LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 451-06-0152
Parish: Ouachita
Routes: I-20
Description: END ELEVATED SECTION TO EAST OF GARRETT ROAD
Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT,PAVEMENT PATCHING, AND RELATED WORK.
Estimated Construction Cost: $13,704,232.25
Maximum Number of Days Allowed for Construction: 300
Calculated Daily User Cost: $15,000.00


RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 12312 Gilchrist Construction Co. LLC $14,733,829.68 253 $18,528,829.68
2 05789 D & J Construction Co., Inc. $15,284,411.00 275 $19,409,411.00
3 12487 Diamond B Construction Co., L.L.C. $15,805,661.72 300 $20,305,661.72


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Gilchrist Construction Co. LLC
- 2 -
D & J Construction Co., Inc.
- 3 -
Diamond B Construction Co., L.L.C.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-01-00100 Removal of Structures and Obstructions 1      LUMP 15,000.00 15,000.00 12,000.00 12,000.00 6,900.00 6,900.00
0002 202-02-02020 Removal of Asphalt Pavement 8,030.4    SQYD 6.20 49,788.48 8.00 64,243.20 11.00 88,334.40
0003 202-02-14500 Removal of Guard Rail 1,857      LNFT 12.00 22,284.00 18.00 33,426.00 4.00 7,428.00
0004 202-03-38000 Relocation of Sign (As neccessary within work zone) 24      EACH 500.00 12,000.00 500.00 12,000.00 490.00 11,760.00
0005 203-07-00100 Borrow (Vehicular Measurement) 10,172      CUYD 25.00 254,300.00 22.00 223,784.00 17.25 175,467.00
0006 204-02-00100 Temporary Hay or Straw Bales 100      EACH 20.00 2,000.00 30.00 3,000.00 8.00 800.00
0007 204-05-00100 Temporary Sediment Check Dams (Hay) 138      EACH 240.00 33,120.00 175.00 24,150.00 185.00 25,530.00
0008 204-06-00100 Temporary Silt Fencing 11,776      LNFT 1.50 17,664.00 0.75 8,832.00 3.75 44,160.00
0009 502-01-00100 Superpave Asphaltic Concrete 75,110.6    TON 84.00 6,309,290.40 98.00 7,360,838.80 87.50 6,572,177.50
0010 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,226.8    TON 130.00 159,484.00 155.00 190,154.00 112.25 137,708.30
0011 508-01-00100 Asphalt Concrete (SMA) Wearing Course 12,939      TON 128.00 1,656,192.00 118.00 1,526,802.00 133.50 1,727,356.50
0012 509-01-00100 Cold Planing Asphaltic Pavement 64,905      SQYD 2.00 129,810.00 4.00 259,620.00 3.35 217,431.75
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -3,609      CUYD 1.00 -3,609.00 1.00 -3,609.00 0.10 -360.90
0014 510-01-00200 Pavement Patching (12" Minimum Thickness) 1,253      SQYD 100.00 125,300.00 125.00 156,625.00 117.00 146,601.00
0015 602-02-00200 Cleaning and Resealing Existing Longitudinal Pavement Joints 2,919      LNFT 3.20 9,340.80 2.00 5,838.00 2.00 5,838.00
0016 602-02-00300 Cleaning and Resealing Existing Transverse Pavements Joints 3,644      LNFT 3.20 11,660.80 2.00 7,288.00 2.00 7,288.00
0017 602-05-01160 Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9" Thick) 235.4    SQYD 278.00 65,441.20 275.00 64,735.00 281.00 66,147.40
0018 602-05-01200 Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) 2,875.9    SQYD 300.00 862,770.00 285.00 819,631.50 292.00 839,762.80
0019 602-05-02160 Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9" Thick) 135.1    SQYD 278.00 37,557.80 265.00 35,801.50 270.00 36,477.00
0020 602-05-02200 Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) 1,277.1    SQYD 300.00 383,130.00 275.00 351,202.50 281.00 358,865.10
