Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 600-90-0166 | |
| Parish: East Baton Rouge | |
| Routes: | |
| Description: HQTS Annex Back-Up A/C Unit, Generator & Distr. Panel | |
| Type Const: Furnish and install back-up a/c unit, generator and distribution panel & related work | |
| Estimated Construction Cost: $312,500.00 | |
| Maximum Number of Days Allowed for Construction: 120 | |
| Calculated Daily User Cost: $270.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 08470 | Diamond Electrical Co., Inc. | $239,900.00 | 120 | $272,300.00 |
| 2 | 22027 | Sun Elect. & Instrumentation Inc. | $279,753.00 | 120 | $312,153.00 |
| 04515 | Buffalo Electric Inc | IRREGULAR | IRREGULAR | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond Electrical Co., Inc. |
- 2 - Sun Elect. & Instrumentation Inc. |
Buffalo Electric Inc |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | NS-MNT-00103 | Backup Chiller | 1 | LUMP | 133,000.00 | 133,000.00 | 162,761.00 | 162,761.00 | 135,910.00 | 135,910.00 |
| 0002 | NS-MNT-00104 | Generator | 1 | LUMP | 83,400.00 | 83,400.00 | 99,500.00 | 99,500.00 | 87,850.00 | 87,850.00 |
| 0003 | NS-MNT-00105 | Distribution Panel | 1 | LUMP | 23,500.00 | 23,500.00 | 17,492.00 | 17,492.00 | 10,775.00 | 10,775.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 239,900.00 | 279,753.00 | 234,535.00 | |||||||
| NUMBER OF DAYS BID AT $270 PER DAY. | 32,400.00 | 32,400.00 | 0.00 | |||||||
| TOTAL BID | 272,300.00 | 312,153.00 | 234,535.00 | |||||||