Bid Tabulations
Letting of
06/15/2011
LA DOTD Headquarters
| Lead Project: 291-02-0015 | |
| Parish: Claiborne | |
| Routes: LA 521 | |
| Description: SAND CREEK BRIDGE REPLACEMENT | |
| Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $782,091.66 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12135 | Blount Bros. Construction, Inc. | $785,933.65 |
| 2 | 18546 | C W & W Contractors, Inc. | $817,691.20 |
| 3 | 39462 | Jb James Construction Llc | $833,105.00 |
| 4 | 09090 | Guinn Brothers, LLC. | $903,657.40 |
| 5 | 01012 | Cecil D. Gassiott, LLC | $950,373.03 |
| 6 | 46451 | Proforce, LLC | $1,145,102.09 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Blount Bros. Construction, Inc. |
- 2 - C W & W Contractors, Inc. |
- 3 - Jb James Construction Llc |
- 4 - Guinn Brothers, LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 26,000.00 | 26,000.00 | 75,000.00 | 75,000.00 | 50,000.00 | 50,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 3,000.00 | 3,000.00 | 500.00 | 500.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge STA. 111+54.96; 27.0 ft X 57 FT CONCRETE PRECAST SLAB UNIT BRIDGE | 1 | EACH | 30,000.00 | 30,000.00 | 5,000.00 | 5,000.00 | 30,000.00 | 30,000.00 | 12,000.00 | 12,000.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 160 | LNFT | 10.00 | 1,600.00 | 6.00 | 960.00 | 5.00 | 800.00 | 10.00 | 1,600.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,863.8 | SQYD | 4.00 | 7,455.20 | 4.00 | 7,455.20 | 5.00 | 9,319.00 | 5.00 | 9,319.00 |
| 0006 | 203-01-00100 | General Excavation | 1,372 | CUYD | 4.00 | 5,488.00 | 11.00 | 15,092.00 | 10.00 | 13,720.00 | 5.00 | 6,860.00 |
| 0007 | 203-02-00100 | Drainage Excavation | 148 | CUYD | 15.00 | 2,220.00 | 11.00 | 1,628.00 | 20.00 | 2,960.00 | 10.00 | 1,480.00 |
| 0008 | 203-03-00100 | Embankment | 2,066 | CUYD | 12.00 | 24,792.00 | 15.00 | 30,990.00 | 20.00 | 41,320.00 | 18.00 | 37,188.00 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 150.00 | 2,400.00 | 150.00 | 2,400.00 | 20.00 | 320.00 | 100.00 | 1,600.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 1,960 | LNFT | 3.00 | 5,880.00 | 3.00 | 5,880.00 | 3.00 | 5,880.00 | 2.00 | 3,920.00 |
| 0011 | 302-02-04000 | Class II Base Course (8 1/2" Thick) | 3,866.9 | SQYD | 23.00 | 88,938.70 | 35.00 | 135,341.50 | 14.00 | 54,136.60 | 20.00 | 77,338.00 |
| 0012 | 304-05-00100 | Lime Treatment (Type E) | 8.41 | TON | 275.00 | 2,312.75 | 250.00 | 2,102.50 | 50.00 | 420.50 | 1,000.00 | 8,410.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 40.00 | 2,000.00 | 35.00 | 1,750.00 | 150.00 | 7,500.00 | 50.00 | 2,500.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 484.9 | TON | 140.00 | 67,886.00 | 175.00 | 84,857.50 | 185.00 | 89,706.50 | 200.00 | 96,980.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 266.4 | TON | 150.00 | 39,960.00 | 225.00 | 59,940.00 | 200.00 | 53,280.00 | 235.00 | 62,604.00 |
| 0016 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 64 | LNFT | 90.00 | 5,760.00 | 60.00 | 3,840.00 | 120.00 | 7,680.00 | 175.00 | 11,200.00 |
