Bid Tabulations
Letting of
08/31/2011
LA DOTD Headquarters
| Lead Project: 454-02-0074 | |
| Parish: Livingston | |
| Routes: I-12 | |
| Description: LA 1026 - LA 447 | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC PAVEMENT, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, BRIDGE WIDENING, ROADWAY LIGHTING, AND RELATED WORK. | |
| Estimated Construction Cost: $29,992,508.19 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $21,946,038.20 | 425 | $24,071,038.20 |
| 2 | 34567 | James Construction Group LLC | $22,661,901.20 | 390 | $24,611,901.20 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $24,447,835.63 | 465 | $26,772,835.63 |
| 4 | 39462 | Jb James Construction Llc | $25,627,933.70 | 540 | $28,327,933.70 |
| 5 | 00481 | Coastal Bridge Co., L.L.C. | $36,457,738.98 | 500 | $38,957,738.98 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - James Construction Group LLC |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Jb James Construction Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 | 200,000.00 | 200,000.00 | 280,000.00 | 280,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 100,000.00 | 100,000.00 | 50,000.00 | 50,000.00 | 150,000.00 | 150,000.00 | 100,000.00 | 100,000.00 |
| 0003 | 202-02-00010 | Removal of Incidental Concrete Pavement (Under Median Guardrail at Juban Rd. Approx 1120 SQ.YD) | 1 | EACH | 10,000.00 | 10,000.00 | 1,125.00 | 1,125.00 | 10,000.00 | 10,000.00 | 16,000.00 | 16,000.00 |
| 0004 | 202-02-02020 | Removal of Asphalt Pavement | 1,311.1 | SQYD | 6.00 | 7,866.60 | 1.00 | 1,311.10 | 7.00 | 9,177.70 | 7.00 | 9,177.70 |
| 0005 | 202-02-06000 | Removal of Concrete Approach Slabs | 212 | SQYD | 21.00 | 4,452.00 | 100.00 | 21,200.00 | 100.00 | 21,200.00 | 20.00 | 4,240.00 |
| 0006 | 202-02-06060 | Removal of Concrete Catch Basin | 14 | EACH | 1,000.00 | 14,000.00 | 625.00 | 8,750.00 | 650.00 | 9,100.00 | 500.00 | 7,000.00 |
| 0007 | 202-02-14500 | Removal of Guard Rail | 1,729 | LNFT | 1.00 | 1,729.00 | 3.45 | 5,965.05 | 10.00 | 17,290.00 | 4.00 | 6,916.00 |
| 0008 | 202-02-32000 | Removal of Paved Ditches (Approx. 10 SQ.YD RT of Sta 556+90 - 557+12) | 10 | SQYD | 100.00 | 1,000.00 | 45.00 | 450.00 | 100.00 | 1,000.00 | 40.00 | 400.00 |
| 0009 | 202-02-32100 | Removal of Pipe (Cross Drain) End Joints of Median Cross Drains | 104 | LNFT | 150.00 | 15,600.00 | 7.20 | 748.80 | 43.88 | 4,563.52 | 30.00 | 3,120.00 |
| 0010 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 7,275 | SQYD | 10.00 | 72,750.00 | 8.00 | 58,200.00 | 11.00 | 80,025.00 | 9.00 | 65,475.00 |
| 0011 | 202-02-38240 | Removal of Signs and Supports | 34 | EACH | 210.00 | 7,140.00 | 265.00 | 9,010.00 | 275.00 | 9,350.00 | 250.00 | 8,500.00 |
| 0012 | 202-02-38300 | Removal of Sign and U-Channel Post | 10 | EACH | 1.10 | 11.00 | 110.00 | 1,100.00 | 115.00 | 1,150.00 | 100.00 | 1,000.00 |
| 0013 | 202-02-38360 | Removal of Sign Faces | 15 | EACH | 110.00 | 1,650.00 | 160.00 | 2,400.00 | 165.00 | 2,475.00 | 150.00 | 2,250.00 |
| 0014 | 202-02-38500 | Removal of Surfacing and Stablized Base | 15,466.7 | SQYD | 1.00 | 15,466.70 | 1.60 | 24,746.72 | 2.00 | 30,933.40 | 3.50 | 54,133.45 |
| 0015 | 203-01-00100 | General Excavation | 21,740 | CUYD | 5.00 | 108,700.00 | 6.00 | 130,440.00 | 4.00 | 86,960.00 | 8.80 | 191,312.00 |
| 0016 | 203-02-00100 | Drainage Excavation | 1,224 | CUYD | 40.00 | 48,960.00 | 17.00 | 20,808.00 | 15.00 | 18,360.00 | 12.00 | 14,688.00 |
| 0017 | 203-03-00100 | Embankment | 34,781 | CUYD | 20.00 | 695,620.00 | 17.00 | 591,277.00 | 22.00 | 765,182.00 | 17.00 | 591,277.00 |
| 0018 | 203-08-00100 | Geotextile Fabric (RT of Sta 556+90 - 557+12) | 75 | SQYD | 10.00 | 750.00 | 3.50 | 262.50 | 1.00 | 75.00 | 5.00 | 375.00 |
| 0019 | 204-02-00100 | Temporary Hay or Straw Bales | 500 | EACH | 11.00 | 5,500.00 | 14.00 | 7,000.00 | 16.00 | 8,000.00 | 10.00 | 5,000.00 |
| 0020 | 204-06-00100 | Temporary Silt Fencing | 38,240 | LNFT | 0.25 | 9,560.00 | 2.40 | 91,776.00 | 1.00 | 38,240.00 | 1.30 | 49,712.00 |
