Bid Tabulations
Letting of
06/29/2011
LA DOTD Headquarters
| Lead Project: 450-15-0099 | |
| Parish: Jefferson | |
| Routes: I-10 | |
| Description: VETERANS BLVD. TO CLEARVIEW PARKWAY ROUTE I-10 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC PAVEMENT, CLASS II BASE COURSE, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVMENT, ASPHALTIC CONCRETE SMA WEARING COURSE, SIGNING, LIGHTING, SOUND BARRIER WALLS, SLAB SPAN AND GIRDER SPAN BRIDGES, AND RELATED WORK. | |
| Estimated Construction Cost: $48,449,619.57 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $15,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 39462 | Jb James Construction Llc | $42,463,843.76 | 600 | $51,463,843.76 |
| 2 | 34567 | James Construction Group LLC | $43,446,610.56 | 550 | $51,696,610.56 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $51,812,957.10 | 730 | $62,762,957.10 |
| 4 | 06276 | Barriere Construction Co., LLC | $53,611,567.61 | 775 | $65,236,567.61 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Jb James Construction Llc |
- 2 - James Construction Group LLC |
- 3 - Boh Bros. Construction Co., LLC. |
- 4 - Barriere Construction Co., LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | lump | 450,000.00 | 450,000.00 | 180,000.00 | 180,000.00 | 25,000.00 | 25,000.00 | 130,000.00 | 130,000.00 |
| 0002 | 201-01-00200 | Clearing and Grubbing (Selective) (Tree Trimming) | 1 | lump | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 11,400.00 | 11,400.00 |
| 0003 | 202-01-00100 | Removal of Structures and Obstructions | 1 | lump | 13,000.00 | 13,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 |
| 0004 | 202-02-04000 | Removal of Bridge (Eastbound And Westbound) | 2 | each | 340,000.00 | 680,000.00 | 150,000.00 | 300,000.00 | 115,000.00 | 230,000.00 | 540,000.00 | 1,080,000.00 |
| 0005 | 202-02-06060 | Removal of Concrete Catch Basin | 22 | each | 400.00 | 8,800.00 | 615.00 | 13,530.00 | 700.00 | 15,400.00 | 760.00 | 16,720.00 |
| 0006 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 3 | ln m | 20.00 | 60.00 | 10.00 | 30.00 | 135.00 | 405.00 | 19.00 | 57.00 |
| 0007 | 202-02-06100 | Removal of Concrete Walks and Drives | 76 | sq m | 12.00 | 912.00 | 80.00 | 6,080.00 | 20.00 | 1,520.00 | 11.50 | 874.00 |
| 0008 | 202-02-06140 | Removal of Curbs (Concrete) | 278.2 | ln m | 11.00 | 3,060.20 | 20.00 | 5,564.00 | 21.00 | 5,842.20 | 21.00 | 5,842.20 |
| 0009 | 202-02-12020 | Removal of Fence (Chain Link) | 310 | ln m | 15.00 | 4,650.00 | 20.00 | 6,200.00 | 70.00 | 21,700.00 | 6.00 | 1,860.00 |
| 0010 | 202-02-14500 | Removal of Guard Rail | 603 | ln m | 13.00 | 7,839.00 | 10.00 | 6,030.00 | 15.00 | 9,045.00 | 15.00 | 9,045.00 |
| 0011 | 202-02-26000 | Removal of Manholes | 4 | each | 500.00 | 2,000.00 | 1,185.00 | 4,740.00 | 700.00 | 2,800.00 | 1,500.00 | 6,000.00 |
| 0012 | 202-02-32140 | Removal of Pipe (Storm Drain) (381mm, 610mm, 762mm, 904mm, 1067mm, 1219mm, 1372mm) | 1,823.66 | ln m | 33.00 | 60,180.78 | 26.00 | 47,415.16 | 85.00 | 155,011.10 | 80.00 | 145,892.80 |
| 0013 | 202-02-38220 | Removal of Sign Supports | 26 | each | 400.00 | 10,400.00 | 340.00 | 8,840.00 | 320.00 | 8,320.00 | 500.00 | 13,000.00 |
| 0014 | 202-02-38330 | Removal of Sign Cantilever and Footing | 3 | each | 3,500.00 | 10,500.00 | 6,700.00 | 20,100.00 | 8,500.00 | 25,500.00 | 9,000.00 | 27,000.00 |
| 0015 | 202-02-38360 | Removal of Sign Faces | 44 | each | 100.00 | 4,400.00 | 220.00 | 9,680.00 | 200.00 | 8,800.00 | 115.00 | 5,060.00 |
| 0016 | 202-02-38380 | Removal of Sign Truss and Footings | 3 | each | 4,000.00 | 12,000.00 | 8,350.00 | 25,050.00 | 12,500.00 | 37,500.00 | 11,400.00 | 34,200.00 |
| 0017 | 202-02-38500 | Removal of Surfacing and Stablized Base | 12,566 | sq m | 6.00 | 75,396.00 | 18.00 | 226,188.00 | 21.00 | 263,886.00 | 5.80 | 72,882.80 |
| 0018 | 203-01-00100 | General Excavation | 7,991 | cu m | 17.00 | 135,847.00 | 10.00 | 79,910.00 | 27.00 | 215,757.00 | 9.80 | 78,311.80 |
