Bid Tabulations
Letting of
06/30/2010
LA DOTD Headquarters
| Lead Project: 450-13-0051 | |
| Parish: St. John, Tangipahoa | |
| Routes: I-12, I-10 | |
| Description: I-10 & I-12 CABLE MEDIAN BARRIER INSTALLATION PROGRAM | |
| Type Const: INSTALLATION OF CABLE BARRIER SYSTEM, CONCRETE MOW STRIP, AND RELATED WORK. | |
| Estimated Construction Cost: $3,562,050.42 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 32954 | Gulf Equipment Corp. Of Alabama | $2,380,183.08 |
| 2 | 51292 | JJH Construction Co. LLC | $2,630,888.45 |
| 3 | 43371 | RMD Holdings Ltd | $2,767,192.35 |
| 4 | 48896 | Command Construction Industries LLC | $3,177,675.25 |
| 5 | 41771 | Holliday Construction Llc | $4,383,397.69 |
| 6 | 34068 | Alpha Service and Products, Inc. | $4,673,495.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gulf Equipment Corp. Of Alabama |
- 2 - JJH Construction Co. LLC |
- 3 - RMD Holdings Ltd |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 68,000.00 | 68,000.00 | 99,270.00 | 99,270.00 | 185,000.00 | 185,000.00 | 25,000.00 | 25,000.00 |
| 0002 | 204-06-00100 | Temporary Silt Fencing | 6,700 | LNFT | 2.00 | 13,400.00 | 1.75 | 11,725.00 | 1.60 | 10,720.00 | 2.00 | 13,400.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 242 | CUYD | 80.00 | 19,360.00 | 75.00 | 18,150.00 | 72.00 | 17,424.00 | 100.00 | 24,200.00 |
| 0004 | 701-15-00100 | Concrete Collar | 113 | EACH | 448.00 | 50,624.00 | 300.00 | 33,900.00 | 600.00 | 67,800.00 | 250.00 | 28,250.00 |
| 0005 | 702-04-00200 | Adjusting Catch Basins | 16 | EACH | 1,340.00 | 21,440.00 | 750.00 | 12,000.00 | 1,764.00 | 28,224.00 | 2,000.00 | 32,000.00 |
| 0006 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 138.6 | SQYD | 70.00 | 9,702.00 | 85.00 | 11,781.00 | 132.30 | 18,336.78 | 350.00 | 48,510.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 106,700.00 | 106,700.00 | 47,000.00 | 47,000.00 | 87,830.00 | 87,830.00 | 25,000.00 | 25,000.00 |
| 0008 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 18,000 | SQYD | 1.20 | 21,600.00 | 1.75 | 31,500.00 | 1.25 | 22,500.00 | 2.00 | 36,000.00 |
| 0009 | 721-01-00100 | Mowing | 1,012.61 | ACRE | 43.00 | 43,542.23 | 45.00 | 45,567.45 | 38.76 | 39,248.76 | 25.00 | 25,315.25 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 86,960.00 | 86,960.00 | 86,500.00 | 86,500.00 | 318,914.00 | 318,914.00 | 300,000.00 | 300,000.00 |
| 0011 | 739-01-00100 | Hydro-Seeding | 19.9 | ACRE | 2,000.00 | 39,800.00 | 1,000.00 | 19,900.00 | 1,080.45 | 21,500.96 | 2,500.00 | 49,750.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 14,000.00 | 14,000.00 | 30,000.00 | 30,000.00 | 25,305.00 | 25,305.00 | 25,000.00 | 25,000.00 |
| 0013 | NS-704-00001 | High Tension Cable Barrier | 86,507 | LNFT | 7.15 | 618,525.05 | 11.25 | 973,203.75 | 9.25 | 800,189.75 | 12.50 | 1,081,337.50 |
| 0014 | NS-704-00002 | Cable Barrier Gated End Terminal | 54 | EACH | 2,715.00 | 146,610.00 | 2,955.00 | 159,570.00 | 2,897.00 | 156,438.00 | 4,500.00 | 243,000.00 |
| 0015 | NS-704-00003 | Concrete Strip | 88,073 | LNFT | 12.60 | 1,109,719.80 | 11.25 | 990,821.25 | 10.70 | 942,381.10 | 12.50 | 1,100,912.50 |
| 0016 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 1,700.00 | 10,200.00 | 10,000.00 | 60,000.00 | 4,230.00 | 25,380.00 | 20,000.00 | 120,000.00 |
| CONTRACTOR TOTAL | 2,380,183.08 | 2,630,888.45 | 2,767,192.35 | 3,177,675.25 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Holliday Construction Llc |
- 6 - Alpha Service and Products, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 363,000.00 | 363,000.00 | 30,000.00 | 30,000.00 |
| 0002 | 204-06-00100 | Temporary Silt Fencing | 6,700 | LNFT | 5.00 | 33,500.00 | 2.50 | 16,750.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 242 | CUYD | 55.84 | 13,513.28 | 30.00 | 7,260.00 |
| 0004 | 701-15-00100 | Concrete Collar | 113 | EACH | 672.00 | 75,936.00 | 950.00 | 107,350.00 |
| 0005 | 702-04-00200 | Adjusting Catch Basins | 16 | EACH | 1,770.00 | 28,320.00 | 3,500.00 | 56,000.00 |
| 0006 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 138.6 | SQYD | 70.80 | 9,812.88 | 75.00 | 10,395.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 177,000.00 | 177,000.00 | 300,000.00 | 300,000.00 |
| 0008 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 18,000 | SQYD | 5.13 | 92,340.00 | 2.00 | 36,000.00 |
| 0009 | 721-01-00100 | Mowing | 1,012.61 | ACRE | 68.44 | 69,303.03 | 50.00 | 50,630.50 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 100,000.00 | 100,000.00 | 500,000.00 | 500,000.00 |
| 0011 | 739-01-00100 | Hydro-Seeding | 19.9 | ACRE | 3,000.00 | 59,700.00 | 1,500.00 | 29,850.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 250,000.00 | 250,000.00 | 30,000.00 | 30,000.00 |
| 0013 | NS-704-00001 | High Tension Cable Barrier | 86,507 | LNFT | 15.50 | 1,340,858.50 | 17.50 | 1,513,872.50 |
| 0014 | NS-704-00002 | Cable Barrier Gated End Terminal | 54 | EACH | 2,200.00 | 118,800.00 | 4,000.00 | 216,000.00 |
| 0015 | NS-704-00003 | Concrete Strip | 88,073 | LNFT | 18.00 | 1,585,314.00 | 19.00 | 1,673,387.00 |
| 0016 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 11,000.00 | 66,000.00 | 16,000.00 | 96,000.00 |
| CONTRACTOR TOTAL | 4,383,397.69 | 4,673,495.00 | ||||||