| 0022 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 86,540.6 | SQYD | 5.00 | 432,703.00 | 10.00 | 865,406.00 | 10.00 | 865,406.00 | 9.00 | 778,865.40 |
| 0024 | 304-05-00100 | Lime Treatment (Type E) | 1,529.77 | TON | 50.00 | 76,488.50 | 275.00 | 420,686.75 | 75.00 | 114,732.75 | 150.00 | 229,465.50 |
| 0025 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 9,795.1 | TON | 110.00 | 1,077,461.00 | 129.00 | 1,263,567.90 | 122.00 | 1,195,002.20 | 130.00 | 1,273,363.00 |
| 0026 | 501-02-00001 | Tack Coat | 38,980.4 | GAL | 3.00 | 116,941.20 | 3.37 | 131,363.95 | 3.00 | 116,941.20 | 3.50 | 136,431.40 |
| 0027 | 502-01-00100 | Superpave Asphaltic Concrete | 107,167.2 | TON | 72.00 | 7,716,038.40 | 71.00 | 7,608,871.20 | 67.00 | 7,180,202.40 | 73.00 | 7,823,205.60 |
| 0028 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 458.3 | TON | 72.00 | 32,997.60 | 127.00 | 58,204.10 | 120.00 | 54,996.00 | 130.00 | 59,579.00 |
| 0029 | 509-01-00100 | Cold Planing Asphaltic Pavement | 103,573 | SQYD | 1.10 | 113,930.30 | 1.12 | 116,001.76 | 0.50 | 51,786.50 | 1.30 | 134,644.90 |
| 0030 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,316 | CUYD | 10.00 | -43,160.00 | 0.10 | -431.60 | 1.00 | -4,316.00 | 0.10 | -431.60 |
| 0031 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 708 | LNFT | 40.00 | 28,320.00 | 72.00 | 50,976.00 | 67.00 | 47,436.00 | 50.00 | 35,400.00 |
| 0032 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 800 | LNFT | 62.00 | 49,600.00 | 98.00 | 78,400.00 | 95.00 | 76,000.00 | 60.00 | 48,000.00 |
| 0033 | 701-15-00100 | Concrete Collar | 1 | EACH | 3,000.00 | 3,000.00 | 1,570.00 | 1,570.00 | 1,000.00 | 1,000.00 | 600.00 | 600.00 |
| 0034 | 702-03-00100 | Catch Basins (CB-01) | 9 | EACH | 3,500.00 | 31,500.00 | 3,450.00 | 31,050.00 | 3,500.00 | 31,500.00 | 2,500.00 | 22,500.00 |
| 0035 | 703-01-00100 | Shoulder Underdrain Systems | 3,150 | LNFT | 6.00 | 18,900.00 | 9.00 | 28,350.00 | 12.00 | 37,800.00 | 10.00 | 31,500.00 |
| 0036 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 250.4 | LNFT | 51.00 | 12,770.40 | 50.00 | 12,520.00 | 54.00 | 13,521.60 | 50.00 | 12,520.00 |
| 0037 | 704-03-00100 | Blocked Out Guard Rail | 1,100 | LNFT | 15.00 | 16,500.00 | 20.00 | 22,000.00 | 15.00 | 16,500.00 | 15.00 | 16,500.00 |
| 0038 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 50.4 | LNFT | 52.00 | 2,620.80 | 88.00 | 4,435.20 | 54.00 | 2,721.60 | 55.00 | 2,772.00 |
| 0039 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 26.00 | 1,300.00 | 25.00 | 1,250.00 | 25.00 | 1,250.00 | 25.00 | 1,250.00 |
| 0040 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 62.00 | 12,400.00 | 60.00 | 12,000.00 | 65.00 | 13,000.00 | 65.00 | 13,000.00 |
| 0041 | 704-11-00100 | Guard Rail End Treatment (Flared) | 10 | EACH | 2,100.00 | 21,000.00 | 220.00 | 2,200.00 | 2,200.00 | 22,000.00 | 2,200.00 | 22,000.00 |
| 0042 | 707-01-00100 | Concrete Curb | 40 | LNFT | 22.00 | 880.00 | 17.00 | 680.00 | 50.00 | 2,000.00 | 15.00 | 600.00 |
| 0043 | 710-01-00100 | Flowable Fill | 332 | CUYD | 140.00 | 46,480.00 | 180.00 | 59,760.00 | 112.00 | 37,184.00 | 150.00 | 49,800.00 |
| 0044 | 711-01-03040 | Riprap (30 lb, 24" Thick) (RT. of Sta 556+90 - 557+12) | 50 | SQYD | 700.00 | 35,000.00 | 78.00 | 3,900.00 | 70.00 | 3,500.00 | 110.00 | 5,500.00 |
| 0045 | 712-04-00100 | Flexible Revetment | 2,630 | SQYD | 57.00 | 149,910.00 | 58.00 | 152,540.00 | 35.00 | 92,050.00 | 54.00 | 142,020.00 |
| 0046 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 600,000.00 | 600,000.00 | 100,000.00 | 100,000.00 | 700,000.00 | 700,000.00 | 200,000.00 | 200,000.00 |
| 0047 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.121 | MILE | 120.00 | 1,574.52 | 235.00 | 3,083.44 | 335.00 | 4,395.54 | 300.00 | 3,936.30 |
| 0048 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 0.152 | MILE | 3,000.00 | 456.00 | 2,950.00 | 448.40 | 3,200.00 | 486.40 | 3,000.00 | 456.00 |
