Bid Tabulations
Letting of
02/23/2011
LA DOTD Headquarters
| Lead Project: 373-01-0021 | |
| Parish: Vernon | |
| Routes: LA 8 | |
| Description: LA 8 TURNLANES | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II AND IN-PLACE CEMENT TREATED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $738,758.51 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 30774 | Progressive Construction Co., LLC | $724,430.34 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $776,177.05 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $808,210.42 |
| 4 | 36384 | John Bailey, Inc. | $959,572.86 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Progressive Construction Co., LLC |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Diamond B Construction Co., L.L.C. |
- 4 - John Bailey, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 2,000.00 | 2,000.00 | 6,000.00 | 6,000.00 | 2,500.00 | 2,500.00 |
| 0002 | 202-02-38500 | Removal of Surfacing and Stablized Base | 7,664.9 | SQYD | 3.50 | 26,827.15 | 5.00 | 38,324.50 | 4.30 | 32,959.07 | 7.00 | 53,654.30 |
| 0003 | 203-01-00100 | General Excavation | 2,154 | CUYD | 8.00 | 17,232.00 | 6.80 | 14,647.20 | 13.00 | 28,002.00 | 12.00 | 25,848.00 |
| 0004 | 203-03-00100 | Embankment | 930 | CUYD | 20.00 | 18,600.00 | 25.00 | 23,250.00 | 16.00 | 14,880.00 | 18.00 | 16,740.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 42 | EACH | 12.00 | 504.00 | 20.00 | 840.00 | 11.00 | 462.00 | 25.00 | 1,050.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 35 | EACH | 125.00 | 4,375.00 | 185.00 | 6,475.00 | 246.00 | 8,610.00 | 200.00 | 7,000.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 5.00 | 1,500.00 | 3.50 | 1,050.00 | 8.00 | 2,400.00 | 4.00 | 1,200.00 |
| 0008 | 302-02-02080 | Class II Base Course (6" Thick) (Stone) | 8,580.2 | SQYD | 18.00 | 154,443.60 | 16.00 | 137,283.20 | 19.00 | 163,023.80 | 19.00 | 163,023.80 |
| 0009 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 8,583 | SQYD | 7.50 | 64,372.50 | 7.50 | 64,372.50 | 12.00 | 102,996.00 | 14.00 | 120,162.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 40.00 | 8,000.00 | 30.00 | 6,000.00 | 29.00 | 5,800.00 | 90.00 | 18,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 1,697.7 | TON | 110.00 | 186,747.00 | 100.00 | 169,770.00 | 115.00 | 195,235.50 | 150.00 | 254,655.00 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 634.2 | TON | 125.00 | 79,275.00 | 115.00 | 72,933.00 | 99.00 | 62,785.80 | 150.00 | 95,130.00 |
| 0013 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 3,000.00 | 3,000.00 | 4,000.00 | 4,000.00 | 3,700.00 | 3,700.00 | 4,000.00 | 4,000.00 |
| 0014 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 382.2 | SQYD | 50.00 | 19,110.00 | 58.00 | 22,167.60 | 75.00 | 28,665.00 | 65.00 | 24,843.00 |
| 0015 | 707-01-00300 | Concrete Curb (Mountable) | 683.3 | LNFT | 10.00 | 6,833.00 | 16.00 | 10,932.80 | 40.00 | 27,332.00 | 25.00 | 17,082.50 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,500.00 | 4,500.00 | 38,000.00 | 38,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 |
| 0017 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 735 | LNFT | 0.33 | 242.55 | 0.40 | 294.00 | 0.35 | 257.25 | 0.36 | 264.60 |
| 0018 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 24 | LNFT | 0.66 | 15.84 | 0.70 | 16.80 | 0.50 | 12.00 | 0.72 | 17.28 |
