Bid Tabulations
Letting of
03/30/2011
LA DOTD Headquarters
| Lead Project: 384-01-0022 | |
| Parish: Cameron | |
| Routes: LA 82 | |
| Description: 0.230 MILE W DEEP BAYOU RD - 0.030 MILE W MIDDLE RIDGE RD | |
| Type Const: MICROSURFACING, PAVEMENT MARKINGS, AND RELATED WORK | |
| Estimated Construction Cost: $319,865.99 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 14422 | T. L. Wallace Construction, Inc. | $182,259.89 |
| 2 | 32934 | Vance Brothers Inc. | $195,700.10 |
| 3 | 30339 | Missouri Petroleum Products Co. LLC | $232,569.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - T. L. Wallace Construction, Inc. |
- 2 - Vance Brothers Inc. |
- 3 - Missouri Petroleum Products Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 975.00 | 975.00 | 12,383.50 | 12,383.50 | 4,428.28 | 4,428.28 |
| 0002 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.467 | MILE | 400.00 | 1,386.80 | 420.00 | 1,456.14 | 400.00 | 1,386.80 |
| 0003 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.345 | MILE | 550.00 | 3,489.75 | 577.50 | 3,664.24 | 550.00 | 3,489.75 |
| 0004 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 915 | EACH | 1.35 | 1,235.25 | 2.00 | 1,830.00 | 1.35 | 1,235.25 |
| 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 6,300.00 | 6,300.00 | 20,000.00 | 20,000.00 | 32,862.00 | 32,862.00 |
| 0006 | 731-02-00100 | Reflectorized Raised Pavement Markers | 458 | EACH | 4.50 | 2,061.00 | 4.73 | 2,166.34 | 4.50 | 2,061.00 |
| 0007 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 6.345 | MILE | 2,700.00 | 17,131.50 | 2,835.00 | 17,988.08 | 2,700.00 | 17,131.50 |
| 0008 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.467 | MILE | 800.00 | 2,773.60 | 840.00 | 2,912.28 | 800.00 | 2,773.60 |
| 0009 | 732-05-00100 | Removal of Existing Markings | 3.467 | MILE | 4,000.00 | 13,868.00 | 4,200.00 | 14,561.40 | 4,000.00 | 13,868.00 |
| 0010 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,450.00 | 2,450.00 | 5,000.00 | 5,000.00 | 25,397.00 | 25,397.00 |
| 0011 | NS-500-00380 | Micro-surfacing Aggregate | 585.8 | TON | 110.00 | 64,438.00 | 102.51 | 60,050.36 | 113.00 | 66,195.40 |
| 0012 | NS-500-00400 | Micro-surfacing Asphalt | 19,174.2 | GAL | 3.45 | 66,150.99 | 2.80 | 53,687.76 | 3.22 | 61,740.92 |
| CONTRACTOR TOTAL | 182,259.89 | 195,700.10 | 232,569.50 | |||||||