Bid Tabulations
Letting of
05/25/2011
LA DOTD Headquarters
| Lead Project: 450-90-0228 | |
| Parish: Orleans | |
| Routes: I-10 | |
| Description: Entrance Ramp from Carrollton Ave. to I-10 East | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $200,231.49 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $224,777.15 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $262,354.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 35 | LNFT | 15.00 | 525.00 | 25.00 | 875.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 6 | CUYD | 85.00 | 510.00 | 100.00 | 600.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 577.1 | TON | 125.00 | 72,137.50 | 180.00 | 103,878.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 3,883 | SQYD | 8.75 | 33,976.25 | 5.00 | 19,415.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | 215.72 | CUYD | -5.00 | -1,078.60 | 0.00 | 0.00 |
| 0006 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 4,425 | LNFT | 0.50 | 2,212.50 | 1.00 | 4,425.00 |
| 0007 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 2,000 | LNFT | 0.50 | 1,000.00 | 1.00 | 2,000.00 |
| 0008 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 2,225 | LNFT | 0.50 | 1,112.50 | 1.00 | 2,225.00 |
| 0009 | 707-03-00100 | Combination Concrete Curb and Gutter | 50 | LNFT | 30.00 | 1,500.00 | 65.00 | 3,250.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 70,000.00 | 70,000.00 |
| 0011 | 717-01-00100 | Seeding | 5 | LB | 1.00 | 5.00 | 100.00 | 500.00 |
| 0012 | 718-01-00100 | Fertilizer | 60 | LB | 1.00 | 60.00 | 10.00 | 600.00 |
| 0013 | 727-01-00100 | Mobilization | 1 | LUMP | 22,000.00 | 22,000.00 | 26,000.00 | 26,000.00 |
| 0014 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,050 | LNFT | 4.50 | 4,725.00 | 5.50 | 5,775.00 |
| 0015 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.512 | MILE | 3,500.00 | 1,792.00 | 3,000.00 | 1,536.00 |
| 0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,000.00 | 7,000.00 | 2,500.00 | 2,500.00 |
| 0017 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 2,000 | LNFT | 2.00 | 4,000.00 | 2.50 | 5,000.00 |
| 0018 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 2,225 | LNFT | 2.00 | 4,450.00 | 2.50 | 5,562.50 |
| 0019 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 4,425 | LNFT | 2.00 | 8,850.00 | 0.50 | 2,212.50 |
| 0020 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 5,000.00 | 15,000.00 | 2,000.00 | 6,000.00 |
| CONTRACTOR TOTAL | 224,777.15 | 262,354.00 | ||||||