| 0019 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 188 | LNFT | 1.10 | 206.80 | 1.20 | 225.60 | 1.00 | 188.00 | 1.20 | 225.60 |
| 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.53 | MILE | 800.00 | 424.00 | 820.00 | 434.60 | 650.00 | 344.50 | 828.00 | 438.84 |
| 0021 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 6 | EACH | 75.00 | 450.00 | 75.00 | 450.00 | 60.00 | 360.00 | 78.00 | 468.00 |
| 0022 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 6 | EACH | 75.00 | 450.00 | 75.00 | 450.00 | 60.00 | 360.00 | 78.00 | 468.00 |
| 0023 | 716-01-00100 | Mulch (Vegetative) | 8 | TON | 500.00 | 4,000.00 | 475.00 | 3,800.00 | 450.00 | 3,600.00 | 600.00 | 4,800.00 |
| 0024 | 717-01-00100 | Seeding | 320 | LB | 10.00 | 3,200.00 | 8.30 | 2,656.00 | 8.00 | 2,560.00 | 10.00 | 3,200.00 |
| 0025 | 718-01-00100 | Fertilizer | 4,000 | LB | 0.50 | 2,000.00 | 0.45 | 1,800.00 | 0.40 | 1,600.00 | 0.60 | 2,400.00 |
| 0026 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 6,800 | SQYD | 0.90 | 6,120.00 | 1.20 | 8,160.00 | 1.10 | 7,480.00 | 1.25 | 8,500.00 |
| 0027 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 720 | SQYD | 1.35 | 972.00 | 1.30 | 936.00 | 1.20 | 864.00 | 2.00 | 1,440.00 |
| 0028 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 225 | SQYD | 1.80 | 405.00 | 1.35 | 303.75 | 1.30 | 292.50 | 2.50 | 562.50 |
| 0029 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5,500.00 | 5,500.00 | 8,000.00 | 8,000.00 | 2,500.00 | 2,500.00 | 15,000.00 | 15,000.00 |
| 0030 | 726-01-00100 | Bedding Material | 2 | CUYD | 100.00 | 200.00 | 200.00 | 400.00 | 110.00 | 220.00 | 150.00 | 300.00 |
| 0031 | 727-01-00100 | Mobilization | 1 | LUMP | 58,000.00 | 58,000.00 | 75,000.00 | 75,000.00 | 50,750.00 | 50,750.00 | 50,000.00 | 50,000.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 494 | EACH | 5.00 | 2,470.00 | 5.85 | 2,889.90 | 4.60 | 2,272.40 | 5.88 | 2,904.72 |
| 0033 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,623 | LNFT | 1.10 | 2,885.30 | 1.20 | 3,147.60 | 1.10 | 2,885.30 | 1.20 | 3,147.60 |
| 0034 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 48 | LNFT | 2.50 | 120.00 | 3.00 | 144.00 | 2.10 | 100.80 | 3.00 | 144.00 |
| 0035 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 727 | LNFT | 5.50 | 3,998.50 | 6.00 | 4,362.00 | 4.10 | 2,980.70 | 6.00 | 4,362.00 |
| 0036 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.018 | MILE | 2,700.00 | 2,748.60 | 3,000.00 | 3,054.00 | 2,600.00 | 2,646.80 | 3,090.00 | 3,145.62 |
| 0037 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 200.00 | 2,400.00 | 210.00 | 2,520.00 | 260.00 | 3,120.00 | 210.00 | 2,520.00 |
| 0038 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 12 | EACH | 210.00 | 2,520.00 | 230.00 | 2,760.00 | 260.00 | 3,120.00 | 234.00 | 2,808.00 |
| 0039 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 30,000.00 | 30,000.00 | 14,000.00 | 14,000.00 | 9,500.00 | 9,500.00 |
| 0040 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 22,750 | INLF | 0.75 | 17,062.50 | 0.50 | 11,375.00 | 0.30 | 6,825.00 | 0.57 | 12,967.50 |
| 0041 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 0.68 | MILE | 4,000.00 | 2,720.00 | 1,400.00 | 952.00 | 1,500.00 | 1,020.00 | 7,500.00 | 5,100.00 |
| CONTRACTOR TOTAL | 724,430.34 | 776,177.05 | 808,210.42 | 959,572.86 | ||||||||