Bid Tabulations
Letting of
10/09/2013
LA DOTD Headquarters
| Lead Project: 4400003910-R1 | |
| Parish: St. John, Tangipahoa | |
| Routes: I-55 | |
| Description: I-55 ASSET MAINTENANCE IN DISTRICT 62 | |
| Type Const: PERFORMING I-55 ASSET MAINTENANCE TO INCLUDE: REPAIR AND REPLACEMENT OF GUARDRAIL, IMPACT ATTENUATORS, AND CABLE BARRIERS, WHILE PERFORMING INT. SWEEPING, REST AREA MAINT., REST AREA SEC., MOWING OPERATIONS, ROAD & BRIDGE REP. IN DIST. 62 | |
| Estimated Construction Cost: $3,379,228.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49239 | WL Bass Construction Inc. | $3,643,995.00 |
| 2 | 49356 | Kort's Trucking Inc. | $4,379,200.00 |
| 3 | 48896 | Command Construction Industries LLC | $4,976,098.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - WL Bass Construction Inc. |
- 2 - Kort's Trucking Inc. |
- 3 - Command Construction Industries LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 15 | SQYD | 225.00 | 3,375.00 | 1,050.00 | 15,750.00 | 400.00 | 6,000.00 |
| 0002 | 510-01-00102 | Pavement Patching (8" Minimum Thickness) | 90 | SQYD | 225.00 | 20,250.00 | 210.00 | 18,900.00 | 150.00 | 13,500.00 |
| 0003 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 15 | SQYD | 280.00 | 4,200.00 | 1,200.00 | 18,000.00 | 900.00 | 13,500.00 |
| 0004 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 15 | SQYD | 300.00 | 4,500.00 | 1,250.00 | 18,750.00 | 1,000.00 | 15,000.00 |
| 0005 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 15 | SQYD | 300.00 | 4,500.00 | 1,250.00 | 18,750.00 | 1,250.00 | 18,750.00 |
| 0006 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 3,000 | LNFT | 4.00 | 12,000.00 | 3.00 | 9,000.00 | 4.00 | 12,000.00 |
| 0007 | 602-03-00100 | Cleaning and Sealing Random cracks | 500 | LNFT | 6.00 | 3,000.00 | 3.50 | 1,750.00 | 5.00 | 2,500.00 |
| 0008 | 602-05-01160 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9" Thick) | 15 | SQYD | 240.00 | 3,600.00 | 505.00 | 7,575.00 | 400.00 | 6,000.00 |
| 0009 | 602-05-01180 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9 1/2" Thick) | 15 | SQYD | 250.00 | 3,750.00 | 505.00 | 7,575.00 | 450.00 | 6,750.00 |
| 0010 | 602-05-01280 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (12" Thick) | 15 | SQYD | 265.00 | 3,975.00 | 520.00 | 7,800.00 | 500.00 | 7,500.00 |
| 0011 | 602-05-02160 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9" Thick) | 60 | SQYD | 220.00 | 13,200.00 | 185.00 | 11,100.00 | 300.00 | 18,000.00 |
| 0012 | 602-05-02180 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9 1/2" Thick) | 60 | SQYD | 220.00 | 13,200.00 | 185.00 | 11,100.00 | 350.00 | 21,000.00 |
| 0013 | 602-05-02280 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (12" Thick) | 60 | SQYD | 230.00 | 13,800.00 | 225.00 | 13,500.00 | 400.00 | 24,000.00 |
| 0014 | 602-05-03160 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) | 150 | SQYD | 150.00 | 22,500.00 | 180.00 | 27,000.00 | 175.00 | 26,250.00 |
| 0015 | 602-05-03180 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9 1/2" Thick) | 150 | SQYD | 150.00 | 22,500.00 | 180.00 | 27,000.00 | 180.00 | 27,000.00 |
| 0016 | 602-05-03280 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (12" Thick) | 150 | SQYD | 160.00 | 24,000.00 | 200.00 | 30,000.00 | 200.00 | 30,000.00 |
| 0017 | 602-09-00100 | Grinding Isolated Joints | 15 | SQYD | 100.00 | 1,500.00 | 250.00 | 3,750.00 | 50.00 | 750.00 |
| 0018 | 701-14-00100 | Cleaning Existing Pipes | 990 | LNFT | 8.00 | 7,920.00 | 10.00 | 9,900.00 | 50.00 | 49,500.00 |
| 0019 | 705-01-00100 | Barbed Wire Fence | 3,000 | LNFT | 10.00 | 30,000.00 | 9.00 | 27,000.00 | 15.00 | 45,000.00 |
| 0020 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 3,000 | LNFT | 10.00 | 30,000.00 | 10.00 | 30,000.00 | 15.00 | 45,000.00 |
| 0021 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 3,000 | LNFT | 20.00 | 60,000.00 | 18.50 | 55,500.00 | 22.00 | 66,000.00 |
| 0022 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 3,000 | LNFT | 20.00 | 60,000.00 | 21.50 | 64,500.00 | 25.00 | 75,000.00 |
| 0023 | 729-14-00100 | Delineator Assembly (Ground Mounted) | 90 | EACH | 87.00 | 7,830.00 | 150.00 | 13,500.00 | 50.00 | 4,500.00 |