| 0017 | 704-03-00100 | Blocked Out Guard Rail | 362.5 | LNFT | 30.00 | 10,875.00 | 25.00 | 9,062.50 | 20.00 | 7,250.00 | 25.00 | 9,062.50 |
| 0018 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 100.00 | 10,000.00 | 90.00 | 9,000.00 | 55.00 | 5,500.00 | 62.00 | 6,200.00 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 3,000.00 | 12,000.00 | 2,800.00 | 11,200.00 | 2,100.00 | 8,400.00 | 2,500.00 | 10,000.00 |
| 0020 | 705-01-00100 | Barbed Wire Fence | 665 | LNFT | 10.00 | 6,650.00 | 8.00 | 5,320.00 | 7.00 | 4,655.00 | 10.00 | 6,650.00 |
| 0021 | 708-01-00100 | Right-of-Way Monument | 10 | EACH | 250.00 | 2,500.00 | 150.00 | 1,500.00 | 150.00 | 1,500.00 | 250.00 | 2,500.00 |
| 0022 | 708-02-00100 | Right-of-Way Monument Witness Post | 10 | EACH | 200.00 | 2,000.00 | 50.00 | 500.00 | 150.00 | 1,500.00 | 100.00 | 1,000.00 |
| 0023 | 712-04-00100 | Flexible Revetment | 800 | SQYD | 55.00 | 44,000.00 | 45.00 | 36,000.00 | 53.00 | 42,400.00 | 85.00 | 68,000.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 12,500.00 | 12,500.00 |
| 0025 | 716-01-00100 | Mulch (Vegetative) | 4 | TON | 600.00 | 2,400.00 | 1,500.00 | 6,000.00 | 650.00 | 2,600.00 | 1,000.00 | 4,000.00 |
| 0026 | 717-01-00100 | Seeding | 160 | LB | 10.00 | 1,600.00 | 10.00 | 1,600.00 | 10.00 | 1,600.00 | 20.00 | 3,200.00 |
| 0027 | 718-01-00100 | Fertilizer | 2,000 | LB | 1.00 | 2,000.00 | 0.50 | 1,000.00 | 1.00 | 2,000.00 | 0.75 | 1,500.00 |
| 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 2,000 | SQYD | 3.00 | 6,000.00 | 3.00 | 6,000.00 | 3.50 | 7,000.00 | 1.00 | 2,000.00 |
| 0029 | 726-01-00100 | Bedding Material | 30.2 | CUYD | 100.00 | 3,020.00 | 35.00 | 1,057.00 | 67.00 | 2,023.40 | 100.00 | 3,020.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 35,000.00 | 35,000.00 | 50,000.00 | 50,000.00 | 80,000.00 | 80,000.00 | 75,000.00 | 75,000.00 |
| 0031 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 100.00 | 200.00 | 100.00 | 200.00 | 75.00 | 150.00 | 100.00 | 200.00 |
| 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 150.00 | 600.00 | 100.00 | 400.00 | 75.00 | 300.00 | 100.00 | 400.00 |
| 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 22 | EACH | 25.00 | 550.00 | 100.00 | 2,200.00 | 22.00 | 484.00 | 30.00 | 660.00 |
| 0034 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 24 | LNFT | 20.00 | 480.00 | 50.00 | 1,200.00 | 15.00 | 360.00 | 20.00 | 480.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.318 | MILE | 6,000.00 | 1,908.00 | 10,000.00 | 3,180.00 | 10,000.00 | 3,180.00 | 7,000.00 | 2,226.00 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.159 | MILE | 3,000.00 | 477.00 | 5,000.00 | 795.00 | 3,000.00 | 477.00 | 4,000.00 | 636.00 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 9,000.00 | 9,000.00 | 8,000.00 | 8,000.00 | 15,000.00 | 15,000.00 |
| 0038 | 804-01-00300 | Precast Concrete Piles (16") | 900 | LNFT | 105.00 | 94,500.00 | 84.00 | 75,600.00 | 78.00 | 70,200.00 | 75.00 | 67,500.00 |