| 0019 | 203-03-00100 | Embankment | 19,969 | cu m | 40.00 | 798,760.00 | 40.00 | 798,760.00 | 30.00 | 599,070.00 | 29.00 | 579,101.00 |
| 0020 | 204-02-00100 | Temporary Hay or Straw Bales | 308 | each | 15.00 | 4,620.00 | 12.00 | 3,696.00 | 15.00 | 4,620.00 | 9.70 | 2,987.60 |
| 0021 | 204-06-00100 | Temporary Silt Fencing | 6,700 | ln m | 4.00 | 26,800.00 | 15.00 | 100,500.00 | 7.30 | 48,910.00 | 3.80 | 25,460.00 |
| 0022 | 204-07-00100 | Temporary Stone Construction Entrance | 3 | each | 2,500.00 | 7,500.00 | 4,000.00 | 12,000.00 | 11,000.00 | 33,000.00 | 3,600.00 | 10,800.00 |
| 0023 | 302-02-02560 | Class II Base Course (175 mm Thick) (Stone or Recycled Portland Cement Concrete) | 39,591 | sq m | 17.00 | 673,047.00 | 17.00 | 673,047.00 | 15.00 | 593,865.00 | 15.00 | 593,865.00 |
| 0024 | 502-01-00100 | Superpave Asphaltic Concrete | 45,171.5 | Mg | 106.00 | 4,788,179.00 | 106.00 | 4,788,179.00 | 109.00 | 4,923,693.50 | 100.00 | 4,517,150.00 |
| 0025 | 508-01-00100 | Asphalt Concrete (SMA) Wearing Course | 9,027.5 | Mg | 165.00 | 1,489,537.50 | 165.00 | 1,489,537.50 | 133.00 | 1,200,657.50 | 160.00 | 1,444,400.00 |
| 0026 | 509-01-00100 | Cold Planing Asphaltic Pavement | 49,665 | sq m | 5.50 | 273,157.50 | 5.50 | 273,157.50 | 10.00 | 496,650.00 | 5.50 | 273,157.50 |
| 0027 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,725 | cu m | 10.00 | -37,250.00 | 10.00 | -37,250.00 | 7.00 | -26,075.00 | 34.00 | -126,650.00 |
| 0028 | 701-03-01000 | Storm Drain Pipe (375 mm RCP/PP) | 72 | ln m | 335.00 | 24,120.00 | 136.00 | 9,792.00 | 395.00 | 28,440.00 | 430.00 | 30,960.00 |
| 0029 | 701-03-01020 | Storm Drain Pipe (450 mm RCP/PP) | 255.3 | ln m | 340.00 | 86,802.00 | 147.00 | 37,529.10 | 480.00 | 122,544.00 | 500.00 | 127,650.00 |
| 0030 | 701-03-01040 | Storm Drain Pipe (600 mm RCP/PP) | 128.6 | ln m | 380.00 | 48,868.00 | 186.00 | 23,919.60 | 575.00 | 73,945.00 | 485.00 | 62,371.00 |
| 0031 | 701-03-01060 | Storm Drain Pipe (750 mm RCP/PP) | 391.8 | ln m | 450.00 | 176,310.00 | 225.00 | 88,155.00 | 610.00 | 238,998.00 | 525.00 | 205,695.00 |
| 0032 | 701-03-01080 | Storm Drain Pipe (900 mm RCP/PP) | 189 | ln m | 500.00 | 94,500.00 | 277.50 | 52,447.50 | 685.00 | 129,465.00 | 560.00 | 105,840.00 |
| 0033 | 701-03-01090 | Storm Drain Pipe (1050 mm RCP/PP) | 392 | ln m | 600.00 | 235,200.00 | 339.00 | 132,888.00 | 765.00 | 299,880.00 | 900.00 | 352,800.00 |
| 0034 | 701-03-01100 | Storm Drain Pipe (1200 mm RCP/PP) | 602 | ln m | 675.00 | 406,350.00 | 426.50 | 256,753.00 | 915.00 | 550,830.00 | 850.00 | 511,700.00 |
| 0035 | 701-03-01120 | Storm Drain Pipe (1350 mm RCP) | 43 | ln m | 850.00 | 36,550.00 | 481.00 | 20,683.00 | 1,280.00 | 55,040.00 | 1,255.00 | 53,965.00 |
| 0036 | 701-04-01120 | Storm Drain Pipe Arch (1200 mm Equiv. RCPA) | 255.9 | ln m | 900.00 | 230,310.00 | 420.50 | 107,605.95 | 1,030.00 | 263,577.00 | 1,300.00 | 332,670.00 |
| 0037 | 701-04-01140 | Storm Drain Pipe Arch (1350 mm Equiv. RCPA) | 222 | ln m | 950.00 | 210,900.00 | 513.50 | 113,997.00 | 1,015.00 | 225,330.00 | 1,400.00 | 310,800.00 |
| 0038 | 701-04-01160 | Storm Drain Pipe Arch (1500 mm Equiv. RCPA) | 263.5 | ln m | 1,150.00 | 303,025.00 | 508.00 | 133,858.00 | 1,230.00 | 324,105.00 | 1,600.00 | 421,600.00 |
| 0039 | 701-14-00100 | Cleaning Existing Pipes | 1,690 | ln m | 41.00 | 69,290.00 | 28.00 | 47,320.00 | 20.00 | 33,800.00 | 22.00 | 37,180.00 |
| 0040 | 701-15-00100 | Concrete Collar | 18 | each | 900.00 | 16,200.00 | 575.00 | 10,350.00 | 1,500.00 | 27,000.00 | 1,200.00 | 21,600.00 |
| 0041 | 702-02-00200 | Manholes (R-CB-11) | 3 | each | 4,000.00 | 12,000.00 | 3,400.00 | 10,200.00 | 7,000.00 | 21,000.00 | 5,500.00 | 16,500.00 |
| 0042 | 702-02-00300 | Manholes (R-CB-11 MOD) | 12 | each | 4,200.00 | 50,400.00 | 2,600.00 | 31,200.00 | 7,300.00 | 87,600.00 | 5,500.00 | 66,000.00 |