0021 602-05-03160 Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) 106.7    SQYD 280.00 29,876.00 255.00 27,208.50 259.00 27,635.30
0022 602-05-03200 Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) 550.7    SQYD 300.00 165,210.00 265.00 145,935.50 270.00 148,689.00
0023 602-09-00100 Grinding Isolated Joints 522.2    SQYD 55.00 28,721.00 24.00 12,532.80 26.50 13,838.30
0024 602-10-00100 Longitudinal Shoulder Joints 14,190      LNFT 1.95 27,670.50 2.00 28,380.00 1.40 19,866.00
0025 602-11-00100 Removal of Existing Shoulder Underdrain Systems 32,089      LNFT 2.00 64,178.00 3.50 112,311.50 8.50 272,756.50
0026 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 12      LNFT 115.00 1,380.00 200.00 2,400.00 141.00 1,692.00
0027 702-04-00200 Adjusting Catch Basins 1      EACH 2,000.00 2,000.00 5,000.00 5,000.00 3,700.00 3,700.00
0028 703-01-00100 Shoulder Underdrain Systems 32,089      LNFT 11.00 352,979.00 18.50 593,646.50 20.00 641,780.00
0029 703-02-00100 Shoulder Outlet Underdrains 109      EACH 450.00 49,050.00 600.00 65,400.00 562.00 61,258.00
0031 704-07-00200 Guard Rail Bridge Attachments (Single Thrie Beam) 35      LNFT 25.00 875.00 35.00 1,225.00 34.00 1,190.00
0032 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 250      LNFT 65.00 16,250.00 60.00 15,000.00 62.00 15,500.00
0033 704-11-00100 Guard Rail End Treatment (Flared) 10      EACH 2,200.00 22,000.00 2,100.00 21,000.00 2,136.00 21,360.00
0034 713-01-00100 Temporary Signs and Barricades 1      LUMP 400,000.00 400,000.00 600,000.00 600,000.00 874,000.00 874,000.00
0035 713-02-00300 Temporary Pavement Markings (8" Width) 21,700      LNFT 0.30 6,510.00 0.50 10,850.00 0.30 6,510.00
0036 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 46.405  MILE 530.00 24,594.65 750.00 34,803.75 394.00 18,283.57
0037 713-03-02020 Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) 3.341  MILE 2,800.00 9,354.80 2,500.00 8,352.50 2,000.00 6,682.00
0038 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 70.64   MILE 620.00 43,796.80 350.00 24,724.00 787.00 55,593.68
0039 713-04-01020 Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 5.438  MILE 6,700.00 36,434.60 3,500.00 19,033.00 7,872.00 42,807.94
0040 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 3      EACH 50.00 150.00 200.00 600.00 56.00 168.00
0041 713-05-00300 Temporary Pavement Legends & Symbols (ONLY) 3      EACH 50.00 150.00 300.00 900.00 56.00 168.00
0042 727-01-00100 Mobilization 1      LUMP 1,315,000.00 1,315,000.00 842,000.00 842,000.00 1,505,000.00 1,505,000.00
0043 729-16-00300 Object Marker Assembly (Type 3) 64      EACH 65.00 4,160.00 100.00 6,400.00 84.00 5,376.00
0044 731-02-00100 Reflectorized Raised Pavement Markers 1,929      EACH 5.50 10,609.50 10.00 19,290.00 5.60 10,802.40
0045 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 4,340      LNFT 1.50 6,510.00 6.00 26,040.00 1.00 4,340.00
0046 732-01-01080 Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 1,349      LNFT 5.00 6,745.00 10.00 13,490.00 4.00 5,396.00
0047 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 14.128  MILE 2,800.00 39,558.40 3,300.00 46,622.40 3,000.00 42,384.00
0048 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 9.281  MILE 950.00 8,816.95 2,100.00 19,490.10 790.00 7,331.99
