Bid Tabulations
Letting of
06/29/2011
LA DOTD Headquarters
| Lead Project: 455-05-0125 | |
| Parish: Rapides, Natchitoches | |
| Routes: I-49 | |
| Description: I-49 CONCRETE PAVEMENT RE-HAB | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, FULL DEPTH PATCHING OF JOINTED CONCRETE PAVEMENT, GUARD RAIL, RAISING AND UNDERSEALING CONCRETE SLABS, AND RELATED WORK. | |
| Estimated Construction Cost: $3,903,919.42 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $3,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 30774 | Progressive Construction Co., LLC | $2,997,807.30 | 180 | $3,537,807.30 |
| 2 | 21982 | Forby Contracting, Inc. | $3,400,827.55 | 80 | $3,640,827.55 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $3,773,525.00 | 150 | $4,223,525.00 |
| 4 | 46547 | Interstate Improvement, Inc. | $4,355,532.55 | 75 | $4,580,532.55 |
| 5 | 24901 | Hard Rock Construction Co. | $5,155,470.00 | 90 | $5,425,470.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Progressive Construction Co., LLC |
- 2 - Forby Contracting, Inc. |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Interstate Improvement, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 3,710 | LNFT | 5.00 | 18,550.00 | 6.00 | 22,260.00 | 10.00 | 37,100.00 | 3.00 | 11,130.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 140 | CUYD | 20.00 | 2,800.00 | 35.00 | 4,900.00 | 60.00 | 8,400.00 | 40.00 | 5,600.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 3,307 | TON | 103.00 | 340,621.00 | 150.00 | 496,050.00 | 160.00 | 529,120.00 | 155.00 | 512,585.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 11,600 | SQYD | 4.40 | 51,040.00 | 5.00 | 58,000.00 | 5.00 | 58,000.00 | 5.00 | 58,000.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -270 | CUYD | 0.01 | -2.70 | 0.01 | -2.70 | 1.00 | -270.00 | 0.01 | -2.70 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 800 | SQYD | 61.50 | 49,200.00 | 80.00 | 64,000.00 | 75.00 | 60,000.00 | 25.00 | 20,000.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 800 | SQYD | 70.50 | 56,400.00 | 100.00 | 80,000.00 | 125.00 | 100,000.00 | 50.00 | 40,000.00 |
| 0008 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 30,000 | LNFT | 1.45 | 43,500.00 | 3.00 | 90,000.00 | 1.50 | 45,000.00 | 2.50 | 75,000.00 |
| 0009 | 602-03-00100 | Cleaning and Sealing Random cracks | 8,000 | LNFT | 3.00 | 24,000.00 | 5.00 | 40,000.00 | 7.50 | 60,000.00 | 3.50 | 28,000.00 |
| 0010 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 3,200 | SQYD | 165.00 | 528,000.00 | 170.00 | 544,000.00 | 190.00 | 608,000.00 | 225.00 | 720,000.00 |
| 0011 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 3,200 | SQYD | 165.00 | 528,000.00 | 150.00 | 480,000.00 | 170.00 | 544,000.00 | 225.00 | 720,000.00 |
| 0012 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 3,200 | SQYD | 165.00 | 528,000.00 | 140.00 | 448,000.00 | 180.00 | 576,000.00 | 225.00 | 720,000.00 |
| 0013 | 704-03-00100 | Blocked Out Guard Rail | 2,975 | LNFT | 19.75 | 58,756.25 | 16.75 | 49,831.25 | 19.00 | 56,525.00 | 16.75 | 49,831.25 |
| 0014 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 175 | LNFT | 44.75 | 7,831.25 | 38.00 | 6,650.00 | 42.00 | 7,350.00 | 38.00 | 6,650.00 |
| 0015 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 350 | LNFT | 62.35 | 21,822.50 | 53.00 | 18,550.00 | 60.00 | 21,000.00 | 53.00 | 18,550.00 |
| 0016 | 704-11-00100 | Guard Rail End Treatment (Flared) | 14 | EACH | 2,350.00 | 32,900.00 | 2,000.00 | 28,000.00 | 2,300.00 | 32,200.00 | 2,000.00 | 28,000.00 |
| 0017 | 707-01-00100 | Concrete Curb | 90 | LNFT | 25.00 | 2,250.00 | 50.00 | 4,500.00 | 100.00 | 9,000.00 | 50.00 | 4,500.00 |
| 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 47,000.00 | 47,000.00 | 230,000.00 | 230,000.00 | 250,000.00 | 250,000.00 | 550,000.00 | 550,000.00 |
| 0019 | 727-01-00100 | Mobilization | 1 | LUMP | 130,000.00 | 130,000.00 | 352,000.00 | 352,000.00 | 290,000.00 | 290,000.00 | 325,000.00 | 325,000.00 |
