Bid Tabulations
Letting of
07/21/2010
LA DOTD Headquarters
| Lead Project: 373-01-0020 | |
| Parish: Vernon | |
| Routes: LA 8 | |
| Description: LA 8 / US 171 ROUNDABOUT | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTUES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $2,385,756.98 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $2,141,165.49 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $2,295,832.55 |
| 3 | 30774 | Progressive Construction Co., Inc. | $2,514,961.02 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Progressive Construction Co., Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 75,000.00 | 75,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | 40,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 29,000.00 | 29,000.00 | 5,000.00 | 5,000.00 | 24,000.00 | 24,000.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 3,431 | SQYD | 13.00 | 44,603.00 | 9.50 | 32,594.50 | 9.00 | 30,879.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 10,131.6 | SQYD | 12.00 | 121,579.20 | 7.00 | 70,921.20 | 9.00 | 91,184.40 |
| 0005 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 6,000.00 | 6,000.00 | 12,000.00 | 12,000.00 | 10,500.00 | 10,500.00 |
| 0006 | 203-01-00100 | General Excavation | 17,745 | CUYD | 5.50 | 97,597.50 | 5.70 | 101,146.50 | 8.50 | 150,832.50 |
| 0007 | 203-03-00100 | Embankment | 6,968 | CUYD | 5.50 | 38,324.00 | 10.50 | 73,164.00 | 15.00 | 104,520.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 25 | EACH | 200.00 | 5,000.00 | 330.00 | 8,250.00 | 125.00 | 3,125.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 3,450 | LNFT | 5.00 | 17,250.00 | 1.80 | 6,210.00 | 2.50 | 8,625.00 |
| 0010 | 302-02-02080 | Class II Base Course (6" Thick) (Stone) | 14,785 | SQYD | 18.00 | 266,130.00 | 17.50 | 258,737.50 | 20.25 | 299,396.25 |
| 0011 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 14,785 | SQYD | 11.50 | 170,027.50 | 15.30 | 226,210.50 | 10.00 | 147,850.00 |
| 0012 | 304-05-00100 | Lime Treatment (Type E) | 41.92 | TON | 330.00 | 13,833.60 | 320.00 | 13,414.40 | 250.00 | 10,480.00 |
| 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 27 | CUYD | 43.00 | 1,161.00 | 55.00 | 1,485.00 | 100.00 | 2,700.00 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 150 | CUYD | 20.00 | 3,000.00 | 40.00 | 6,000.00 | 100.00 | 15,000.00 |
| 0015 | 502-01-00100 | Superpave Asphaltic Concrete | 3,959.1 | TON | 89.00 | 352,359.90 | 86.00 | 340,482.60 | 100.00 | 395,910.00 |
| 0016 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 732.9 | SQYD | 80.00 | 58,632.00 | 95.00 | 69,625.50 | 71.50 | 52,402.35 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 356 | LNFT | 73.00 | 25,988.00 | 68.00 | 24,208.00 | 70.00 | 24,920.00 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 172 | LNFT | 100.00 | 17,200.00 | 95.00 | 16,340.00 | 100.00 | 17,200.00 |
| 0019 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,700.00 | 2,700.00 | 3,000.00 | 3,000.00 | 4,000.00 | 4,000.00 |
| 0020 | 702-03-00500 | Catch Basins (CB-06) | 2 | EACH | 4,300.00 | 8,600.00 | 6,500.00 | 13,000.00 | 4,000.00 | 8,000.00 |
| 0021 | 702-03-00700 | Catch Basins (CB-08) | 3 | EACH | 10,000.00 | 30,000.00 | 10,000.00 | 30,000.00 | 7,500.00 | 22,500.00 |
| 0022 | 707-01-00100 | Concrete Curb | 713.1 | LNFT | 26.00 | 18,540.60 | 27.00 | 19,253.70 | 25.00 | 17,827.50 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 3,943.9 | LNFT | 26.00 | 102,541.40 | 30.00 | 118,317.00 | 25.00 | 98,597.50 |
| 0024 | 711-01-03020 | Riprap (30 lb, 18" Thick) | 260 | SQYD | 95.00 | 24,700.00 | 55.00 | 14,300.00 | 75.00 | 19,500.00 |
| 0025 | 711-04-00100 | Geotextile Fabric | 260 | SQYD | 4.00 | 1,040.00 | 2.00 | 520.00 | 2.50 | 650.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | 50,000.00 | 50,000.00 |
| 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 237 | LNFT | 0.25 | 59.25 | 0.30 | 71.10 | 0.22 | 52.14 |
