Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 451-04-0059 | |
| Parish: Bienville | |
| Routes: I-10 | |
| Description: I-20 @ La154 Eastbound/Westbound Acceleration Lane Extension | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, GUARD RAIL AND RELATED WORK. | |
| Estimated Construction Cost: $323,847.95 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $434,245.37 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 20,000.00 | 20,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 330 | LNFT | 6.00 | 1,980.00 |
| 0003 | 203-01-00100 | General Excavation | 425.07 | CUYD | 10.00 | 4,250.70 |
| 0004 | 203-03-00100 | Embankment | 2,154.5 | CUYD | 19.50 | 42,012.75 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 4 | EACH | 200.00 | 800.00 |
| 0006 | 302-02-06120 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete) | 3,044.46 | SQYD | 39.05 | 118,886.16 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 1,161.57 | TON | 109.30 | 126,959.60 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 3,262.39 | SQYD | 2.25 | 7,340.38 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -67.97 | CUYD | 1.00 | -67.97 |
| 0010 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 125 | LNFT | 65.00 | 8,125.00 |
| 0011 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 18.00 | 4,500.00 |
| 0012 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 6.25 | LNFT | 97.00 | 606.25 |
| 0013 | 704-11-00100 | Guard Rail End Treatment (Flared) | 2 | EACH | 2,200.00 | 4,400.00 |
| 0014 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 17.78 | SQYD | 100.00 | 1,778.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 31,900.00 | 31,900.00 |
| 0016 | 716-01-00100 | Mulch (Vegetative) | 1.5 | TON | 1,000.00 | 1,500.00 |
| 0017 | 717-01-00100 | Seeding | 30 | LB | 10.00 | 300.00 |
| 0018 | 718-01-00100 | Fertilizer | 1,000 | LB | 1.00 | 1,000.00 |
| 0019 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 17.78 | SQYD | 25.00 | 444.50 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 31,900.00 | 31,900.00 |
| 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 75.00 | 150.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 20 | EACH | 30.00 | 600.00 |
| 0023 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 100 | LNFT | 10.00 | 1,000.00 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.378 | MILE | 20,000.00 | 7,560.00 |
| 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.132 | MILE | 10,000.00 | 1,320.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 |
| CONTRACTOR TOTAL | 434,245.37 | |||||