| 0049 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.121 | MILE | 325.00 | 4,264.33 | 300.00 | 3,936.30 | 335.00 | 4,395.54 | 300.00 | 3,936.30 |
| 0050 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.152 | MILE | 4,200.00 | 638.40 | 4,000.00 | 608.00 | 4,450.00 | 676.40 | 4,000.00 | 608.00 |
| 0051 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 26.242 | MILE | 525.00 | 13,777.05 | 500.00 | 13,121.00 | 550.00 | 14,433.10 | 500.00 | 13,121.00 |
| 0052 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.152 | MILE | 9,750.00 | 1,482.00 | 9,600.00 | 1,459.20 | 10,750.00 | 1,634.00 | 10,000.00 | 1,520.00 |
| 0053 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,760 | EACH | 3.50 | 6,160.00 | 3.35 | 5,896.00 | 3.75 | 6,600.00 | 3.50 | 6,160.00 |
| 0054 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 1,667 | EACH | 50.00 | 83,350.00 | 290.00 | 483,430.00 | 225.00 | 375,075.00 | 780.00 | 1,300,260.00 |
| 0055 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 782 | EACH | 50.00 | 39,100.00 | 195.00 | 152,490.00 | 165.00 | 129,030.00 | 180.00 | 140,760.00 |
| 0056 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 130 | EACH | 50.00 | 6,500.00 | 17.00 | 2,210.00 | 60.00 | 7,800.00 | 110.00 | 14,300.00 |
| 0057 | 721-01-00100 | Mowing | 271.6 | ACRE | 200.00 | 54,320.00 | 35.00 | 9,506.00 | 50.00 | 13,580.00 | 100.00 | 27,160.00 |
| 0058 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 40,000.00 | 40,000.00 | 10,000.00 | 10,000.00 | 35,000.00 | 35,000.00 | 20,000.00 | 20,000.00 |
| 0059 | 726-01-00100 | Bedding Material | 264.9 | CUYD | 57.00 | 15,099.30 | 38.00 | 10,066.20 | 72.71 | 19,260.88 | 65.00 | 17,218.50 |
| 0060 | 727-01-00100 | Mobilization | 1 | LUMP | 1,375,000.00 | 1,375,000.00 | 1,650,000.00 | 1,650,000.00 | 2,000,000.00 | 2,000,000.00 | 2,500,000.00 | 2,500,000.00 |
| 0061 | 729-01-00100 | Sign (Type A) | 376 | SQFT | 24.00 | 9,024.00 | 27.00 | 10,152.00 | 27.00 | 10,152.00 | 26.00 | 9,776.00 |
| 0062 | 729-04-00100 | Sign (Type D) | 80 | SQFT | 25.50 | 2,040.00 | 27.00 | 2,160.00 | 27.00 | 2,160.00 | 26.00 | 2,080.00 |
| 0063 | 729-05-00100 | Sign (Type E) | 196 | SQFT | 25.50 | 4,998.00 | 27.00 | 5,292.00 | 27.00 | 5,292.00 | 26.00 | 5,096.00 |
| 0064 | 729-06-00100 | Sign (Overhead Mounted) | 1,433 | SQFT | 25.50 | 36,541.50 | 32.00 | 45,856.00 | 33.00 | 47,289.00 | 32.00 | 45,856.00 |
| 0065 | 729-08-00200 | Mounting (3 1/2" Size Post) | 14 | EACH | 900.00 | 12,600.00 | 850.00 | 11,900.00 | 880.00 | 12,320.00 | 850.00 | 11,900.00 |
| 0066 | 729-08-00210 | Mounting (3 1/2" Size Post)(Structure Mount) | 6 | EACH | 1,450.00 | 8,700.00 | 740.00 | 4,440.00 | 775.00 | 4,650.00 | 750.00 | 4,500.00 |
| 0067 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 8 | EACH | 950.00 | 7,600.00 | 1,270.00 | 10,160.00 | 1,250.00 | 10,000.00 | 1,300.00 | 10,400.00 |
| 0068 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 8 | EACH | 28,500.00 | 228,000.00 | 25,000.00 | 200,000.00 | 25,000.00 | 200,000.00 | 24,000.00 | 192,000.00 |
| 0069 | 729-16-00300 | Object Marker Assembly (Type 3) | 15 | EACH | 70.00 | 1,050.00 | 85.00 | 1,275.00 | 83.00 | 1,245.00 | 70.00 | 1,050.00 |
| 0070 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 6 | EACH | 155.00 | 930.00 | 265.00 | 1,590.00 | 275.00 | 1,650.00 | 260.00 | 1,560.00 |
| 0071 | 729-18-00200 | Milepost Assembly (Structure Mounted) (Secondary) | 28 | EACH | 155.00 | 4,340.00 | 265.00 | 7,420.00 | 275.00 | 7,700.00 | 260.00 | 7,280.00 |
| 0072 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 8 | EACH | 19,500.00 | 156,000.00 | 16,000.00 | 128,000.00 | 21,000.00 | 168,000.00 | 18,000.00 | 144,000.00 |
| 0073 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") 2 #2 XHHW-2, 1 #2 Bare Solid Ground | 2,100 | LNFT | 11.00 | 23,100.00 | 8.00 | 16,800.00 | 11.40 | 23,940.00 | 11.00 | 23,100.00 |
| 0074 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") Empty Conduit w/Pull Line | 3,600 | LNFT | 3.10 | 11,160.00 | 1.25 | 4,500.00 | 3.15 | 11,340.00 | 3.30 | 11,880.00 |