| 0039 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 2,500.00 | 2,500.00 | 1.00 | 1.00 | 500.00 | 500.00 | 1.00 | 1.00 |
| 0040 | 804-17-00100 | Dynamic Monitoring | 1 | EACH | 1,500.00 | 1,500.00 | 800.00 | 800.00 | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 |
| 0041 | 805-01-00700 | Class A Concrete (Bents) | 28.87 | CUYD | 600.00 | 17,322.00 | 800.00 | 23,096.00 | 1,400.00 | 40,418.00 | 1,200.00 | 34,644.00 |
| 0042 | 805-03-00100 | Class AA Concrete | 108.76 | CUYD | 700.00 | 76,132.00 | 900.00 | 97,884.00 | 650.00 | 70,694.00 | 1,000.00 | 108,760.00 |
| 0043 | 806-01-00100 | Deformed Reinforcing Steel | 24,321 | LB | 2.00 | 48,642.00 | 1.00 | 24,321.00 | 1.00 | 24,321.00 | 1.00 | 24,321.00 |
| 0044 | 810-01-00100 | Concrete Railing (Standard Barrier) | 160 | LNFT | 100.00 | 16,000.00 | 95.00 | 15,200.00 | 65.00 | 10,400.00 | 100.00 | 16,000.00 |
| 0045 | 813-01-00100 | Concrete Approach Slabs | 137.78 | SQYD | 250.00 | 34,445.00 | 200.00 | 27,556.00 | 200.00 | 27,556.00 | 255.00 | 35,133.90 |
| 0046 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 594 | INLF | 10.00 | 5,940.00 | 3.00 | 1,782.00 | 1.00 | 594.00 | 6.00 | 3,564.00 |
| CONTRACTOR TOTAL | 785,933.65 | 817,691.20 | 833,105.00 | 903,657.40 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Cecil D. Gassiott, LLC |
- 6 - Proforce, LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 25,000.00 | 25,000.00 | 23,699.38 | 23,699.38 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 21,699.38 | 21,699.38 |
| 0003 | 202-02-04000 | Removal of Bridge STA. 111+54.96; 27.0 ft X 57 FT CONCRETE PRECAST SLAB UNIT BRIDGE | 1 | EACH | 8,500.00 | 8,500.00 | 21,275.00 | 21,275.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 160 | LNFT | 6.00 | 960.00 | 3.50 | 560.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,863.8 | SQYD | 6.00 | 11,182.80 | 9.20 | 17,146.96 |
| 0006 | 203-01-00100 | General Excavation | 1,372 | CUYD | 12.00 | 16,464.00 | 12.00 | 16,464.00 |
| 0007 | 203-02-00100 | Drainage Excavation | 148 | CUYD | 15.00 | 2,220.00 | 14.50 | 2,146.00 |
| 0008 | 203-03-00100 | Embankment | 2,066 | CUYD | 20.00 | 41,320.00 | 15.00 | 30,990.00 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 200.00 | 3,200.00 | 100.00 | 1,600.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 1,960 | LNFT | 3.00 | 5,880.00 | 1.75 | 3,430.00 |
| 0011 | 302-02-04000 | Class II Base Course (8 1/2" Thick) | 3,866.9 | SQYD | 25.00 | 96,672.50 | 65.00 | 251,348.50 |
| 0012 | 304-05-00100 | Lime Treatment (Type E) | 8.41 | TON | 300.00 | 2,523.00 | 1,380.00 | 11,605.80 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 125.00 | 6,250.00 | 65.00 | 3,250.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 484.9 | TON | 210.00 | 101,829.00 | 203.50 | 98,677.15 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 266.4 | TON | 210.00 | 55,944.00 | 220.00 | 58,608.00 |
| 0016 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 64 | LNFT | 135.00 | 8,640.00 | 122.33 | 7,829.12 |