| 0043 | 702-02-00400 | Manholes (R-CB-32) | 21 | each | 4,700.00 | 98,700.00 | 3,575.00 | 75,075.00 | 8,100.00 | 170,100.00 | 5,500.00 | 115,500.00 |
| 0044 | 702-03-00100 | Catch Basins (CB-01(M)) | 24 | each | 2,600.00 | 62,400.00 | 2,575.00 | 61,800.00 | 4,200.00 | 100,800.00 | 5,500.00 | 132,000.00 |
| 0045 | 702-03-00500 | Catch Basins (CB-06(M)) | 5 | each | 4,000.00 | 20,000.00 | 3,200.00 | 16,000.00 | 8,500.00 | 42,500.00 | 5,500.00 | 27,500.00 |
| 0046 | 702-04-00100 | Adjusting Manholes | 4 | each | 1,250.00 | 5,000.00 | 4,350.00 | 17,400.00 | 1,400.00 | 5,600.00 | 600.00 | 2,400.00 |
| 0047 | 702-04-00200 | Adjusting Catch Basins | 9 | each | 2,500.00 | 22,500.00 | 1,575.00 | 14,175.00 | 1,700.00 | 15,300.00 | 900.00 | 8,100.00 |
| 0048 | 702-07-00100 | Cross Drain Safety End (Type 1) | 12 | each | 1,500.00 | 18,000.00 | 1,950.00 | 23,400.00 | 3,600.00 | 43,200.00 | 2,000.00 | 24,000.00 |
| 0049 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (950 mm post spacing) | 111.4 | ln m | 130.00 | 14,482.00 | 225.00 | 25,065.00 | 150.00 | 16,710.00 | 148.00 | 16,487.20 |
| 0050 | 704-03-00100 | Blocked Out Guard Rail | 106.7 | ln m | 60.00 | 6,402.00 | 60.00 | 6,402.00 | 70.00 | 7,469.00 | 69.00 | 7,362.30 |
| 0051 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 5.7 | ln m | 250.00 | 1,425.00 | 275.00 | 1,567.50 | 275.00 | 1,567.50 | 290.00 | 1,653.00 |
| 0052 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 45.7 | ln m | 210.00 | 9,597.00 | 105.00 | 4,798.50 | 225.00 | 10,282.50 | 240.00 | 10,968.00 |
| 0053 | 704-11-00100 | Guard Rail End Treatment (Flared) | 6 | each | 2,100.00 | 12,600.00 | 2,700.00 | 16,200.00 | 2,250.00 | 13,500.00 | 2,400.00 | 14,400.00 |
| 0054 | 706-01-00100 | Concrete Walk (100 mm Thick) | 76 | sq m | 55.00 | 4,180.00 | 72.00 | 5,472.00 | 220.00 | 16,720.00 | 54.00 | 4,104.00 |
| 0055 | 706-03-00100 | Incidental Concrete Paving (100 mm Thick) | 13,325.7 | sq m | 49.00 | 652,959.30 | 55.00 | 732,913.50 | 55.00 | 732,913.50 | 42.50 | 566,342.25 |
| 0056 | 706-03-00300 | Incidental Concrete Paving (150 mm Thick) | 1,090.4 | sq m | 59.00 | 64,333.60 | 70.00 | 76,328.00 | 71.00 | 77,418.40 | 56.00 | 61,062.40 |
| 0057 | 707-03-00100 | Combination Concrete Curb and Gutter | 311.1 | ln m | 95.00 | 29,554.50 | 60.00 | 18,666.00 | 138.00 | 42,931.80 | 98.00 | 30,487.80 |
| 0058 | 713-01-00100 | Temporary Signs and Barricades | 1 | lump | 250,000.00 | 250,000.00 | 225,000.00 | 225,000.00 | 300,000.00 | 300,000.00 | 367,000.00 | 367,000.00 |
| 0059 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (100 mm Width) (3.0 m Length) | 50.029 | km | 250.00 | 12,507.25 | 248.00 | 12,407.19 | 370.00 | 18,510.73 | 280.00 | 14,008.12 |
| 0060 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (100 mm Width) | 31.026 | km | 310.00 | 9,618.06 | 310.00 | 9,618.06 | 425.00 | 13,186.05 | 360.00 | 11,169.36 |
| 0061 | 713-05-00200 | Temporary Pavement Legends & Symbols (Double Arrow) | 1 | each | 50.00 | 50.00 | 50.00 | 50.00 | 55.00 | 55.00 | 58.00 | 58.00 |
| 0062 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,496 | each | 5.00 | 7,480.00 | 4.00 | 5,984.00 | 5.50 | 8,228.00 | 4.50 | 6,732.00 |
| 0063 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 616 | each | 900.00 | 554,400.00 | 830.00 | 511,280.00 | 1,500.00 | 924,000.00 | 414.00 | 255,024.00 |
| 0064 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 616 | each | 250.00 | 154,000.00 | 500.00 | 308,000.00 | 377.00 | 232,232.00 | 72.00 | 44,352.00 |
| 0065 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 990 | each | 75.00 | 74,250.00 | 50.00 | 49,500.00 | 160.00 | 158,400.00 | 49.00 | 48,510.00 |
| 0066 | 717-01-00100 | Seeding | 96 | kg | 33.00 | 3,168.00 | 30.00 | 2,880.00 | 60.00 | 5,760.00 | 23.00 | 2,208.00 |
| 0067 | 718-01-00100 | Fertilizer | 3,136 | kg | 2.30 | 7,212.80 | 2.25 | 7,056.00 | 2.25 | 7,056.00 | 1.80 | 5,644.80 |