| 0075 | 730-03-01060 | Conductors in Existing Conduit (PVC/HDPE) (1 1/4") 2 #8 XHHW-2, 1 #8 Bare Solid Ground | 335 | LNFT | 10.50 | 3,517.50 | 4.75 | 1,591.25 | 3.15 | 1,055.25 | 11.00 | 3,685.00 |
| 0076 | 730-03-01060 | Conductors in Existing Conduit (PVC/HDPE) (1 1/4") 2 #2 XHHW-2, 1 #2 Bare Solid Ground | 55 | LNFT | 6.70 | 368.50 | 9.25 | 508.75 | 10.00 | 550.00 | 7.00 | 385.00 |
| 0077 | 730-03-01080 | Conductors in Existing Conduit (PVC/HDPE) (1 1/2") 2 #2 XHHW-2, 2 #8 XHHW-2, 1 #2 Bare Solid Ground | 1,450 | LNFT | 13.00 | 18,850.00 | 9.65 | 13,992.50 | 7.75 | 11,237.50 | 14.00 | 20,300.00 |
| 0078 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) | 600 | LNFT | 31.00 | 18,600.00 | 25.00 | 15,000.00 | 35.00 | 21,000.00 | 32.00 | 19,200.00 |
| 0079 | 730-05-22220 | Light Pole (50') (Aluminum) (Twin Arm) (Lowering Device) | 8 | EACH | 12,000.00 | 96,000.00 | 11,150.00 | 89,200.00 | 1,400.00 | 11,200.00 | 13,000.00 | 104,000.00 |
| 0080 | 730-07-06000 | Luminaire (400 Watt) (High PressureSodium) | 16 | EACH | 2,500.00 | 40,000.00 | 2,300.00 | 36,800.00 | 1,100.00 | 17,600.00 | 2,500.00 | 40,000.00 |
| 0081 | 730-09-00100 | Electrical System | 1 | LUMP | 610.00 | 610.00 | 550.00 | 550.00 | 4,000.00 | 4,000.00 | 650.00 | 650.00 |
| 0082 | 730-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 510.00 | 510.00 | 475.00 | 475.00 | 1,400.00 | 1,400.00 | 530.00 | 530.00 |
| 0083 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) Steel with Brkwy. Trans. Base, 50' | 4 | EACH | 310.00 | 1,240.00 | 285.00 | 1,140.00 | 515.00 | 2,060.00 | 320.00 | 1,280.00 |
| 0084 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 6 | EACH | 540.00 | 3,240.00 | 500.00 | 3,000.00 | 575.00 | 3,450.00 | 550.00 | 3,300.00 |
| 0085 | 730-14-00100 | Removal and Disposal of Luminaires | 8 | EACH | 67.00 | 536.00 | 60.00 | 480.00 | 6.50 | 52.00 | 70.00 | 560.00 |
| 0086 | 730-16-00200 | Underground Junction Box (11" x 18") | 22 | EACH | 410.00 | 9,020.00 | 270.00 | 5,940.00 | 345.00 | 7,590.00 | 440.00 | 9,680.00 |
| 0087 | 730-16-00300 | Underground Junction Box (13" x 24") | 4 | EACH | 500.00 | 2,000.00 | 335.00 | 1,340.00 | 785.00 | 3,140.00 | 500.00 | 2,000.00 |
| 0088 | 730-19-00010 | Modular Breakaway Cable System | 7 | EACH | 1,900.00 | 13,300.00 | 1,760.00 | 12,320.00 | 2,000.00 | 14,000.00 | 2,000.00 | 14,000.00 |
| 0089 | 730-21-00020 | Duct Marker (Concrete) | 11 | EACH | 280.00 | 3,080.00 | 260.00 | 2,860.00 | 160.00 | 1,760.00 | 280.00 | 3,080.00 |
| 0090 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 1,350 | LNFT | 0.60 | 810.00 | 0.50 | 675.00 | 0.45 | 607.50 | 0.50 | 675.00 |
| 0091 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 200 | EACH | 7.00 | 1,400.00 | 10.65 | 2,130.00 | 10.00 | 2,000.00 | 10.00 | 2,000.00 |
| 0092 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,360 | EACH | 4.50 | 10,620.00 | 4.25 | 10,030.00 | 4.75 | 11,210.00 | 4.50 | 10,620.00 |
| 0093 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.92 | MILE | 2,750.00 | 38,280.00 | 2,500.00 | 34,800.00 | 2,700.00 | 37,584.00 | 2,500.00 | 34,800.00 |
| 0094 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.685 | MILE | 5,400.00 | 3,699.00 | 5,280.00 | 3,616.80 | 5,700.00 | 3,904.50 | 5,500.00 | 3,767.50 |
| 0095 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.374 | MILE | 15,500.00 | 5,797.00 | 14,900.00 | 5,572.60 | 16,000.00 | 5,984.00 | 16,000.00 | 5,984.00 |
| 0096 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 14.03 | MILE | 900.00 | 12,627.00 | 790.00 | 11,083.70 | 880.00 | 12,346.40 | 850.00 | 11,925.50 |
| 0097 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.645 | MILE | 2,200.00 | 1,419.00 | 2,000.00 | 1,290.00 | 2,200.00 | 1,419.00 | 2,100.00 | 1,354.50 |
| 0098 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 2 | EACH | 500.00 | 1,000.00 | 400.00 | 800.00 | 445.00 | 890.00 | 420.00 | 840.00 |
| 0099 | 732-05-00100 | Removal of Existing Markings | 6.666 | MILE | 2,700.00 | 17,998.20 | 2,500.00 | 16,665.00 | 2,800.00 | 18,664.80 | 2,600.00 | 17,331.60 |