| 0024 | 729-15-00100 | Delineator Assembly (Structure Mounted) | 90 | EACH | 305.00 | 27,450.00 | 200.00 | 18,000.00 | 150.00 | 13,500.00 |
| 0025 | 729-16-00100 | Object Marker Assembly (Type 1) | 90 | EACH | 87.00 | 7,830.00 | 175.00 | 15,750.00 | 30.00 | 2,700.00 |
| 0026 | 729-16-00200 | Object Marker Assembly (Type 2) | 90 | EACH | 75.00 | 6,750.00 | 115.00 | 10,350.00 | 30.00 | 2,700.00 |
| 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 90 | EACH | 90.00 | 8,100.00 | 65.00 | 5,850.00 | 80.00 | 7,200.00 |
| 0028 | 729-17-00100 | Milepost Assembly (Ground Mounted) | 90 | EACH | 330.00 | 29,700.00 | 375.00 | 33,750.00 | 125.00 | 11,250.00 |
| 0029 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 90 | EACH | 412.00 | 37,080.00 | 425.00 | 38,250.00 | 225.00 | 20,250.00 |
| 0030 | 729-18-00200 | Milepost Assembly (Structure Mounted) (Secondary) | 90 | EACH | 423.00 | 38,070.00 | 315.00 | 28,350.00 | 150.00 | 13,500.00 |
| 0031 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 15 | EACH | 1,150.00 | 17,250.00 | 2,200.00 | 33,000.00 | 250.00 | 3,750.00 |
| 0032 | NS-201-00002 | Tree and Stump Removal (Over 36" - 48" Diameter) | 15 | EACH | 1,800.00 | 27,000.00 | 3,400.00 | 51,000.00 | 350.00 | 5,250.00 |
| 0033 | NS-201-00003 | Tree and Stump Removal (Over 48" Diameter) | 15 | EACH | 3,250.00 | 48,750.00 | 4,000.00 | 60,000.00 | 500.00 | 7,500.00 |
| 0034 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 300 | INLF | 4.00 | 1,200.00 | 2.40 | 720.00 | 25.00 | 7,500.00 |
| 0035 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 300 | INLF | 4.00 | 1,200.00 | 3.60 | 1,080.00 | 25.00 | 7,500.00 |
| 0036 | NS-702-00001 | Cleaning Existing Catch Basin | 60 | EACH | 285.00 | 17,100.00 | 225.00 | 13,500.00 | 250.00 | 15,000.00 |
| 0037 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension | 75 | LF | 20.00 | 1,500.00 | 23.00 | 1,725.00 | 30.00 | 2,250.00 |
| 0038 | NS-810-00002 | Barrier Rail Repair | 30 | LNFT | 285.00 | 8,550.00 | 525.00 | 15,750.00 | 750.00 | 22,500.00 |
| 0039 | NS-MNT-02650 | Repair and Replacement of Guardrail on I-55 In District 62. | 2,700 | LNFT | 65.00 | 175,500.00 | 100.00 | 270,000.00 | 150.00 | 405,000.00 |
| 0040 | NS-MNT-05000 | One Cycle Litter and Trash Collection on Control Section 452-90 (Approximately 997 Acres) in District 62 | 24 | EACH | 16,000.00 | 384,000.00 | 23,280.00 | 558,720.00 | 35,000.00 | 840,000.00 |
| 0041 | NS-MNT-05020 | One Cycle Maintenance Mowing on Control Section 452-90. (Approximately 997 Acres) in District 62 | 18 | EACH | 19,000.00 | 342,000.00 | 32,400.00 | 583,200.00 | 35,000.00 | 630,000.00 |
| 0042 | NS-MNT-05040 | Cutting Brush | 30 | ACRE | 100.00 | 3,000.00 | 2,000.00 | 60,000.00 | 1,250.00 | 37,500.00 |
| 0043 | NS-MNT-05060 | Tree Removal (Less than 18" in diameter) | 60 | EACH | 50.00 | 3,000.00 | 550.00 | 33,000.00 | 150.00 | 9,000.00 |
| 0044 | NS-MNT-05080 | Tree Removal (18" in diameter and greater) | 30 | EACH | 50.00 | 1,500.00 | 550.00 | 16,500.00 | 250.00 | 7,500.00 |
| 0045 | NS-MNT-07000 | Interstate Sweeping on I-55 In District 62. | 1,560 | CURM | 225.00 | 351,000.00 | 200.00 | 312,000.00 | 100.00 | 156,000.00 |
| 0046 | NS-MNT-10000 | Maintenance and Operation of Interstate Rest Areas at (Kentwood) on I-55 In District 62. | 1,095 | DAY | 685.00 | 750,075.00 | 637.00 | 697,515.00 | 1,200.00 | 1,314,000.00 |
| 0047 | NS-MNT-10060 | Rest Area Security at (Kentwood) on I-55 In District 62. | 1,095 | DAY | 250.00 | 273,750.00 | 365.00 | 399,675.00 | 425.00 | 465,375.00 |
| 0048 | NS-MNT-10100 | Mobilization of Asset Maintenance Contract | 1 | LUMP | 540,000.00 | 540,000.00 | 429,879.00 | 429,879.00 | 300,000.00 | 300,000.00 |
| 0049 | NS-MNT-10102 | Cleaning & Reshaping Ditches | 600 | LNFT | 5.00 | 3,000.00 | 9.00 | 5,400.00 | 25.00 | 15,000.00 |
| 0050 | NS-MNT-90250 | Removal of Debris (Bridge Drains) | 30 | EACH | 55.00 | 1,650.00 | 93.00 | 2,790.00 | 100.00 | 3,000.00 |
| 0052 | NS-MNT-90252 | Pick-up and Disposal of Roadside Debris | 16,839 | MILE | 10.00 | 168,390.00 | 14.00 | 235,746.00 | 7.00 | 117,873.00 |
| CONTRACTOR TOTAL | 3,643,995.00 | 4,379,200.00 | 4,976,098.00 | |||||||