| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $682,454.65 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $735,646.35 |
| 3 | 34356 | Prairie Contractors Inc. | $1,134,894.61 |
| 4 | 51821 | Elliott Construction, LLC | $1,172,187.06 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Prairie Contractors Inc. |
- 4 - Elliott Construction, LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 50,000.00 | 50,000.00 | 35,000.00 | 35,000.00 | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 501-01-00001 | Thin Asphaltic Concrete | 795 | TON | 227.00 | 180,465.00 | 250.00 | 198,750.00 | 300.00 | 238,500.00 | 361.00 | 286,995.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 1,853.9 | TON | 115.00 | 213,198.50 | 140.00 | 259,546.00 | 200.00 | 370,780.00 | 241.00 | 446,789.90 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 7,183 | SQYD | 8.00 | 57,464.00 | 8.00 | 57,464.00 | 15.00 | 107,745.00 | 18.00 | 129,294.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -399 | CUYD | 0.10 | -39.90 | 10.00 | -3,990.00 | 0.01 | -3.99 | 0.01 | -3.99 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 68,000.00 | 68,000.00 | 100,000.00 | 100,000.00 | 125,000.00 | 125,000.00 | 85,000.00 | 85,000.00 |
| 0007 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.563 | MILE | 650.00 | 1,015.95 | 600.00 | 937.80 | 500.00 | 781.50 | 601.97 | 940.88 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.053 | MILE | 715.00 | 1,467.90 | 700.00 | 1,437.10 | 700.00 | 1,437.10 | 662.16 | 1,359.41 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 68,000.00 | 68,000.00 | 70,000.00 | 70,000.00 | 125,000.00 | 125,000.00 | 180,000.00 | 180,000.00 |
| 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 115 | EACH | 7.00 | 805.00 | 6.25 | 718.75 | 10.00 | 1,150.00 | 6.32 | 726.80 |
| 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.186 | MILE | 3,300.00 | 3,913.80 | 3,000.00 | 3,558.00 | 10,000.00 | 11,860.00 | 3,009.84 | 3,569.67 |
| 0012 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.861 | MILE | 1,100.00 | 947.10 | 1,000.00 | 861.00 | 5,000.00 | 4,305.00 | 1,023.34 | 881.10 |
| 0013 | 732-05-00100 | Removal of Existing Markings | 0.555 | MILE | 6,500.00 | 3,607.50 | 6,000.00 | 3,330.00 | 10,000.00 | 5,550.00 | 6,019.68 | 3,340.92 |
| 0014 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 2,600.00 | 2,600.00 | 2,300.00 | 2,300.00 | 5,000.00 | 5,000.00 | 2,648.66 | 2,648.66 |
| 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 28,875.00 | 28,875.00 | 5,200.00 | 5,200.00 | 70,000.00 | 70,000.00 | 15,000.00 | 15,000.00 |
| 0016 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 1.186 | MILE | 1,800.00 | 2,134.80 | 450.00 | 533.70 | 15,000.00 | 17,790.00 | 543.60 | 644.71 |
| CONTRACTOR TOTAL | 682,454.65 | 735,646.35 | 1,134,894.61 | 1,172,187.06 | ||||||||