| 0100 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 19,025 | LNFT | 270.00 | 5,136,750.00 | 230.00 | 4,375,750.00 | 330.00 | 6,278,250.00 | 268.00 | 5,098,700.00 |
| 0101 | 739-01-00100 | Hydro-Seeding | 8.8 | ACRE | 1,200.00 | 10,560.00 | 1,125.00 | 9,900.00 | 1,250.00 | 11,000.00 | 1,100.00 | 9,680.00 |
| 0102 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 50,000.00 | 50,000.00 | 175,000.00 | 175,000.00 | 240,000.00 | 240,000.00 |
| 0103 | 804-01-00300 | Precast Concrete Piles (16") | 2,376 | LNFT | 92.00 | 218,592.00 | 72.00 | 171,072.00 | 64.00 | 152,064.00 | 85.00 | 201,960.00 |
| 0104 | 804-05-00300 | Precast Concrete Test Piles (16") | 1 | EACH | 22,000.00 | 22,000.00 | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 |
| 0105 | 804-09-00100 | Loading Test Piles | 1 | EACH | 22,000.00 | 22,000.00 | 2,500.00 | 2,500.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 |
| 0106 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 110.00 | 110.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 100.00 | 100.00 |
| 0107 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 110.00 | 110.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 100.00 | 100.00 |
| 0108 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,250.00 | 1,250.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0109 | 804-17-00100 | Dynamic Monitoring | 7 | EACH | 1,300.00 | 9,100.00 | 1,200.00 | 8,400.00 | 550.00 | 3,850.00 | 1,200.00 | 8,400.00 |
| 0110 | 805-01-00700 | Class A Concrete (Bents) | 83.42 | CUYD | 1,400.00 | 116,788.00 | 850.00 | 70,907.00 | 1,100.00 | 91,762.00 | 1,300.00 | 108,446.00 |
| 0111 | 805-03-00100 | Class AA Concrete | 508.8 | CUYD | 700.00 | 356,160.00 | 575.00 | 292,560.00 | 500.00 | 254,400.00 | 640.00 | 325,632.00 |
| 0112 | 805-09-00100 | Expansion Joint Seal | 1,125 | LNFT | 30.00 | 33,750.00 | 10.00 | 11,250.00 | 12.00 | 13,500.00 | 25.00 | 28,125.00 |
| 0113 | 806-01-00100 | Deformed Reinforcing Steel | 123,348 | LB | 1.10 | 135,682.80 | 1.00 | 123,348.00 | 0.70 | 86,343.60 | 1.00 | 123,348.00 |
| 0114 | 810-01-00100 | Concrete Railing (Standard Barrier) | 560 | LNFT | 78.00 | 43,680.00 | 55.00 | 30,800.00 | 70.00 | 39,200.00 | 70.00 | 39,200.00 |
| 0115 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 400 | LNFT | 78.00 | 31,200.00 | 75.00 | 30,000.00 | 70.00 | 28,000.00 | 72.00 | 28,800.00 |
| 0116 | 813-01-00100 | Concrete Approach Slabs | 1,097.76 | SQYD | 240.00 | 263,462.40 | 250.00 | 274,440.00 | 225.00 | 246,996.00 | 220.00 | 241,507.20 |
| 0117 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 404,300 | INLF | 0.01 | 4,043.00 | 0.50 | 202,150.00 | 0.01 | 4,043.00 | 0.50 | 202,150.00 |
| 0118 | NS-700-00180 | Impact Attenuator (Construction Zone) | 8 | EACH | 100.00 | 800.00 | 13,000.00 | 104,000.00 | 10,000.00 | 80,000.00 | 11,000.00 | 88,000.00 |
| 0119 | NS-700-00181 | Impact Attenuator Relocation (Construction Zone) | 8 | EACH | 100.00 | 800.00 | 3,600.00 | 28,800.00 | 1,500.00 | 12,000.00 | 1,200.00 | 9,600.00 |
| 0120 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 2,000.00 | 12,000.00 | 25,000.00 | 150,000.00 | 15,000.00 | 90,000.00 | 13,000.00 | 78,000.00 |
| 0121 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 13.333 | MILE | 700.00 | 9,333.10 | 375.00 | 4,999.88 | 550.00 | 7,333.15 | 650.00 | 8,666.45 |
| 0122 | NS-MSC-00120 | Drainage Structure Capping Catch Basins | 3 | EACH | 3,000.00 | 9,000.00 | 3,575.00 | 10,725.00 | 2,000.00 | 6,000.00 | 2,400.00 | 7,200.00 |
| 0123 | 302-02-01061 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone or Recycled Portland Cement Concrete ONLY) | 90,807.3 | SQYD | 8.00 | 726,458.40 | 10.00 | 908,073.00 | 9.00 | 817,265.70 | 10.00 | 908,073.00 |
| 0124 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone or Recycled Portland Cement Concrete ONLY) | 21,988.9 | SQYD | 23.00 | 505,744.70 | 27.50 | 604,694.75 | 25.00 | 549,722.50 | 25.00 | 549,722.50 |
