Bid Tabulations
Letting of
01/26/2011
LA DOTD Headquarters
| Lead Project: 450-15-0139 | |
| Parish: Jefferson | |
| Routes: I-10 | |
| Description: METAIRIE BIKE PATH REPLACEMENT | |
| Type Const: GRADING, REPLACING ASPHALTIC CONCRETE BIKE PATH, CONCRETE CURBS AND RELATED WORK | |
| Estimated Construction Cost: $228,119.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $243,647.75 |
| 2 | 49356 | Kort's Trucking Inc. | $248,815.50 |
| 3 | 42466 | Beard Construction Group LLC | $336,284.48 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Kort's Trucking Inc. |
- 3 - Beard Construction Group LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 350.00 | 350.00 | 375.00 | 375.00 | 863.31 | 863.31 |
| 0002 | 203-01-00100 | General Excavation | 1,992 | CUYD | 20.00 | 39,840.00 | 15.50 | 30,876.00 | 12.82 | 25,537.44 |
| 0003 | 203-03-00100 | Embankment | 17 | CUYD | 50.00 | 850.00 | 17.00 | 289.00 | 517.17 | 8,791.89 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 30 | EACH | 3.00 | 90.00 | 20.00 | 600.00 | 25.17 | 755.10 |
| 0005 | 502-03-00200 | Superpave Asphaltic Concrete (4" Thick) | 4,033 | SQYD | 26.00 | 104,858.00 | 33.00 | 133,089.00 | 36.67 | 147,890.11 |
| 0006 | 707-01-00100 | Concrete Curb | 300 | LNFT | 15.00 | 4,500.00 | 14.50 | 4,350.00 | 16.50 | 4,950.00 |
| 0007 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,235 | LNFT | 20.00 | 24,700.00 | 20.00 | 24,700.00 | 16.50 | 20,377.50 |
| 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 24,000.00 | 24,000.00 | 10,000.00 | 10,000.00 | 21,017.92 | 21,017.92 |
| 0009 | 716-01-00100 | Mulch (Vegetative) | 3.2 | TON | 600.00 | 1,920.00 | 800.00 | 2,560.00 | 847.00 | 2,710.40 |
| 0010 | 717-01-00100 | Seeding | 56 | LB | 15.00 | 840.00 | 14.00 | 784.00 | 21.80 | 1,220.80 |
| 0011 | 718-01-00100 | Fertilizer | 1,850 | LB | 0.40 | 740.00 | 0.65 | 1,202.50 | 0.60 | 1,110.00 |
| 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 24,000.00 | 24,000.00 | 10,000.00 | 10,000.00 | 56,157.42 | 56,157.42 |
| 0013 | 729-01-00100 | Sign (Type A) | 26.5 | SQFT | 16.50 | 437.25 | 20.00 | 530.00 | 16.52 | 437.78 |
| 0014 | 729-21-00100 | U-Channel Post | 8 | EACH | 60.00 | 480.00 | 65.00 | 520.00 | 106.40 | 851.20 |
| 0015 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 0.85 | MILE | 500.00 | 425.00 | 3,600.00 | 3,060.00 | 2,730.82 | 2,321.20 |
| 0016 | 737-03-00300 | Painted Traffic Striping (Solid Line) (8" Width) | 485 | LNFT | 0.50 | 242.50 | 1.50 | 727.50 | 3.95 | 1,915.75 |
| 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 3,000.00 | 3,000.00 | 11,738.50 | 11,738.50 |
| 0018 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 12,350 | INLF | 0.10 | 1,235.00 | 1.35 | 16,672.50 | 1.53 | 18,895.50 |
| 0019 | NS-ENH-04000 | Drainage Grates (Replacement) (Type A) | 2 | EACH | 1,000.00 | 2,000.00 | 600.00 | 1,200.00 | 1,289.73 | 2,579.46 |
| 0020 | NS-ENH-07900 | Gutter Cleaning Adjacent to Bike Path | 4,280 | LNFT | 0.50 | 2,140.00 | 1.00 | 4,280.00 | 1.44 | 6,163.20 |
| CONTRACTOR TOTAL | 243,647.75 | 248,815.50 | 336,284.48 | |||||||