Bid Tabulations
Letting of
01/26/2011
LA DOTD Headquarters
| Lead Project: 450-18-0115 | |
| Parish: St. Tammany | |
| Routes: I-10 | |
| Description: N.E. FRONTAGE ROAD RIGHT TURN LANE @ U.S. 190 | |
| Type Const: PAVEMENT WIDENING, SURFACE PREPARATATION, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $72,579.79 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $69,892.81 |
| 2 | 06487 | Huey Stockstill, Inc. | $72,967.71 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $79,007.33 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Huey Stockstill, Inc. |
- 3 - Boh Bros. Construction Co., LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-03-38000 | Relocation of Sign sign to be relocated as directed by project engineer | 1 | EACH | 250.00 | 250.00 | 100.00 | 100.00 | 170.00 | 170.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 20 | CUYD | 25.00 | 500.00 | 100.00 | 2,000.00 | 20.00 | 400.00 |
| 0003 | 204-06-00100 | Temporary Silt Fencing | 360 | LNFT | 1.00 | 360.00 | 3.00 | 1,080.00 | 3.50 | 1,260.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 90.1 | TON | 200.00 | 18,020.00 | 188.00 | 16,938.80 | 250.00 | 22,525.00 |
| 0005 | 510-02-00100 | Pavement Widening | 81 | SQYD | 150.00 | 12,150.00 | 100.00 | 8,100.00 | 120.00 | 9,720.00 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 11,000.00 | 11,000.00 | 19,000.00 | 19,000.00 | 19,000.00 | 19,000.00 |
| 0007 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 180 | LNFT | 0.10 | 18.00 | 0.20 | 36.00 | 0.25 | 45.00 |
| 0008 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 26 | LNFT | 0.10 | 2.60 | 0.75 | 19.50 | 0.85 | 22.10 |
| 0009 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.069 | MILE | 1,500.00 | 103.50 | 140.00 | 9.66 | 600.00 | 41.40 |
| 0010 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.137 | MILE | 0.10 | 0.01 | 550.00 | 75.35 | 625.00 | 85.63 |
| 0011 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 0.10 | 0.20 | 45.00 | 90.00 | 50.00 | 100.00 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 3,000.00 | 300.00 | 200.00 | 20.00 | 10,000.00 | 1,000.00 |
| 0013 | 717-01-00100 | Seeding | 1 | LB | 100.00 | 100.00 | 80.00 | 80.00 | 25.00 | 25.00 |
| 0014 | 718-01-00100 | Fertilizer | 8 | LB | 12.50 | 100.00 | 90.00 | 720.00 | 1.00 | 8.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 6,900.00 | 6,900.00 | 7,100.00 | 7,100.00 | 7,900.00 | 7,900.00 |
| 0016 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 100.00 | 200.00 | 100.00 | 200.00 | 100.00 | 200.00 |
| 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 20 | EACH | 7.00 | 140.00 | 6.00 | 120.00 | 6.00 | 120.00 |
| 0018 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 180 | LNFT | 2.00 | 360.00 | 1.50 | 270.00 | 1.50 | 270.00 |
| 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 26 | LNFT | 7.00 | 182.00 | 5.00 | 130.00 | 5.00 | 130.00 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.069 | MILE | 4,000.00 | 276.00 | 3,300.00 | 227.70 | 3,200.00 | 220.80 |
| 0021 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.137 | MILE | 1,500.00 | 205.50 | 1,100.00 | 150.70 | 1,200.00 | 164.40 |
| 0022 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 300.00 | 600.00 | 250.00 | 500.00 | 250.00 | 500.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 |
| 0024 | NS-500-00280 | Surface Preparation | 1 | LUMP | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 | 8,000.00 | 8,000.00 |
| 0025 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 2,375.00 | 7,125.00 | 3,000.00 | 9,000.00 | 1,700.00 | 5,100.00 |
| CONTRACTOR TOTAL | 69,892.81 | 72,967.71 | 79,007.33 | |||||||