| ITEM TOTAL (CONSTRUCTION BID) | 21,946,038.20 | 22,661,901.20 | 24,447,835.63 | 25,627,933.70 | ||||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 2,125,000.00 | 1,950,000.00 | 2,325,000.00 | 2,700,000.00 | ||||||||
| TOTAL BID | 24,071,038.20 | 24,611,901.20 | 26,772,835.63 | 28,327,933.70 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Coastal Bridge Co., L.L.C. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 280,000.00 | 280,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 200,000.00 | 200,000.00 |
| 0003 | 202-02-00010 | Removal of Incidental Concrete Pavement (Under Median Guardrail at Juban Rd. Approx 1120 SQ.YD) | 1 | EACH | 11,500.00 | 11,500.00 |
| 0004 | 202-02-02020 | Removal of Asphalt Pavement | 1,311.1 | SQYD | 11.00 | 14,422.10 |
| 0005 | 202-02-06000 | Removal of Concrete Approach Slabs | 212 | SQYD | 168.00 | 35,616.00 |
| 0006 | 202-02-06060 | Removal of Concrete Catch Basin | 14 | EACH | 725.00 | 10,150.00 |
| 0007 | 202-02-14500 | Removal of Guard Rail | 1,729 | LNFT | 7.00 | 12,103.00 |
| 0008 | 202-02-32000 | Removal of Paved Ditches (Approx. 10 SQ.YD RT of Sta 556+90 - 557+12) | 10 | SQYD | 580.00 | 5,800.00 |
| 0009 | 202-02-32100 | Removal of Pipe (Cross Drain) End Joints of Median Cross Drains | 104 | LNFT | 18.00 | 1,872.00 |
| 0010 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 7,275 | SQYD | 8.50 | 61,837.50 |
| 0011 | 202-02-38240 | Removal of Signs and Supports | 34 | EACH | 300.00 | 10,200.00 |
| 0012 | 202-02-38300 | Removal of Sign and U-Channel Post | 10 | EACH | 120.00 | 1,200.00 |
| 0013 | 202-02-38360 | Removal of Sign Faces | 15 | EACH | 180.00 | 2,700.00 |
| 0014 | 202-02-38500 | Removal of Surfacing and Stablized Base | 15,466.7 | SQYD | 9.00 | 139,200.30 |
| 0015 | 203-01-00100 | General Excavation | 21,740 | CUYD | 17.00 | 369,580.00 |
| 0016 | 203-02-00100 | Drainage Excavation | 1,224 | CUYD | 20.00 | 24,480.00 |
| 0017 | 203-03-00100 | Embankment | 34,781 | CUYD | 25.00 | 869,525.00 |
| 0018 | 203-08-00100 | Geotextile Fabric (RT of Sta 556+90 - 557+12) | 75 | SQYD | 1.00 | 75.00 |
| 0019 | 204-02-00100 | Temporary Hay or Straw Bales | 500 | EACH | 12.00 | 6,000.00 |
| 0020 | 204-06-00100 | Temporary Silt Fencing | 38,240 | LNFT | 1.50 | 57,360.00 |
| 0022 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 86,540.6 | SQYD | 12.50 | 1,081,757.50 |
| 0024 | 304-05-00100 | Lime Treatment (Type E) | 1,529.77 | TON | 300.00 | 458,931.00 |
| 0025 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 9,795.1 | TON | 175.00 | 1,714,142.50 |
| 0026 | 501-02-00001 | Tack Coat | 38,980.4 | GAL | 4.00 | 155,921.60 |
| 0027 | 502-01-00100 | Superpave Asphaltic Concrete | 107,167.2 | TON | 85.00 | 9,109,212.00 |
| 0028 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 458.3 | TON | 150.00 | 68,745.00 |
| 0029 | 509-01-00100 | Cold Planing Asphaltic Pavement | 103,573 | SQYD | 2.50 | 258,932.50 |
| 0030 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,316 | CUYD | 0.10 | -431.60 |
| 0031 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 708 | LNFT | 2.50 | 1,770.00 |
| 0032 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 800 | LNFT | 0.10 | 80.00 |
| 0033 | 701-15-00100 | Concrete Collar | 1 | EACH | 970.00 | 970.00 |
| 0034 | 702-03-00100 | Catch Basins (CB-01) | 9 | EACH | 2,800.00 | 25,200.00 |
| 0035 | 703-01-00100 | Shoulder Underdrain Systems | 3,150 | LNFT | 66.00 | 207,900.00 |
| 0036 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 250.4 | LNFT | 60.00 | 15,024.00 |
| 0037 | 704-03-00100 | Blocked Out Guard Rail | 1,100 | LNFT | 24.00 | 26,400.00 |
| 0038 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 50.4 | LNFT | 100.00 | 5,040.00 |
| 0039 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 30.00 | 1,500.00 |
| 0040 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 72.00 | 14,400.00 |
| 0041 | 704-11-00100 | Guard Rail End Treatment (Flared) | 10 | EACH | 2,500.00 | 25,000.00 |
| 0042 | 707-01-00100 | Concrete Curb | 40 | LNFT | 25.00 | 1,000.00 |
