Bid Tabulations
Letting of
03/31/2010
LA DOTD Headquarters
| Lead Project: 453-01-0060 | |
| Parish: St. Tammany | |
| Routes: I-59 | |
| Description: I-59 PAVEMENT MARKER REPLACEMENT | |
| Type Const: PAVEMENT MARKER REPLACEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $37,165.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 23811 | Highway Technologies Inc | $29,794.00 |
| 2 | 47954 | Stripe-A-Zone Inc | $32,000.00 |
| 3 | 48416 | Southern Synergy LLC | $37,112.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Highway Technologies Inc |
- 2 - Stripe-A-Zone Inc |
- 3 - Southern Synergy LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000.00 | 1,000.00 | 3,800.00 | 3,800.00 | 2,000.00 | 2,000.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 3,000.00 | 3,000.00 | 1,500.00 | 1,500.00 | 2,000.00 | 2,000.00 |
| 0003 | 731-02-00100 | Reflectorized Raised Pavement Markers | 6,550 | EACH | 3.48 | 22,794.00 | 4.00 | 26,200.00 | 4.75 | 31,112.50 |
| 0004 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 1,500.00 | 3,000.00 | 250.00 | 500.00 | 1,000.00 | 2,000.00 |
| CONTRACTOR TOTAL | 29,794.00 | 32,000.00 | 37,112.50 | |||||||