Bid Tabulations
Letting of
06/29/2011
LA DOTD Headquarters
| Lead Project: 450-91-0165 | |
| Parish: Calcasieu | |
| Routes: I-10 | |
| Description: COLUMBIA SOUTHERN OVERPASS-CALCASIEU RIVER BRIDGE | |
| Type Const: GRADING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, GUARD RAIL, STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $2,614,508.48 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 34356 | Prairie Contractors Inc. | $4,230,585.84 | 160 | $5,030,585.84 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $4,418,798.58 | 180 | $5,318,798.58 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Prairie Contractors Inc. |
- 2 - Gilchrist Construction Co. LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 30,000.00 | 30,000.00 | 3,500.00 | 3,500.00 |
| 0002 | 202-02-12020 | Removal of Fence (Chain Link) | 3,200 | LNFT | 10.00 | 32,000.00 | 3.67 | 11,744.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 1,600 | LNFT | 6.00 | 9,600.00 | 7.50 | 12,000.00 |
| 0004 | 203-01-00100 | General Excavation | 790 | CUYD | 20.00 | 15,800.00 | 10.00 | 7,900.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 125.00 | 25,000.00 | 62.00 | 12,400.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 18,191.5 | TON | 105.00 | 1,910,107.50 | 135.00 | 2,455,852.50 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 83,839 | SQYD | 4.10 | 343,739.90 | 1.35 | 113,182.65 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,489 | CUYD | 0.01 | -24.89 | 1.00 | -2,489.00 |
| 0010 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 250 | SQYD | 289.00 | 72,250.00 | 312.00 | 78,000.00 |
| 0011 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 250 | SQYD | 315.00 | 78,750.00 | 320.00 | 80,000.00 |
| 0012 | 510-02-00100 | Pavement Widening | 369.33 | SQYD | 300.00 | 110,799.00 | 130.00 | 48,012.90 |
| 0013 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 7 | EACH | 500.00 | 3,500.00 | 975.00 | 6,825.00 |
| 0014 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 418.8 | LNFT | 48.00 | 20,102.40 | 50.00 | 20,940.00 |
| 0015 | 704-01-02020 | Guard Rail (DoubleThrie Beam) (6'-3" post spacing) | 25 | LNFT | 10.00 | 250.00 | 1.15 | 28.75 |
| 0016 | 704-03-00100 | Blocked Out Guard Rail | 1,750 | LNFT | 20.00 | 35,000.00 | 20.00 | 35,000.00 |
| 0017 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 68.8 | LNFT | 100.00 | 6,880.00 | 106.00 | 7,292.80 |
| 0018 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 12.5 | LNFT | 100.00 | 1,250.00 | 48.00 | 600.00 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,200.00 | 8,800.00 |
| 0020 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 8 | EACH | 3,000.00 | 24,000.00 | 2,700.00 | 21,600.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 300,000.00 | 300,000.00 | 335,000.00 | 335,000.00 |
| 0022 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 21.304 | MILE | 600.00 | 12,782.40 | 565.00 | 12,036.76 |
| 0023 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 2.619 | MILE | 3,500.00 | 9,166.50 | 2,800.00 | 7,333.20 |
| 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 24.672 | MILE | 750.00 | 18,504.00 | 620.00 | 15,296.64 |
| 0025 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.228 | MILE | 10,000.00 | 2,280.00 | 9,800.00 | 2,234.40 |
| 0026 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 107 | EACH | 50.00 | 5,350.00 | 315.00 | 33,705.00 |
| 0027 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 107 | EACH | 10.00 | 1,070.00 | 24.00 | 2,568.00 |
| 0028 | 717-01-00100 | Seeding | 130 | LB | 10.00 | 1,300.00 | 9.60 | 1,248.00 |
| 0029 | 718-01-00100 | Fertilizer | 2,200 | LB | 1.00 | 2,200.00 | 0.67 | 1,474.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 390,000.00 | 390,000.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 14 | EACH | 100.00 | 1,400.00 | 85.00 | 1,190.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,093 | EACH | 6.00 | 12,558.00 | 5.90 | 12,348.70 |
| 0033 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,786 | LNFT | 5.25 | 9,376.50 | 5.13 | 9,162.18 |
| 0034 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.238 | MILE | 3,000.00 | 15,714.00 | 3,100.00 | 16,237.80 |
| 0035 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.114 | MILE | 10,000.00 | 1,140.00 | 7,300.00 | 832.20 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.856 | MILE | 1,000.00 | 7,856.00 | 950.00 | 7,463.20 |
| 0037 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 1.274 | MILE | 3,500.00 | 4,459.00 | 3,300.00 | 4,204.20 |
| 0038 | 732-05-00100 | Removal of Existing Markings | 0.455 | MILE | 10,000.00 | 4,550.00 | 3,900.00 | 1,774.50 |
| 0039 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 |
| 0040 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 100 | INLF | 20.00 | 2,000.00 | 3.40 | 340.00 |
| 0041 | NS-602-00001 | Milling Concrete Pavement | 884 | SQYD | 15.00 | 13,260.00 | 19.00 | 16,796.00 |
| 0042 | NS-713-00001 | Dynamic Message Sign Unit | 8 | EACH | 20,000.00 | 160,000.00 | 10,000.00 | 80,000.00 |
| 0043 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 4.9 | MILE | 1,500.00 | 7,350.00 | 2,200.00 | 10,780.00 |
| 0044 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 2,699.4 | TON | 205.00 | 553,377.00 | 175.00 | 472,395.00 |
| 0045 | 501-02-00001 | Tack Coat | 10,797.3 | GAL | 4.25 | 45,888.53 | 4.00 | 43,189.20 |
| ITEM TOTAL (CONSTRUCTION BID) | 4,230,585.84 | 4,418,798.58 | ||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 800,000.00 | 900,000.00 | ||||||
| TOTAL BID | 5,030,585.84 | 5,318,798.58 | ||||||