0049 732-04-05020 Plastic Pavement Legends and Symbols (EXIT) 6      EACH 225.00 1,350.00 1,100.00 6,600.00 281.00 1,686.00
0050 732-04-12000 Plastic Pavement Legends and Symbols (LANE) 6      EACH 240.00 1,440.00 1,100.00 6,600.00 281.00 1,686.00
0051 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 6      EACH 250.00 1,500.00 1,100.00 6,600.00 281.00 1,686.00
0052 732-05-00100 Removal of Existing Markings 7.048  MILE 4,500.00 31,716.00 2,100.00 14,800.80 5,300.00 37,354.40
0053 734-01-00100 Rubblizing Portland Cement Concrete Pavement 92,451      SQYD 5.50 508,480.50 6.50 600,931.50 5.80 536,215.80
0054 739-01-00100 Hydro-Seeding 13.67   ACRE 1,700.00 23,239.00 1,250.00 17,087.50 1,200.00 16,404.00
0055 740-01-00100 Construction Layout 1      LUMP 100,000.00 100,000.00 132,000.00 132,000.00 190,000.00 190,000.00
0056 805-09-00100 Expansion Joint Seal 80      LNFT 3.30 264.00 100.00 8,000.00 108.00 8,640.00
0057 NS-500-00220 Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay 20,157      LNFT 3.30 66,518.10 1.25 25,196.25 1.30 26,204.10
0058 NS-500-00240 Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay 3,528      LNFT 3.30 11,642.40 1.35 4,762.80 1.40 4,939.20
0059 NS-500-00260 Sawcuts in Asphaltic Concrete Lifts 45,874      LNFT 2.20 100,922.80 1.00 45,874.00 1.00 45,874.00
0060 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 147,681      INLF 2.20 324,898.20 0.10 14,768.10 0.50 73,840.50
0061 NS-602-00001 Milling Concrete Pavement 4,468.4    SQYD 15.00 67,026.00 20.00 89,368.00 15.00 67,026.00
0062 NS-700-00020 Adjusting Guard Rail 6,513      LNFT 17.00 110,721.00 5.00 32,565.00 5.65 36,798.45
0063 NS-700-00220 Impact Attenuator (Kinetic) 2      EACH 21,000.00 42,000.00 12,500.00 25,000.00 13,200.00 26,400.00
0064 NS-713-00001 Dynamic Message Sign Unit 4      EACH 20,000.00 80,000.00 10,000.00 40,000.00 13,500.00 54,000.00
0065 NS-724-00002 Rumble Strips (Shoulder Ground-In) 14.1    MILE 1,350.00 19,035.00 600.00 8,460.00 990.00 13,959.00
0066 NS-810-00001 Barrier Rail Rehabiltation 2,607      LNFT 60.00 156,420.00 25.00 65,175.00 42.82 111,631.74
0068 202-02-00010 Removal of Existing Pier Protection 2      EACH 9,000.00 18,000.00 10,000.00 20,000.00 10,300.00 20,600.00
0069 202-03-00010 Relocation of Light Poles (at Texas Ave. Interchange) 14      EACH 1,100.00 15,400.00 1,100.00 15,400.00 1,100.00 15,400.00
0070 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 2,584      LNFT 33.00 85,272.00 30.00 77,520.00 31.00 80,104.00
0071 704-03-00100 Blocked Out Guard Rail 1,794      LNFT 20.00 35,880.00 16.00 28,704.00 18.00 32,292.00
0072 NS-736-00100 Radar Traffic Sensor and Recorder System 1      EACH 30,000.00 30,000.00 25,000.00 25,000.00 28,200.00 28,200.00
0073 NS-800-00120 Pier Protection System (Vehicle) 2      EACH 28,000.00 56,000.00 35,000.00 70,000.00 38,240.00 76,480.00
0074 713-08-00100 Temporary Precast Concrete Barrier (Department Furnished) 60      EACH 350.00 21,000.00 750.00 45,000.00 141.00 8,460.00
                     
    ITEM TOTAL (CONSTRUCTION BID)       14,733,829.68   15,284,411.00   15,805,661.72
    NUMBER OF DAYS BID AT $15000 PER DAY.       3,795,000.00   4,125,000.00   4,500,000.00
    TOTAL BID       18,528,829.68   19,409,411.00   20,305,661.72