| 0020 | 729-16-00300 | Object Marker Assembly (Type 3) | 14 | EACH | 83.50 | 1,169.00 | 71.00 | 994.00 | 80.00 | 1,120.00 | 71.00 | 994.00 |
| 0021 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 4,400.00 | 4,400.00 | 4,000.00 | 4,000.00 | 3,400.00 | 3,400.00 | 4,000.00 | 4,000.00 |
| 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 1,100.00 | 1,100.00 | 1,000.00 | 1,000.00 | 980.00 | 980.00 | 1,000.00 | 1,000.00 |
| 0023 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 1,350.00 | 1,350.00 | 1,095.00 | 1,095.00 | 1,200.00 | 1,200.00 | 1,095.00 | 1,095.00 |
| 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 |
| 0025 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 80,000 | INLF | 0.75 | 60,000.00 | 0.10 | 8,000.00 | 0.40 | 32,000.00 | 0.75 | 60,000.00 |
| 0026 | NS-602-00003 | Raising and/or Under-sealing Concrete Slabs (Polyurethane) | 76,000 | LB | 5.12 | 389,120.00 | 4.00 | 304,000.00 | 4.90 | 372,400.00 | 4.35 | 330,600.00 |
| 0027 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 10,000.00 | 40,000.00 | 10,000.00 | 40,000.00 | 14,000.00 | 56,000.00 | 10,000.00 | 40,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 2,997,807.30 | 3,400,827.55 | 3,773,525.00 | 4,355,532.55 | ||||||||
| NUMBER OF DAYS BID AT $3000 PER DAY. | 540,000.00 | 240,000.00 | 450,000.00 | 225,000.00 | ||||||||
| TOTAL BID | 3,537,807.30 | 3,640,827.55 | 4,223,525.00 | 4,580,532.55 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Hard Rock Construction Co. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 3,710 | LNFT | 3.00 | 11,130.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 140 | CUYD | 50.00 | 7,000.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 3,307 | TON | 170.00 | 562,190.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 11,600 | SQYD | 10.00 | 116,000.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -270 | CUYD | 1.00 | -270.00 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 800 | SQYD | 150.00 | 120,000.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 800 | SQYD | 200.00 | 160,000.00 |
| 0008 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 30,000 | LNFT | 3.00 | 90,000.00 |
| 0009 | 602-03-00100 | Cleaning and Sealing Random cracks | 8,000 | LNFT | 3.00 | 24,000.00 |
| 0010 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 3,200 | SQYD | 240.00 | 768,000.00 |
| 0011 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 3,200 | SQYD | 240.00 | 768,000.00 |
| 0012 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 3,200 | SQYD | 240.00 | 768,000.00 |
| 0013 | 704-03-00100 | Blocked Out Guard Rail | 2,975 | LNFT | 20.00 | 59,500.00 |
| 0014 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 175 | LNFT | 30.00 | 5,250.00 |
| 0015 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 350 | LNFT | 80.00 | 28,000.00 |
| 0016 | 704-11-00100 | Guard Rail End Treatment (Flared) | 14 | EACH | 2,100.00 | 29,400.00 |
| 0017 | 707-01-00100 | Concrete Curb | 90 | LNFT | 35.00 | 3,150.00 |
| 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 600,000.00 | 600,000.00 |
| 0019 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 |
| 0020 | 729-16-00300 | Object Marker Assembly (Type 3) | 14 | EACH | 80.00 | 1,120.00 |
| 0021 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 4,000.00 | 4,000.00 |
| 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 1,000.00 | 1,000.00 |
| 0023 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 1,200.00 | 1,200.00 |
| 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 140,000.00 | 140,000.00 |
| 0025 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 80,000 | INLF | 1.00 | 80,000.00 |
| 0026 | NS-602-00003 | Raising and/or Under-sealing Concrete Slabs (Polyurethane) | 76,000 | LB | 5.00 | 380,000.00 |
| 0027 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 7,200.00 | 28,800.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 5,155,470.00 | |||||
| NUMBER OF DAYS BID AT $3000 PER DAY. | 270,000.00 | |||||
| TOTAL BID | 5,425,470.00 | |||||