Bid Tabulations
Letting of
02/10/2010
LA DOTD Headquarters
| Lead Project: 451-01-0129 | |
| Parish: Caddo | |
| Routes: I-20 | |
| Description: RAILROAD OVERPASS TO PINES ROAD WESTBOUND OUTSIDE LANE | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, ASPHALT CONCRETE (SMA) AND RELATED WORK | |
| Estimated Construction Cost: $511,435.60 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, LLC | $690,733.80 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 508-01-00100 | Asphalt Concrete (SMA) Wearing Course | 3,252.5 | TON | 130.00 | 422,825.00 |
| 0002 | 509-01-00100 | Cold Planing Asphaltic Pavement | 29,568 | SQYD | 4.00 | 118,272.00 |
| 0003 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,232 | CUYD | 0.10 | -123.20 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 |
| 0005 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,280 | LNFT | 0.25 | 320.00 |
| 0006 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.4 | MILE | 800.00 | 6,720.00 |
| 0007 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 8.4 | MILE | 475.00 | 3,990.00 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.2 | MILE | 550.00 | 2,310.00 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 60,000.00 | 60,000.00 |
| 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 664 | EACH | 5.25 | 3,486.00 |
| 0011 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 640 | LNFT | 1.35 | 864.00 |
| 0012 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.2 | MILE | 2,500.00 | 10,500.00 |
| 0013 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.2 | MILE | 850.00 | 3,570.00 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,000.00 | 8,000.00 |
| CONTRACTOR TOTAL | 690,733.80 | |||||