| 0028 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,611 | LNFT | 0.70 | 1,127.70 | 1.00 | 1,611.00 | 0.66 | 1,063.26 |
| 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 3.886 | MILE | 500.00 | 1,943.00 | 650.00 | 2,525.90 | 440.00 | 1,709.84 |
| 0030 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 3 | EACH | 55.00 | 165.00 | 55.00 | 165.00 | 55.00 | 165.00 |
| 0031 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 152 | EACH | 1.25 | 190.00 | 1.50 | 228.00 | 1.10 | 167.20 |
| 0032 | 716-01-00100 | Mulch (Vegetative) | 6.5 | TON | 450.00 | 2,925.00 | 700.00 | 4,550.00 | 660.00 | 4,290.00 |
| 0033 | 717-01-00100 | Seeding | 260 | LB | 7.25 | 1,885.00 | 4.83 | 1,255.80 | 4.40 | 1,144.00 |
| 0034 | 718-01-00100 | Fertilizer | 3,250 | LB | 0.50 | 1,625.00 | 0.85 | 2,762.50 | 0.80 | 2,600.00 |
| 0035 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 8,601 | SQYD | 1.25 | 10,751.25 | 1.35 | 11,611.35 | 1.25 | 10,751.25 |
| 0036 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 133 | SQYD | 2.00 | 266.00 | 3.60 | 478.80 | 3.30 | 438.90 |
| 0037 | 725-01-00100 | Temporary Detour Roads | 8,117 | SQYD | 15.00 | 121,755.00 | 35.00 | 284,095.00 | 70.00 | 568,190.00 |
| 0038 | 726-01-00100 | Bedding Material | 216.9 | CUYD | 100.00 | 21,690.00 | 100.00 | 21,690.00 | 80.00 | 17,352.00 |
| 0039 | 727-01-00100 | Mobilization | 1 | LUMP | 200,000.00 | 200,000.00 | 225,000.00 | 225,000.00 | 106,000.00 | 106,000.00 |
| 0040 | 729-01-00100 | Sign (Type A) | 337 | SQFT | 16.00 | 5,392.00 | 25.00 | 8,425.00 | 25.00 | 8,425.00 |
| 0041 | 729-21-00100 | U-Channel Post | 39 | EACH | 50.00 | 1,950.00 | 75.00 | 2,925.00 | 150.00 | 5,850.00 |
| 0042 | 731-02-00100 | Reflectorized Raised Pavement Markers | 144 | EACH | 4.60 | 662.40 | 6.25 | 900.00 | 5.00 | 720.00 |
| 0043 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 502 | LNFT | 1.10 | 552.20 | 1.63 | 818.26 | 1.10 | 552.20 |
| 0044 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 596 | LNFT | 3.10 | 1,847.60 | 5.44 | 3,242.24 | 3.30 | 1,966.80 |
| 0045 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.982 | MILE | 2,300.00 | 2,258.60 | 3,000.00 | 2,946.00 | 2,500.00 | 2,455.00 |
| 0046 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 1.534 | MILE | 5,100.00 | 7,823.40 | 7,700.00 | 11,811.80 | 5,500.00 | 8,437.00 |
| 0047 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.509 | MILE | 710.00 | 361.39 | 1,000.00 | 509.00 | 770.00 | 391.93 |
| 0048 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 210.00 | 420.00 | 245.00 | 490.00 | 220.00 | 440.00 |
| 0049 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 4 | EACH | 210.00 | 840.00 | 315.00 | 1,260.00 | 220.00 | 880.00 |
| 0050 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 210.00 | 630.00 | 255.00 | 765.00 | 220.00 | 660.00 |
| 0051 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 210.00 | 630.00 | 265.00 | 795.00 | 220.00 | 660.00 |
| 0052 | 732-04-25020 | Plastic Pavement Legends and Symbols (Yield Line) | 7 | EACH | 210.00 | 1,470.00 | 235.00 | 1,645.00 | 220.00 | 1,540.00 |
| 0053 | 736-11-00500 | Conduit (4" HDPE, Schedule 80) | 120 | LNFT | 17.00 | 2,040.00 | 30.00 | 3,600.00 | 15.00 | 1,800.00 |
| 0054 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0055 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 2,766 | INLF | 2.00 | 5,532.00 | 1.00 | 2,766.00 | 2.00 | 5,532.00 |
| 0056 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,408 | INLF | 2.00 | 2,816.00 | 1.80 | 2,534.40 | 3.50 | 4,928.00 |
| 0057 | NS-700-00320 | White Preformed Heat-Applied Retroreflective Thermoplastic Striping Material (Symbols) ROUNDABOUT ARROW - FISH HOOK | 5 | EACH | 450.00 | 2,250.00 | 475.00 | 2,375.00 | 500.00 | 2,500.00 |
| 0058 | NS-MSC-00120 | Drainage Structure PAVED GUTTER DRAINS | 17 | EACH | 5,500.00 | 93,500.00 | 3,400.00 | 57,800.00 | 3,100.00 | 52,700.00 |
| CONTRACTOR TOTAL | 2,141,165.49 | 2,295,832.55 | 2,514,961.02 | |||||||