| 0068 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | each | 35,000.00 | 35,000.00 | 28,000.00 | 28,000.00 | 40,000.00 | 40,000.00 | 220,000.00 | 220,000.00 |
| 0069 | 726-01-00100 | Bedding Material | 5,223.3 | cu m | 90.00 | 470,097.00 | 65.00 | 339,514.50 | 100.00 | 522,330.00 | 75.00 | 391,747.50 |
| 0070 | 727-01-00100 | Mobilization | 1 | lump | 3,600,000.00 | 3,600,000.00 | 4,000,000.00 | 4,000,000.00 | 4,535,000.00 | 4,535,000.00 | 6,472,000.00 | 6,472,000.00 |
| 0071 | 728-01-00900 | Jacked or Bored Pipe (450 mm) (Size 500 O.D. Schedule 40, Steel Pipe) | 64 | ln m | 750.00 | 48,000.00 | 1,500.00 | 96,000.00 | 1,850.00 | 118,400.00 | 1,220.00 | 78,080.00 |
| 0072 | 728-01-01100 | Jacked or Bored Pipe (750 mm) (Size 800 O.D. Schedule 40, Steel Pipe) | 34.9 | ln m | 1,250.00 | 43,625.00 | 1,800.00 | 62,820.00 | 3,150.00 | 109,935.00 | 2,600.00 | 90,740.00 |
| 0073 | 728-01-01350 | Jacked or Bored Pipe (1200 mm) (1200 mm I.D. 32 mm Wall, Steel Pipe) | 72 | ln m | 2,000.00 | 144,000.00 | 3,000.00 | 216,000.00 | 6,425.00 | 462,600.00 | 4,700.00 | 338,400.00 |
| 0074 | 729-01-00100 | Sign (Type A) | 36.35 | sq m | 300.00 | 10,905.00 | 195.00 | 7,088.25 | 185.00 | 6,724.75 | 268.00 | 9,741.80 |
| 0075 | 729-04-00100 | Sign (Type D) | 9.2 | sq m | 315.00 | 2,898.00 | 250.00 | 2,300.00 | 230.00 | 2,116.00 | 310.00 | 2,852.00 |
| 0076 | 729-05-00100 | Sign (Type E) | 11.15 | sq m | 330.00 | 3,679.50 | 225.00 | 2,508.75 | 215.00 | 2,397.25 | 310.00 | 3,456.50 |
| 0077 | 729-06-00100 | Sign (Overhead Mounted) | 131.81 | sq m | 316.00 | 41,651.96 | 255.00 | 33,611.55 | 240.00 | 31,634.40 | 310.00 | 40,861.10 |
| 0078 | 729-08-00100 | Mounting (63.5 mm Size Post) | 6 | each | 775.00 | 4,650.00 | 1,015.00 | 6,090.00 | 950.00 | 5,700.00 | 800.00 | 4,800.00 |
| 0079 | 729-08-00200 | Mounting (88.9 mm Size Post) | 2 | each | 910.00 | 1,820.00 | 1,075.00 | 2,150.00 | 1,000.00 | 2,000.00 | 913.00 | 1,826.00 |
| 0080 | 729-08-00300 | Mounting (127 mm Size Post) | 10 | each | 1,300.00 | 13,000.00 | 2,150.00 | 21,500.00 | 2,000.00 | 20,000.00 | 1,030.00 | 10,300.00 |
| 0081 | 729-08-00400 | Mounting (152.4 mm Size Post) | 5 | each | 1,550.00 | 7,750.00 | 2,375.00 | 11,875.00 | 2,230.00 | 11,150.00 | 1,150.00 | 5,750.00 |
| 0082 | 729-08-00600 | Mounting (W150 x 18 Size Post) | 4 | each | 1,600.00 | 6,400.00 | 1,250.00 | 5,000.00 | 1,200.00 | 4,800.00 | 1,400.00 | 5,600.00 |
| 0083 | 729-09-00900 | Mounting (Overhead Truss) (Ground Mounted) (32.4 m Span) | 1 | each | 100,000.00 | 100,000.00 | 76,500.00 | 76,500.00 | 70,000.00 | 70,000.00 | 85,000.00 | 85,000.00 |
| 0084 | 729-09-01000 | Mounting (Overhead Truss) (Ground Mounted) (34.2 m Span) | 1 | each | 105,000.00 | 105,000.00 | 82,000.00 | 82,000.00 | 75,000.00 | 75,000.00 | 91,000.00 | 91,000.00 |
| 0085 | 729-09-01100 | Mounting (Overhead Truss) (Ground Mounted) (36 m Span) | 1 | each | 110,000.00 | 110,000.00 | 82,000.00 | 82,000.00 | 80,000.00 | 80,000.00 | 108,000.00 | 108,000.00 |
| 0086 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 3 | each | 32,000.00 | 96,000.00 | 3,400.00 | 10,200.00 | 32,000.00 | 96,000.00 | 28,500.00 | 85,500.00 |
| 0087 | 729-16-00100 | Object Marker Assembly (Type 1) | 6 | each | 75.00 | 450.00 | 150.00 | 900.00 | 160.00 | 960.00 | 194.00 | 1,164.00 |
| 0088 | 729-17-00100 | Milepost Assembly (Ground Mounted) | 14 | each | 78.00 | 1,092.00 | 250.00 | 3,500.00 | 265.00 | 3,710.00 | 300.00 | 4,200.00 |
| 0089 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 3 | each | 1,700.00 | 5,100.00 | 20,000.00 | 60,000.00 | 8,500.00 | 25,500.00 | 13,200.00 | 39,600.00 |
| 0090 | 729-20-00700 | Footings for Overhead Mountings (Truss) | 6 | each | 1,450.00 | 8,700.00 | 19,000.00 | 114,000.00 | 9,800.00 | 58,800.00 | 12,900.00 | 77,400.00 |
| 0091 | 730-01-00100 | Trenching and Backfilling | 4,000 | ln m | 9.00 | 36,000.00 | 8.50 | 34,000.00 | 9.00 | 36,000.00 | 9.60 | 38,400.00 |
