Bid Tabulations
Letting of
04/27/2011
LA DOTD Headquarters
| Lead Project: 374-03-0023 | |
| Parish: Avoyelles | |
| Routes: LA 451 | |
| Description: IRON BR. CROSSING - POMME DE TERRE RESERVE | |
| Type Const: PAVEMENT PATCHING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK | |
| Estimated Construction Cost: $939,292.96 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $999,948.26 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,165,844.48 |
| 3 | 05789 | D & J Construction Co., Inc. | $1,385,312.51 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - D & J Construction Co., Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,000.00 | 2,000.00 | 3,500.00 | 3,500.00 | 3,000.00 | 3,000.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,330 | CUYD | 70.00 | 93,100.00 | 75.00 | 99,750.00 | 65.00 | 86,450.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 7,721.4 | TON | 80.00 | 617,712.00 | 95.00 | 733,533.00 | 112.00 | 864,796.80 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 276.4 | TON | 170.00 | 46,988.00 | 190.00 | 52,516.00 | 178.00 | 49,199.20 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 133 | SQYD | 14.00 | 1,862.00 | 46.00 | 6,118.00 | 55.00 | 7,315.00 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4 | CUYD | 10.00 | -40.00 | 0.10 | -0.40 | 0.10 | -0.40 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 900 | SQYD | 100.00 | 90,000.00 | 88.00 | 79,200.00 | 125.00 | 112,500.00 |
| 0008 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 128 | LNFT | 115.00 | 14,720.00 | 88.00 | 11,264.00 | 135.00 | 17,280.00 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 18,000.00 | 18,000.00 | 10,500.00 | 10,500.00 | 30,000.00 | 30,000.00 |
| 0010 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.426 | MILE | 250.00 | 1,356.50 | 170.00 | 922.42 | 250.00 | 1,356.50 |
| 0011 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.466 | MILE | 1.00 | 4.47 | 160.00 | 714.56 | 200.00 | 893.20 |
| 0012 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 3.21 | MILE | 1.00 | 3.21 | 310.00 | 995.10 | 1.00 | 3.21 |
| 0013 | 716-01-00100 | Mulch (Vegetative) | 8 | TON | 430.00 | 3,440.00 | 410.00 | 3,280.00 | 400.00 | 3,200.00 |
| 0014 | 717-01-00100 | Seeding | 120 | LB | 7.75 | 930.00 | 7.00 | 840.00 | 7.00 | 840.00 |
| 0015 | 718-01-00100 | Fertilizer | 4,000 | LB | 0.40 | 1,600.00 | 0.36 | 1,440.00 | 0.35 | 1,400.00 |
| 0016 | 726-01-00100 | Bedding Material | 25.6 | CUYD | 125.00 | 3,200.00 | 95.00 | 2,432.00 | 100.00 | 2,560.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 77,700.00 | 77,700.00 | 125,000.00 | 125,000.00 |
| 0018 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 120.00 | 720.00 | 125.00 | 750.00 | 125.00 | 750.00 |
| 0019 | 731-02-00100 | Reflectorized Raised Pavement Markers | 720 | EACH | 6.65 | 4,788.00 | 6.50 | 4,680.00 | 6.00 | 4,320.00 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.21 | MILE | 2,900.00 | 9,309.00 | 2,800.00 | 8,988.00 | 2,800.00 | 8,988.00 |
| 0021 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.466 | MILE | 880.00 | 3,930.08 | 800.00 | 3,572.80 | 1,000.00 | 4,466.00 |
| 0022 | 735-01-00100 | Mailboxes | 34 | EACH | 10.00 | 340.00 | 1.00 | 34.00 | 5.00 | 170.00 |
| 0023 | 735-02-00100 | Mailbox Supports (Single) | 27 | EACH | 135.00 | 3,645.00 | 115.00 | 3,105.00 | 125.00 | 3,375.00 |
| 0024 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 200.00 | 800.00 | 165.00 | 660.00 | 275.00 | 1,100.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 |
| 0026 | NS-500-00280 | Surface Preparation | 1 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 45,000.00 | 45,000.00 |
| 0027 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 25,400 | INLF | 0.10 | 2,540.00 | 0.25 | 6,350.00 | 0.25 | 6,350.00 |
| CONTRACTOR TOTAL | 999,948.26 | 1,165,844.48 | 1,385,312.51 | |||||||