| 0043 | 710-01-00100 | Flowable Fill | 332 | CUYD | 450.00 | 149,400.00 |
| 0044 | 711-01-03040 | Riprap (30 lb, 24" Thick) (RT. of Sta 556+90 - 557+12) | 50 | SQYD | 65.00 | 3,250.00 |
| 0045 | 712-04-00100 | Flexible Revetment | 2,630 | SQYD | 74.00 | 194,620.00 |
| 0046 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,200,000.00 | 1,200,000.00 |
| 0047 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.121 | MILE | 195.00 | 2,558.60 |
| 0048 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 0.152 | MILE | 3,500.00 | 532.00 |
| 0049 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.121 | MILE | 350.00 | 4,592.35 |
| 0050 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.152 | MILE | 4,800.00 | 729.60 |
| 0051 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 26.242 | MILE | 600.00 | 15,745.20 |
| 0052 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.152 | MILE | 11,500.00 | 1,748.00 |
| 0053 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,760 | EACH | 4.00 | 7,040.00 |
| 0054 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 1,667 | EACH | 1,500.00 | 2,500,500.00 |
| 0055 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 782 | EACH | 650.00 | 508,300.00 |
| 0056 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 130 | EACH | 250.00 | 32,500.00 |
| 0057 | 721-01-00100 | Mowing | 271.6 | ACRE | 75.00 | 20,370.00 |
| 0058 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 75,000.00 | 75,000.00 |
| 0059 | 726-01-00100 | Bedding Material | 264.9 | CUYD | 1.25 | 331.13 |
| 0060 | 727-01-00100 | Mobilization | 1 | LUMP | 4,000,000.00 | 4,000,000.00 |
| 0061 | 729-01-00100 | Sign (Type A) | 376 | SQFT | 30.00 | 11,280.00 |
| 0062 | 729-04-00100 | Sign (Type D) | 80 | SQFT | 30.00 | 2,400.00 |
| 0063 | 729-05-00100 | Sign (Type E) | 196 | SQFT | 30.00 | 5,880.00 |
| 0064 | 729-06-00100 | Sign (Overhead Mounted) | 1,433 | SQFT | 30.00 | 42,990.00 |
| 0065 | 729-08-00200 | Mounting (3 1/2" Size Post) | 14 | EACH | 900.00 | 12,600.00 |
| 0066 | 729-08-00210 | Mounting (3 1/2" Size Post)(Structure Mount) | 6 | EACH | 800.00 | 4,800.00 |
| 0067 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 8 | EACH | 1,400.00 | 11,200.00 |
| 0068 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 8 | EACH | 25,000.00 | 200,000.00 |
| 0069 | 729-16-00300 | Object Marker Assembly (Type 3) | 15 | EACH | 110.00 | 1,650.00 |
| 0070 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 6 | EACH | 300.00 | 1,800.00 |
| 0071 | 729-18-00200 | Milepost Assembly (Structure Mounted) (Secondary) | 28 | EACH | 260.00 | 7,280.00 |
| 0072 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 8 | EACH | 50,000.00 | 400,000.00 |
| 0073 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") 2 #2 XHHW-2, 1 #2 Bare Solid Ground | 2,100 | LNFT | 12.00 | 25,200.00 |
| 0074 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") Empty Conduit w/Pull Line | 3,600 | LNFT | 3.50 | 12,600.00 |
| 0075 | 730-03-01060 | Conductors in Existing Conduit (PVC/HDPE) (1 1/4") 2 #8 XHHW-2, 1 #8 Bare Solid Ground | 335 | LNFT | 7.50 | 2,512.50 |
| 0076 | 730-03-01060 | Conductors in Existing Conduit (PVC/HDPE) (1 1/4") 2 #2 XHHW-2, 1 #2 Bare Solid Ground | 55 | LNFT | 12.00 | 660.00 |
| 0077 | 730-03-01080 | Conductors in Existing Conduit (PVC/HDPE) (1 1/2") 2 #2 XHHW-2, 2 #8 XHHW-2, 1 #2 Bare Solid Ground | 1,450 | LNFT | 15.00 | 21,750.00 |
| 0078 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) | 600 | LNFT | 37.00 | 22,200.00 |
| 0079 | 730-05-22220 | Light Pole (50') (Aluminum) (Twin Arm) (Lowering Device) | 8 | EACH | 15,000.00 | 120,000.00 |
| 0080 | 730-07-06000 | Luminaire (400 Watt) (High PressureSodium) | 16 | EACH | 2,900.00 | 46,400.00 |
| 0081 | 730-09-00100 | Electrical System | 1 | LUMP | 700.00 | 700.00 |
| 0082 | 730-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 600.00 | 600.00 |
| 0083 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) Steel with Brkwy. Trans. Base, 50' | 4 | EACH | 350.00 | 1,400.00 |