| 0092 | 730-02-01040 | Conduit with Conductors (PVC/HDPE) (25 mm) (SCH. 40, Underground, 2 #8 XHHW-2,1 #88) | 1,450 | ln m | 14.00 | 20,300.00 | 17.40 | 25,230.00 | 14.00 | 20,300.00 | 15.00 | 21,750.00 |
| 0093 | 730-02-01040 | Conduit with Conductors (PVC/HDPE) (25 mm) (SCH. 40, Underground, 2 #6 XHHW-2,1 #68) | 3,974 | ln m | 23.00 | 91,402.00 | 19.10 | 75,903.40 | 24.00 | 95,376.00 | 26.00 | 103,324.00 |
| 0094 | 730-02-02040 | Conduit with Conductors (Rigid Aluminum) (25 mm) (Exposed, 2 #6 XHHW-2, 1 #6G) | 160 | ln m | 64.00 | 10,240.00 | 51.55 | 8,248.00 | 67.00 | 10,720.00 | 73.00 | 11,680.00 |
| 0095 | 730-02-04040 | Conduit with Conductors (Liquid Tight Flexible Metal) (25 mm) (Exposed, 2 #6 XHHW-2, 1 #6G) | 40 | ln m | 47.00 | 1,880.00 | 40.15 | 1,606.00 | 49.00 | 1,960.00 | 54.00 | 2,160.00 |
| 0096 | 730-04-00100 | Jacked or Bored Casing (100 mm Diameter) (PVC/HDPE) (PVC/HDPE)(SCH 80) | 175 | ln m | 73.00 | 12,775.00 | 84.15 | 14,726.25 | 75.00 | 13,125.00 | 82.00 | 14,350.00 |
| 0097 | 730-05-10000 | Light Pole (70")(Aluminum)(Twin Arm)(Lowering Device) | 2 | each | 52,000.00 | 104,000.00 | 40,000.00 | 80,000.00 | 55,000.00 | 110,000.00 | 60,000.00 | 120,000.00 |
| 0098 | 730-05-10000 | Light Pole (65")(Aluminum)(Twin Arm)(Lowering Device) | 2 | each | 51,000.00 | 102,000.00 | 27,500.00 | 55,000.00 | 53,500.00 | 107,000.00 | 59,000.00 | 118,000.00 |
| 0099 | 730-05-10000 | Light Pole (60")(Aluminum)(Twin Arm)(Lowering Device) | 1 | each | 51,000.00 | 51,000.00 | 44,500.00 | 44,500.00 | 53,000.00 | 53,000.00 | 59,000.00 | 59,000.00 |
| 0100 | 730-05-22120 | Light Pole (15 m) (Aluminum) (Single Arm) (Lowering Device) | 22 | each | 12,900.00 | 283,800.00 | 10,815.00 | 237,930.00 | 13,000.00 | 286,000.00 | 14,000.00 | 308,000.00 |
| 0101 | 730-05-22220 | Light Pole (15 m) (Aluminum) (Twin Arm) (Lowering Device) | 22 | each | 45,000.00 | 990,000.00 | 38,000.00 | 836,000.00 | 47,000.00 | 1,034,000.00 | 52,000.00 | 1,144,000.00 |
| 0102 | 730-07-04000 | Luminaire (150 Watt) (High PressureSodium) | 8 | each | 370.00 | 2,960.00 | 340.00 | 2,720.00 | 370.00 | 2,960.00 | 400.00 | 3,200.00 |
| 0103 | 730-07-05000 | Luminaire (250 Watt) (High PressureSodium) | 22 | each | 800.00 | 17,600.00 | 665.00 | 14,630.00 | 850.00 | 18,700.00 | 915.00 | 20,130.00 |
| 0104 | 730-07-06000 | Luminaire (400 Watt) (High PressureSodium) | 54 | each | 805.00 | 43,470.00 | 670.00 | 36,180.00 | 855.00 | 46,170.00 | 919.00 | 49,626.00 |
| 0105 | 730-08-00200 | Electrical Service Point (Structure) | 1 | each | 12,000.00 | 12,000.00 | 34,845.00 | 34,845.00 | 12,500.00 | 12,500.00 | 13,400.00 | 13,400.00 |
| 0106 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) (50") | 96 | each | 250.00 | 24,000.00 | 245.00 | 23,520.00 | 250.00 | 24,000.00 | 271.00 | 26,016.00 |
| 0107 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 96 | each | 575.00 | 55,200.00 | 345.00 | 33,120.00 | 600.00 | 57,600.00 | 650.00 | 62,400.00 |
| 0108 | 730-14-00100 | Removal and Disposal of Luminaires | 104 | each | 55.00 | 5,720.00 | 80.00 | 8,320.00 | 55.00 | 5,720.00 | 63.00 | 6,552.00 |
| 0109 | 730-16-00100 | Underground Junction Box (300 mm x 300 mm) | 49 | each | 450.00 | 22,050.00 | 160.00 | 7,840.00 | 470.00 | 23,030.00 | 507.00 | 24,843.00 |
| 0110 | 730-16-00200 | Underground Junction Box (275 mm x 450 mm) | 52 | each | 575.00 | 29,900.00 | 510.00 | 26,520.00 | 595.00 | 30,940.00 | 640.00 | 33,280.00 |
| 0111 | 730-16-00300 | Underground Junction Box (325 mm x 600 mm) | 11 | each | 625.00 | 6,875.00 | 530.00 | 5,830.00 | 625.00 | 6,875.00 | 674.00 | 7,414.00 |
| 0112 | 730-17-00100 | Structure Junction Box (200 mm x 200 mm x 100 mm) (Cast Aluminum) | 20 | each | 600.00 | 12,000.00 | 510.00 | 10,200.00 | 625.00 | 12,500.00 | 669.00 | 13,380.00 |
| 0113 | 730-19-00010 | Modular Breakaway Cable System | 49 | each | 2,000.00 | 98,000.00 | 1,730.00 | 84,770.00 | 2,050.00 | 100,450.00 | 2,200.00 | 107,800.00 |
