Bid Tabulations
Letting of
06/15/2011
LA DOTD Headquarters
| Lead Project: 317-02-0021 | |
| Parish: Ouachita | |
| Routes: LA 151 | |
| Description: US 80 TO LA 837 | |
| Type Const: THIN ASPH. CONCRETE, DRAINAGE STRUCTURES, COLD PLANING, PVMT. PATCHING, AND RELATED WORK. | |
| Estimated Construction Cost: $398,127.84 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05789 | D & J Construction Co., Inc. | $369,006.55 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $393,702.90 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - D & J Construction Co., Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 1 | LUMP | 5,000.00 | 5,000.00 | 4,336.63 | 4,336.63 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 750.00 | 750.00 | 677.60 | 677.60 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 384 | LNFT | 50.00 | 19,200.00 | 6.78 | 2,603.52 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 25.00 | 250.00 | 47.43 | 474.30 |
| 0005 | 501-01-00003 | Thin Asphaltic Concrete (Fine Mix) | 1,006.4 | TON | 115.00 | 115,736.00 | 130.09 | 130,922.58 |
| 0006 | 501-02-00001 | Tack Coat (quantity is for Thin Asphaltic Concrete only) | 1,952 | GAL | 3.50 | 6,832.00 | 5.33 | 10,404.16 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 128.6 | TON | 200.00 | 25,720.00 | 227.60 | 29,269.36 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 131.8 | TON | 200.00 | 26,360.00 | 218.51 | 28,799.62 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 787 | SQYD | 16.00 | 12,592.00 | 19.62 | 15,440.94 |
| 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -10 | CUYD | 0.01 | -0.10 | 1.00 | -10.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 78 | SQYD | 175.00 | 13,650.00 | 229.86 | 17,929.08 |
| 0012 | 701-01-02001 | Cross Drain Pipe (24" RCP/PP/CMP) | 56 | LNFT | 150.00 | 8,400.00 | 182.95 | 10,245.20 |
| 0013 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 16 | LNFT | 100.00 | 1,600.00 | 135.52 | 2,168.32 |
| 0014 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 32 | LNFT | 150.00 | 4,800.00 | 182.95 | 5,854.40 |
| 0015 | 701-15-00100 | Concrete Collar | 1 | EACH | 700.00 | 700.00 | 813.12 | 813.12 |
| 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 3,000.00 | 3,000.00 | 3,726.79 | 3,726.79 |
| 0017 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 100 | LNFT | 35.00 | 3,500.00 | 46.08 | 4,608.00 |
| 0018 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 78 | LNFT | 62.00 | 4,836.00 | 81.31 | 6,342.18 |
| 0019 | 704-03-00100 | Blocked Out Guard Rail | 175 | LNFT | 21.00 | 3,675.00 | 27.10 | 4,742.50 |
| 0020 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,100.00 | 8,400.00 | 2,710.40 | 10,841.60 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 6,335.66 | 6,335.66 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.091 | MILE | 250.00 | 522.75 | 208.60 | 436.18 |
| 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.58 | MILE | 350.00 | 1,603.00 | 406.56 | 1,862.04 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 5,500.00 | 550.00 | 13,552.00 | 1,355.20 |
| 0025 | 717-01-00100 | Seeding | 4 | LB | 50.00 | 200.00 | 67.76 | 271.04 |
| 0026 | 718-01-00100 | Fertilizer | 60 | LB | 10.00 | 600.00 | 4.07 | 244.20 |
| 0027 | 726-01-00100 | Bedding Material | 26.6 | CUYD | 100.00 | 2,660.00 | 135.52 | 3,604.83 |
| 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 35,000.00 | 35,000.00 | 30,936.67 | 30,936.67 |
| 0029 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 | 101.64 | 406.56 |
| 0030 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 101.64 | 406.56 |
| 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 277 | EACH | 10.00 | 2,770.00 | 6.78 | 1,878.06 |
| 0032 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.58 | MILE | 3,500.00 | 16,030.00 | 3,523.51 | 16,137.68 |
| 0033 | 732-05-00100 | Removal of Existing Markings | 0.115 | MILE | 4,500.00 | 517.50 | 5,420.78 | 623.39 |
| 0034 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 3,930.07 | 3,930.07 |
| 0035 | NS-200-00020 | Cleaning Existing Ditches | 13 | LNFT | 10.00 | 130.00 | 10.84 | 140.92 |
| 0036 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 30,887.94 | 30,887.94 |
| 0037 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 4,056 | INLF | 0.40 | 1,622.40 | 1.00 | 4,056.00 |
| CONTRACTOR TOTAL | 369,006.55 | 393,702.90 | ||||||