00100 Mailboxes 3      EACH 57.00 171.00 50.00 150.00 5.00 15.00
0038 735-02-00100 Mailbox Supports (Single) 3      EACH 75.00 225.00 200.00 600.00 200.00 600.00
0039 740-01-00100 Construction Layout 1      LUMP 14,000.00 14,000.00 30,000.00 30,000.00 15,000.00 15,000.00
0040 804-01-00200 Precast Concrete Piles (14") 4,485      LNFT 91.10 408,583.50 51.00 228,735.00 57.00 255,645.00
0041 804-12-00100 Loading Permanent Piles 3      EACH 100.00 300.00 500.00 1,500.00 25,000.00 75,000.00
0042 805-10-01200 Bridge Superstructure and Substructure (24' Clear Roadway; 75 Degree Crossing) 6      SPAN 27,200.00 163,200.00 23,500.00 141,000.00 35,000.00 210,000.00
0043 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 7      SPAN 41,700.00 291,900.00 30,000.00 210,000.00 46,000.00 322,000.00
0044 805-10-02200 Bridge Superstructure and Substructure (28' Clear Roadway; 75 Degree Crossing) 5      SPAN 27,700.00 138,500.00 24,500.00 122,500.00 37,000.00 185,000.00
0045 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 6,500.00 13,000.00 14,000.00 28,000.00 13,000.00 26,000.00
0046 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 75 DEG CROSSING) (W/O ASPHALT) 2      EACH 6,500.00 13,000.00 14,000.00 28,000.00 15,000.00 30,000.00
0047 NS-800-00040 Concrete Approach Slabs (28' CLR RDWY, 75 DEG CROSSING) (W/O ASPHALT) 2      EACH 8,500.00 17,000.00 17,000.00 34,000.00 15,000.00 30,000.00
0048 NS-804-00001 Vibration Monitoring 39      EACH 260.00 10,140.00 200.00 7,800.00 250.00 9,750.00
0049 NS-727-00002 Temporary Construction Matting 1      LUMP 10,000.00 10,000.00 10,000.00 10,000.00 30,000.00 30,000.00
                     
    CONTRACTOR TOTAL       1,752,717.84   1,799,869.93   2,108,146.95