| 0114 | 730-20-00020 | Disconnect (Service) (Non-fused) | 1 | each | 3,400.00 | 3,400.00 | 2,860.00 | 2,860.00 | 3,500.00 | 3,500.00 | 3,800.00 | 3,800.00 |
| 0115 | 730-20-00040 | Disconnect (Underpass) (Circuit Breaker) | 2 | each | 1,800.00 | 3,600.00 | 1,430.00 | 2,860.00 | 1,800.00 | 3,600.00 | 1,938.00 | 3,876.00 |
| 0116 | 730-21-00020 | Duct Marker (Concrete) | 10 | each | 280.00 | 2,800.00 | 170.00 | 1,700.00 | 290.00 | 2,900.00 | 314.00 | 3,140.00 |
| 0117 | 730-22-00220 | Underground Marker Tape (3")(Detectable) | 4,000 | ln m | 2.40 | 9,600.00 | 1.90 | 7,600.00 | 2.50 | 10,000.00 | 2.60 | 10,400.00 |
| 0118 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 390 | each | 0.55 | 214.50 | 9.00 | 3,510.00 | 10.00 | 3,900.00 | 10.00 | 3,900.00 |
| 0119 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,290 | each | 5.00 | 11,450.00 | 4.25 | 9,732.50 | 5.50 | 12,595.00 | 5.00 | 11,450.00 |
| 0120 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (100 mm Width) (Thermoplastic 90 mil) | 14.516 | km | 1,900.00 | 27,580.40 | 1,810.00 | 26,273.96 | 2,000.00 | 29,032.00 | 2,100.00 | 30,483.60 |
| 0121 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (150 mm Width) (Thermoplastic 90 mil) | 0.041 | km | 7,700.00 | 315.70 | 7,400.00 | 303.40 | 3,980.00 | 163.18 | 8,700.00 | 356.70 |
| 0122 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (200 mm Width) (Thermoplastic 90 mil) | 1.067 | km | 3,600.00 | 3,841.20 | 3,475.00 | 3,707.83 | 6,900.00 | 7,362.30 | 4,000.00 | 4,268.00 |
| 0123 | 732-02-02060 | Plastic Pavement Striping (Solid Line) (300 mm Width) (Thermoplastic 90 mil) | 0.176 | km | 5,850.00 | 1,029.60 | 5,525.00 | 972.40 | 8,000.00 | 1,408.00 | 6,500.00 | 1,144.00 |
| 0124 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (600 mm Width) (Thermoplastic 90 mil) | 0.866 | km | 10,200.00 | 8,833.20 | 10,030.00 | 8,685.98 | 18,500.00 | 16,021.00 | 11,500.00 | 9,959.00 |
| 0125 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (100 mm Width) (Thermoplastic 90 mil) | 4.482 | km | 700.00 | 3,137.40 | 700.00 | 3,137.40 | 800.00 | 3,585.60 | 800.00 | 3,585.60 |
| 0126 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | each | 200.00 | 400.00 | 190.00 | 380.00 | 225.00 | 450.00 | 216.00 | 432.00 |
| 0127 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | each | 210.00 | 420.00 | 200.00 | 400.00 | 235.00 | 470.00 | 229.00 | 458.00 |
| 0128 | 732-05-00100 | Removal of Existing Markings | 15.321 | km | 1,600.00 | 24,513.60 | 1,555.00 | 23,824.16 | 2,900.00 | 44,430.90 | 1,775.00 | 27,194.78 |
| 0129 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) (1370 mm w/Drainage Slot) | 3,356.7 | ln m | 470.00 | 1,577,649.00 | 575.00 | 1,930,102.50 | 660.00 | 2,215,422.00 | 540.00 | 1,812,618.00 |
| 0130 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) (810 mm) | 297 | ln m | 400.00 | 118,800.00 | 400.00 | 118,800.00 | 380.00 | 112,860.00 | 460.00 | 136,620.00 |
| 0131 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) (810 mm w/drainage slot) | 766.2 | ln m | 400.00 | 306,480.00 | 365.00 | 279,663.00 | 600.00 | 459,720.00 | 460.00 | 352,452.00 |
| 0132 | 740-01-00100 | Construction Layout | 1 | lump | 225,000.00 | 225,000.00 | 175,000.00 | 175,000.00 | 400,000.00 | 400,000.00 | 250,000.00 | 250,000.00 |
| 0133 | 740-02-00100 | Utility Oversight and Coordination | 1 | lump | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 |
| 0134 | 802-01-00100 | Structural Excavation | 2,403.36 | cu m | 23.00 | 55,277.28 | 40.00 | 96,134.40 | 19.00 | 45,663.84 | 26.00 | 62,487.36 |
| 0135 | 804-01-00200 | Precast Concrete Piles (350 mm) | 21,781.3 | ln m | 86.00 | 1,873,191.80 | 95.00 | 2,069,223.50 | 98.00 | 2,134,567.40 | 109.00 | 2,374,161.70 |
| 0136 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 2,400 | ln m | 72.00 | 172,800.00 | 75.00 | 180,000.00 | 47.00 | 112,800.00 | 86.50 | 207,600.00 |
