Bid Tabulations
Letting of
05/25/2011
LA DOTD Headquarters
| Lead Project: 409-02-0018 | |
| Parish: Orleans | |
| Routes: LA 407, LA 406 | |
| Description: LEVELING APPROACH SLABS AND IMPROVEMENTS | |
| Type Const: Leveling approach slabs, barrier work, cold planing asphalt pavement, superpave asphaltic concrete overlay, and related work | |
| Estimated Construction Cost: $485,536.90 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $554,247.99 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $607,830.36 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 483.5 | LNFT | 6.00 | 2,901.00 | 6.00 | 2,901.00 |
| 0002 | 203-02-00100 | Drainage Excavation | 19 | CUYD | 40.00 | 760.00 | 50.00 | 950.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 415 | CUYD | 52.00 | 21,580.00 | 45.00 | 18,675.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 5 | CUYD | 95.00 | 475.00 | 70.00 | 350.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 2,725.7 | TON | 101.00 | 275,295.70 | 130.00 | 354,341.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 61 | TON | 210.00 | 12,810.00 | 160.00 | 9,760.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 10,881.9 | SQYD | 3.00 | 32,645.70 | 1.50 | 16,322.85 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -510 | CUYD | 10.00 | -5,100.00 | 25.00 | -12,750.00 |
| 0009 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 256.25 | LNFT | 34.00 | 8,712.50 | 35.00 | 8,968.75 |
| 0010 | 704-03-00100 | Blocked Out Guard Rail | 81.25 | LNFT | 23.00 | 1,868.75 | 24.00 | 1,950.00 |
| 0011 | 704-04-00100 | Blocked Out Guard Rail (Double Faced) | 206.25 | LNFT | 42.00 | 8,662.50 | 42.00 | 8,662.50 |
| 0012 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 75 | LNFT | 42.00 | 3,150.00 | 44.00 | 3,300.00 |
| 0013 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 172.92 | LNFT | 67.00 | 11,585.64 | 70.00 | 12,104.40 |
| 0014 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,300.00 | 9,200.00 | 2,400.00 | 9,600.00 |
| 0015 | 704-11-00300 | Guard Rail End Treatment (Bi-Directional) | 1 | EACH | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 |
| 0016 | 707-01-00200 | Concrete Curb (Barrier) | 70 | LNFT | 55.00 | 3,850.00 | 75.00 | 5,250.00 |
| 0017 | 711-02-00300 | Riprap (30 lb) | 5 | CUYD | 600.00 | 3,000.00 | 100.00 | 500.00 |
| 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 55,000.00 | 55,000.00 | 38,000.00 | 38,000.00 |
| 0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.506 | MILE | 400.00 | 202.40 | 10.00 | 5.06 |
| 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.506 | MILE | 500.00 | 253.00 | 7.00 | 3.54 |
| 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.878 | MILE | 500.00 | 1,439.00 | 20.00 | 57.56 |
| 0022 | 717-01-00100 | Seeding | 25.5 | LB | 16.00 | 408.00 | 10.00 | 255.00 |
| 0023 | 718-01-00100 | Fertilizer | 850 | LB | 1.00 | 850.00 | 2.00 | 1,700.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 55,000.00 | 55,000.00 | 60,000.00 | 60,000.00 |
| 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 7 | EACH | 90.00 | 630.00 | 85.00 | 595.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 172 | EACH | 5.00 | 860.00 | 6.00 | 1,032.00 |
| 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.439 | MILE | 3,200.00 | 4,604.80 | 3,000.00 | 4,317.00 |
| 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.253 | MILE | 1,000.00 | 253.00 | 900.00 | 227.70 |
| 0029 | 735-01-00100 | Mailboxes | 2 | EACH | 7.00 | 14.00 | 6.00 | 12.00 |
| 0030 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 230.00 | 460.00 | 220.00 | 440.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,777.00 | 7,777.00 | 2,000.00 | 2,000.00 |
| 0032 | NS-700-00240 | Special Guard Rail Anchor Section | 1 | EACH | 1,400.00 | 1,400.00 | 1,300.00 | 1,300.00 |
| 0033 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 1,200.00 | 4,800.00 | 3,000.00 | 12,000.00 |
| 0034 | NS-810-00001 | Barrier Rail Rehabiltation outside | 172 | LNFT | 75.00 | 12,900.00 | 150.00 | 25,800.00 |
| 0035 | NS-810-00001 | Barrier Rail Rehabiltation median | 80 | LNFT | 125.00 | 10,000.00 | 165.00 | 13,200.00 |
| CONTRACTOR TOTAL | 554,247.99 | 607,830.36 | ||||||