Bid Tabulations
Letting of
10/27/2010
LA DOTD Headquarters
| Lead Project: 300-30-0008 | |
| Parish: Desoto | |
| Routes: LA 346 | |
| Description: OXFORD TO LA 175 | |
| Type Const: GRADING, CEMENT TREATED BASE COURSE, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK | |
| Estimated Construction Cost: $1,111,732.24 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $1,239,374.56 |
| 2 | 36374 | Best-Yet Builders, Llc | $1,321,956.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Best-Yet Builders, Llc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06020 | Removal of Concrete Box Culverts Station 41+70 (3' x 2' x 40' with headwalls) | 1 | EACH | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-02-06020 | Removal of Concrete Box Culverts Station 34+80 (3' x 2' x48' with headwalls) | 1 | EACH | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,000 | CUYD | 14.00 | 70,000.00 | 10.00 | 50,000.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 500 | CUYD | 12.00 | 6,000.00 | 15.00 | 7,500.00 |
| 0005 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 38,793 | SQYD | 8.50 | 329,740.50 | 9.00 | 349,137.00 |
| 0006 | 308-02-00100 | Removal of Existing Patches | 100 | SQYD | 10.00 | 1,000.00 | 50.00 | 5,000.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 100 | CUYD | 37.50 | 3,750.00 | 50.00 | 5,000.00 |
| 0008 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 32 | CUYD | 50.00 | 1,600.00 | 100.00 | 3,200.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 7,020.8 | TON | 86.40 | 606,597.12 | 94.00 | 659,955.20 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 500 | TON | 60.00 | 30,000.00 | 95.00 | 47,500.00 |
| 0011 | 701-02-01040 | Cross Drain Pipe Arch (36" Equiv. RCPA) | 88 | LNFT | 250.00 | 22,000.00 | 285.00 | 25,080.00 |
| 0012 | 701-08-00100 | Relaying Pipe | 44 | LNFT | 150.00 | 6,600.00 | 100.00 | 4,400.00 |
| 0013 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 32 | LNFT | 150.00 | 4,800.00 | 55.20 | 1,766.40 |
| 0014 | 701-14-00100 | Cleaning Existing Pipes | 64 | LNFT | 16.00 | 1,024.00 | 50.00 | 3,200.00 |
| 0015 | 701-15-00100 | Concrete Collar | 11 | EACH | 1,250.00 | 13,750.00 | 1,000.00 | 11,000.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 7,500.00 | 7,500.00 |
| 0017 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 48 | LNFT | 0.60 | 28.80 | 5.00 | 240.00 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 22.64 | MILE | 1.00 | 22.64 | 350.00 | 7,924.00 |
| 0019 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 750 | EACH | 1.50 | 1,125.00 | 2.00 | 1,500.00 |
| 0020 | 716-01-00100 | Mulch (Vegetative) | 6.9 | TON | 1,000.00 | 6,900.00 | 900.00 | 6,210.00 |
| 0021 | 717-01-00100 | Seeding | 138 | LB | 10.00 | 1,380.00 | 7.25 | 1,000.50 |
| 0022 | 718-01-00100 | Fertilizer | 3,430 | LB | 1.00 | 3,430.00 | 0.45 | 1,543.50 |
| 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 40,000.00 | 40,000.00 | 55,000.00 | 55,000.00 |
| 0024 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 75.00 | 900.00 | 65.00 | 780.00 |
| 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 375 | EACH | 4.50 | 1,687.50 | 5.00 | 1,875.00 |
| 0026 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 24 | LNFT | 5.00 | 120.00 | 10.00 | 240.00 |
| 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.32 | MILE | 2,200.00 | 24,904.00 | 2,750.00 | 31,130.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0029 | NS-200-00020 | Cleaning Existing Ditches | 100 | LNFT | 10.00 | 1,000.00 | 50.00 | 5,000.00 |
| 0030 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 16 | TON | 100.00 | 1,600.00 | 150.00 | 2,400.00 |
| 0031 | 735-01-00100 | Mailboxes | 15 | EACH | 1.00 | 15.00 | 50.00 | 750.00 |
| 0032 | 735-02-00100 | Mailbox Supports (Single) | 15 | EACH | 160.00 | 2,400.00 | 75.00 | 1,125.00 |
| CONTRACTOR TOTAL | 1,239,374.56 | 1,321,956.60 | ||||||