| 0137 | 804-05-00200 | Precast Concrete Test Piles (350 mm) | 4 | each | 40,000.00 | 160,000.00 | 50,000.00 | 200,000.00 | 17,600.00 | 70,400.00 | 63,000.00 | 252,000.00 |
| 0138 | 804-09-00100 | Loading Test Piles | 4 | each | 1,500.00 | 6,000.00 | 10,000.00 | 40,000.00 | 18,000.00 | 72,000.00 | 1,729.00 | 6,916.00 |
| 0139 | 804-10-00100 | Reloading Test Piles | 1 | each | 500.00 | 500.00 | 5,000.00 | 5,000.00 | 750.00 | 750.00 | 576.00 | 576.00 |
| 0140 | 804-11-00100 | Redriving Test Piles | 1 | each | 500.00 | 500.00 | 2,500.00 | 2,500.00 | 1,000.00 | 1,000.00 | 576.00 | 576.00 |
| 0141 | 805-01-00400 | Class A Concrete (Retaining Walls) | 236.09 | cu m | 1,200.00 | 283,308.00 | 1,500.00 | 354,135.00 | 1,800.00 | 424,962.00 | 1,412.00 | 333,359.08 |
| 0142 | 805-01-00500 | Class A Concrete (Footings) | 1,130.9 | cu m | 330.00 | 373,197.00 | 430.00 | 486,287.00 | 475.00 | 537,177.50 | 576.00 | 651,398.40 |
| 0143 | 805-01-00700 | Class A Concrete (Bents) | 1,113.17 | cu m | 1,400.00 | 1,558,438.00 | 950.00 | 1,057,511.50 | 800.00 | 890,536.00 | 1,844.00 | 2,052,685.48 |
| 0144 | 805-03-00100 | Class AA Concrete | 3,445.11 | cu m | 670.00 | 2,308,223.70 | 800.00 | 2,756,088.00 | 1,150.00 | 3,961,876.50 | 864.00 | 2,976,575.04 |
| 0145 | 805-08-00300 | Precast-Prestressed Concrete Girder (Type III) | 4,579.77 | ln m | 300.00 | 1,373,931.00 | 300.00 | 1,373,931.00 | 375.00 | 1,717,413.75 | 413.00 | 1,891,445.01 |
| 0146 | 806-01-00100 | Deformed Reinforcing Steel | 669,157 | kg | 1.90 | 1,271,398.30 | 2.25 | 1,505,603.25 | 2.15 | 1,438,687.55 | 2.10 | 1,405,229.70 |
| 0147 | 807-08-00100 | Structural Metalwork | 1 | lump | 50,000.00 | 50,000.00 | 200,000.00 | 200,000.00 | 125,000.00 | 125,000.00 | 57,600.00 | 57,600.00 |
| 0148 | 810-01-00100 | Concrete Railing (Standard Barrier) (810 mm) | 1,008.91 | ln m | 165.00 | 166,470.15 | 175.00 | 176,559.25 | 170.00 | 171,514.70 | 190.00 | 191,692.90 |
| 0149 | 810-01-00100 | Concrete Railing (Standard Barrier) (1370 mm) | 990.46 | ln m | 300.00 | 297,138.00 | 365.00 | 361,517.90 | 270.00 | 267,424.20 | 345.00 | 341,708.70 |
| 0150 | 812-01-00100 | Treated Timber (Land and Fresh Water) | 723.95 | cu m | 365.00 | 264,241.75 | 375.00 | 271,481.25 | 375.00 | 271,481.25 | 445.00 | 322,157.75 |
| 0151 | 813-01-00100 | Concrete Approach Slabs | 361.4 | sq m | 265.00 | 95,771.00 | 265.00 | 95,771.00 | 315.00 | 113,841.00 | 305.00 | 110,227.00 |
| 0152 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 12 | each | 1,000.00 | 12,000.00 | 850.00 | 10,200.00 | 2,125.00 | 25,500.00 | 1,000.00 | 12,000.00 |
| 0153 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 5,468.8 | mmlm | 0.90 | 4,921.92 | 0.05 | 273.44 | 1.00 | 5,468.80 | 0.30 | 1,640.64 |
| 0154 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,000.3 | mmlm | 1.25 | 2,500.38 | 0.10 | 200.03 | 1.00 | 2,000.30 | 0.30 | 600.09 |
| 0155 | NS-700-00003 | Concrete Post (5.5 m) | 436 | each | 2,400.00 | 1,046,400.00 | 1,500.00 | 654,000.00 | 4,400.00 | 1,918,400.00 | 3,675.00 | 1,602,300.00 |
| 0156 | NS-700-00004 | Concrete Post (6.7 m) | 31 | each | 2,500.00 | 77,500.00 | 5,400.00 | 167,400.00 | 5,470.00 | 169,570.00 | 4,100.00 | 127,100.00 |
| 0157 | NS-700-00005 | Special Post | 8 | each | 6,500.00 | 52,000.00 | 1,850.00 | 14,800.00 | 6,200.00 | 49,600.00 | 5,500.00 | 44,000.00 |
| 0158 | NS-700-00006 | Noise Barrier Panel, Architectural (Precast Concrete) | 17,447.3 | sq m | 166.00 | 2,896,251.80 | 215.00 | 3,751,169.50 | 230.00 | 4,012,879.00 | 264.00 | 4,606,087.20 |
| 0159 | NS-700-00007 | Two Pile Concrete Cap | 43 | each | 2,050.00 | 88,150.00 | 1,600.00 | 68,800.00 | 3,860.00 | 165,980.00 | 5,000.00 | 215,000.00 |
| 0160 | NS-700-00008 | Four Pile Concrete Cap | 432 | each | 3,250.00 | 1,404,000.00 | 2,000.00 | 864,000.00 | 6,000.00 | 2,592,000.00 | 6,000.00 | 2,592,000.00 |
