Bid Tabulations
Letting of
06/29/2011
LA DOTD Headquarters
| Lead Project: 690-02-0006 | |
| Parish: Tangipahoa | |
| Routes: I-55 | |
| Description: REST AREA IMPROVEMENTS I-55 AT KENTWOOD | |
| Type Const: GRADING, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, SIDEWALKS, BUILDING CONSTRUCTION, LANDSCAPING AND RELATED WORK. | |
| Estimated Construction Cost: $10,250,102.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12198 | Byron E. Talbot Contractor, Inc. | $7,149,950.50 |
| 2 | 54077 | FHP Tectonics Corp. | $7,388,888.00 |
| 3 | 48896 | Command Construction Industries LLC | $8,039,000.00 |
| 4 | 14422 | T. L. Wallace Construction, Inc. | $8,088,690.50 |
| 5 | 36961 | Cycle Construction Co. L.L.C. | $8,594,110.00 |
| 6 | 39462 | Jb James Construction Llc | $9,195,000.00 |
| 7 | 38936 | Southern Industrial Contractors Llc | $11,645,000.00 |
| 39594 | Arrighi Construction LLC | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Byron E. Talbot Contractor, Inc. |
- 2 - FHP Tectonics Corp. |
- 3 - Command Construction Industries LLC |
- 4 - T. L. Wallace Construction, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | NS-MSC-00261 | Rest Area Improvements | 1 | LUMP | 7,149,950.50 | 7,149,950.50 | 7,388,888.00 | 7,388,888.00 | 8,039,000.00 | 8,039,000.00 | 8,088,690.50 | 8,088,690.50 |
| CONTRACTOR TOTAL | 7,149,950.50 | 7,388,888.00 | 8,039,000.00 | 8,088,690.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Cycle Construction Co. L.L.C. |
- 6 - Jb James Construction Llc |
- 7 - Southern Industrial Contractors Llc |
Arrighi Construction LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | NS-MSC-00261 | Rest Area Improvements | 1 | LUMP | 8,594,110.00 | 8,594,110.00 | 9,195,000.00 | 9,195,000.00 | 11,645,000.00 | 11,645,000.00 | 6,593,000.00 | 6,593,000.00 |
| CONTRACTOR TOTAL | 8,594,110.00 | 9,195,000.00 | 11,645,000.00 | IRREGULAR | ||||||||