| 0017 | 704-03-00100 | Blocked Out Guard Rail | 362.5 | LNFT | 20.00 | 7,250.00 | 21.85 | 7,920.63 |
| 0018 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 58.00 | 5,800.00 | 63.25 | 6,325.00 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 2,415.00 | 9,660.00 |
| 0020 | 705-01-00100 | Barbed Wire Fence | 665 | LNFT | 12.00 | 7,980.00 | 10.00 | 6,650.00 |
| 0021 | 708-01-00100 | Right-of-Way Monument | 10 | EACH | 175.00 | 1,750.00 | 140.00 | 1,400.00 |
| 0022 | 708-02-00100 | Right-of-Way Monument Witness Post | 10 | EACH | 60.00 | 600.00 | 140.00 | 1,400.00 |
| 0023 | 712-04-00100 | Flexible Revetment | 800 | SQYD | 75.00 | 60,000.00 | 78.00 | 62,400.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 12,500.00 | 12,500.00 | 13,639.75 | 13,639.75 |
| 0025 | 716-01-00100 | Mulch (Vegetative) | 4 | TON | 1,100.00 | 4,400.00 | 565.00 | 2,260.00 |
| 0026 | 717-01-00100 | Seeding | 160 | LB | 10.00 | 1,600.00 | 8.00 | 1,280.00 |
| 0027 | 718-01-00100 | Fertilizer | 2,000 | LB | 1.00 | 2,000.00 | 0.50 | 1,000.00 |
| 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 2,000 | SQYD | 1.60 | 3,200.00 | 1.50 | 3,000.00 |
| 0029 | 726-01-00100 | Bedding Material | 30.2 | CUYD | 165.00 | 4,983.00 | 65.00 | 1,963.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 118,000.00 | 118,000.00 | 77,699.38 | 77,699.38 |
| 0031 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 80.00 | 160.00 | 86.25 | 172.50 |
| 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | 86.25 | 345.00 |
| 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 22 | EACH | 20.00 | 440.00 | 23.00 | 506.00 |
| 0034 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 24 | LNFT | 16.00 | 384.00 | 17.25 | 414.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.318 | MILE | 5,000.00 | 1,590.00 | 5,750.00 | 1,828.50 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.159 | MILE | 2,000.00 | 318.00 | 2,300.00 | 365.70 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,500.00 | 12,500.00 | 16,319.63 | 16,319.63 |
| 0038 | 804-01-00300 | Precast Concrete Piles (16") | 900 | LNFT | 80.00 | 72,000.00 | 114.19 | 102,771.00 |
| 0039 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,500.00 | 1,500.00 | 13,125.00 | 13,125.00 |
| 0040 | 804-17-00100 | Dynamic Monitoring | 1 | EACH | 4,000.00 | 4,000.00 | 393.75 | 393.75 |
| 0041 | 805-01-00700 | Class A Concrete (Bents) | 28.87 | CUYD | 1,700.00 | 49,079.00 | 1,515.94 | 43,765.19 |
| 0042 | 805-03-00100 | Class AA Concrete | 108.76 | CUYD | 1,000.00 | 108,760.00 | 840.00 | 91,358.40 |
| 0043 | 806-01-00100 | Deformed Reinforcing Steel | 24,321 | LB | 0.93 | 22,618.53 | 2.30 | 55,938.30 |
| 0044 | 810-01-00100 | Concrete Railing (Standard Barrier) | 160 | LNFT | 75.00 | 12,000.00 | 114.19 | 18,270.40 |
| 0045 | 813-01-00100 | Concrete Approach Slabs | 137.78 | SQYD | 240.00 | 33,067.20 | 232.31 | 32,007.67 |
| 0046 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 594 | INLF | 2.00 | 1,188.00 | 1.00 | 594.00 |
| CONTRACTOR TOTAL | 950,373.03 | 1,145,102.09 | ||||||