| 0084 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 6 | EACH | 640.00 | 3,840.00 |
| 0085 | 730-14-00100 | Removal and Disposal of Luminaires | 8 | EACH | 78.00 | 624.00 |
| 0086 | 730-16-00200 | Underground Junction Box (11" x 18") | 22 | EACH | 450.00 | 9,900.00 |
| 0087 | 730-16-00300 | Underground Junction Box (13" x 24") | 4 | EACH | 550.00 | 2,200.00 |
| 0088 | 730-19-00010 | Modular Breakaway Cable System | 7 | EACH | 2,200.00 | 15,400.00 |
| 0089 | 730-21-00020 | Duct Marker (Concrete) | 11 | EACH | 300.00 | 3,300.00 |
| 0090 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 1,350 | LNFT | 0.50 | 675.00 |
| 0091 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 200 | EACH | 12.00 | 2,400.00 |
| 0092 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,360 | EACH | 5.00 | 11,800.00 |
| 0093 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.92 | MILE | 3,000.00 | 41,760.00 |
| 0094 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.685 | MILE | 6,400.00 | 4,384.00 |
| 0095 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.374 | MILE | 18,000.00 | 6,732.00 |
| 0096 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 14.03 | MILE | 950.00 | 13,328.50 |
| 0097 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.645 | MILE | 2,400.00 | 1,548.00 |
| 0098 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 2 | EACH | 450.00 | 900.00 |
| 0099 | 732-05-00100 | Removal of Existing Markings | 6.666 | MILE | 3,000.00 | 19,998.00 |
| 0100 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 19,025 | LNFT | 420.00 | 7,990,500.00 |
| 0101 | 739-01-00100 | Hydro-Seeding | 8.8 | ACRE | 1,500.00 | 13,200.00 |
| 0102 | 740-01-00100 | Construction Layout | 1 | LUMP | 200,000.00 | 200,000.00 |
| 0103 | 804-01-00300 | Precast Concrete Piles (16") | 2,376 | LNFT | 100.00 | 237,600.00 |
| 0104 | 804-05-00300 | Precast Concrete Test Piles (16") | 1 | EACH | 33,700.00 | 33,700.00 |
| 0105 | 804-09-00100 | Loading Test Piles | 1 | EACH | 23,000.00 | 23,000.00 |
| 0106 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 1,300.00 | 1,300.00 |
| 0107 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1,300.00 | 1,300.00 |
| 0108 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,300.00 | 1,300.00 |
| 0109 | 804-17-00100 | Dynamic Monitoring | 7 | EACH | 2,400.00 | 16,800.00 |
| 0110 | 805-01-00700 | Class A Concrete (Bents) | 83.42 | CUYD | 1,800.00 | 150,156.00 |
| 0111 | 805-03-00100 | Class AA Concrete | 508.8 | CUYD | 1,000.00 | 508,800.00 |
| 0112 | 805-09-00100 | Expansion Joint Seal | 1,125 | LNFT | 38.00 | 42,750.00 |
| 0113 | 806-01-00100 | Deformed Reinforcing Steel | 123,348 | LB | 1.30 | 160,352.40 |
| 0114 | 810-01-00100 | Concrete Railing (Standard Barrier) | 560 | LNFT | 70.00 | 39,200.00 |
| 0115 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 400 | LNFT | 78.00 | 31,200.00 |
| 0116 | 813-01-00100 | Concrete Approach Slabs | 1,097.76 | SQYD | 275.00 | 301,884.00 |
| 0117 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 404,300 | INLF | 0.10 | 40,430.00 |
| 0118 | NS-700-00180 | Impact Attenuator (Construction Zone) | 8 | EACH | 11,500.00 | 92,000.00 |
| 0119 | NS-700-00181 | Impact Attenuator Relocation (Construction Zone) | 8 | EACH | 1,500.00 | 12,000.00 |
| 0120 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 17,000.00 | 102,000.00 |
| 0121 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 13.333 | MILE | 1,000.00 | 13,333.00 |
| 0122 | NS-MSC-00120 | Drainage Structure Capping Catch Basins | 3 | EACH | 970.00 | 2,910.00 |
| 0123 | 302-02-01061 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone or Recycled Portland Cement Concrete ONLY) | 90,807.3 | SQYD | 9.00 | 817,265.70 |
| 0124 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) (Stone or Recycled Portland Cement Concrete ONLY) | 21,988.9 | SQYD | 24.00 | 527,733.60 |
| ITEM TOTAL (CONSTRUCTION BID) | 36,457,738.98 | |||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 2,500,000.00 | |||||
| TOTAL BID | 38,957,738.98 | |||||