| 0161 | NS-700-00009 | Conflict Grade Beam | 27.43 | ln m | 700.00 | 19,201.00 | 650.00 | 17,829.50 | 725.00 | 19,886.75 | 1,180.00 | 32,367.40 |
| 0162 | NS-700-00010 | Precast Concrete Piles w/Tension Hooks (350 mm) | 25,766 | ln m | 92.00 | 2,370,472.00 | 110.00 | 2,834,260.00 | 97.00 | 2,499,302.00 | 110.00 | 2,834,260.00 |
| 0163 | NS-700-00180 | Impact Attenuator (Construction Zone) | 2 | each | 13,000.00 | 26,000.00 | 18,000.00 | 36,000.00 | 29,000.00 | 58,000.00 | 14,000.00 | 28,000.00 |
| 0164 | NS-700-00220 | Impact Attenuator (Kinetic) | 3 | each | 35,000.00 | 105,000.00 | 40,000.00 | 120,000.00 | 37,000.00 | 111,000.00 | 34,000.00 | 102,000.00 |
| 0165 | NS-713-00001 | Dynamic Message Sign Unit | 10 | each | 15,000.00 | 150,000.00 | 20,000.00 | 200,000.00 | 16,500.00 | 165,000.00 | 18,500.00 | 185,000.00 |
| 0166 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 1.8 | km | 8,000.00 | 14,400.00 | 4,000.00 | 7,200.00 | 10,000.00 | 18,000.00 | 800.00 | 1,440.00 |
| 0167 | NS-736-00120 | Construction Photographs And Video | 1 | lump | 25,000.00 | 25,000.00 | 175,000.00 | 175,000.00 | 37,000.00 | 37,000.00 | 107,000.00 | 107,000.00 |
| 0168 | NS-740-01020 | Noise Barrier Construction Layout | 1 | lump | 60,000.00 | 60,000.00 | 10,000.00 | 10,000.00 | 100,000.00 | 100,000.00 | 40,000.00 | 40,000.00 |
| 0169 | NS-800-00060 | Deck Drainage System (Type B) | 1 | lump | 5,000.00 | 5,000.00 | 100,000.00 | 100,000.00 | 255,000.00 | 255,000.00 | 5,800.00 | 5,800.00 |
| 0170 | NS-800-00060 | Deck Drainage System (Type A) | 1 | lump | 5,000.00 | 5,000.00 | 100,000.00 | 100,000.00 | 295,000.00 | 295,000.00 | 5,800.00 | 5,800.00 |
| 0171 | NS-800-00580 | Noise Reduction Systems (Absorptive Type) | 975 | ln m | 700.00 | 682,500.00 | 820.00 | 799,500.00 | 235.00 | 229,125.00 | 807.00 | 786,825.00 |
| 0172 | NS-804-00006 | Vibration Monitoring | 250 | daly | 600.00 | 150,000.00 | 750.00 | 187,500.00 | 2,000.00 | 500,000.00 | 1,300.00 | 325,000.00 |
| 0173 | NS-P26-06020 | Fittings for Waterlines (DI) (Jefferson Parish) | 275 | kg | 9.00 | 2,475.00 | 9.00 | 2,475.00 | 13.00 | 3,575.00 | 21.50 | 5,912.50 |
| 0174 | NS-P26-12080 | Long Body Transitional Coupling (305 mm) (Jefferson Parish) | 2 | each | 600.00 | 1,200.00 | 600.00 | 1,200.00 | 1,250.00 | 2,500.00 | 800.00 | 1,600.00 |
| 0175 | NS-P26-18000 | Removal and Disposal of Existing AC Waterline (Jefferson Parish) | 62 | ln m | 54.00 | 3,348.00 | 54.00 | 3,348.00 | 150.00 | 9,300.00 | 123.00 | 7,626.00 |
| 0176 | NS-P26-23040 | Waterline (300mm DI) (Restrained) (Jefferson Parish) | 9 | ln m | 660.00 | 5,940.00 | 660.00 | 5,940.00 | 465.00 | 4,185.00 | 440.00 | 3,960.00 |
| 0177 | NS-P26-23080 | Waterline (300mm PVC) (Jefferson Parish) | 29 | ln m | 198.00 | 5,742.00 | 198.00 | 5,742.00 | 265.00 | 7,685.00 | 150.00 | 4,350.00 |
| 0178 | NS-P26-23160 | Waterline (300mm PVC) (Restrained) (Jefferson Parish) | 30 | ln m | 330.00 | 9,900.00 | 326.00 | 9,780.00 | 365.00 | 10,950.00 | 620.00 | 18,600.00 |
| 0179 | 510-01-00200 | Pavement Patching (300 mm Minimum Thickness) | 31.5 | sq m | 351.00 | 11,056.50 | 750.00 | 23,625.00 | 300.00 | 9,450.00 | 350.00 | 11,025.00 |
| 0180 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 7,167.3 | ln m | 3.60 | 25,802.28 | 5.50 | 39,420.15 | 3.00 | 21,501.90 | 5.50 | 39,420.15 |
| 0181 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 355 | ln m | 17.37 | 6,166.35 | 16.00 | 5,680.00 | 3.00 | 1,065.00 | 16.00 | 5,680.00 |
| 0182 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 7,170 | ln m | 5.50 | 39,435.00 | 3.50 | 25,095.00 | 1.25 | 8,962.50 | 3.50 | 25,095.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 42,463,843.76 | 43,446,610.56 | 51,812,957.10 | 53,611,567.61 | ||||||||
| NUMBER OF DAYS BID AT $15000 PER DAY. | 9,000,000.00 | 8,250,000.00 | 10,950,000.00 | 11,625,000.00 | ||||||||
| TOTAL BID | 51,463,843.76 | 51,696,610.56 | 62,762,957.10 | 65,236,567.61 | ||||||||