Bid Tabulations
Letting of
05/25/2011
LA DOTD Headquarters
| Lead Project: 283-30-0028 | |
| Parish: Jefferson | |
| Routes: LA 49 | |
| Description: ADD LEFT TURN LANES AND CHANNELIZE THE CROSSOVERS | |
| Type Const: PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE, INCIDENTAL CONCRETE PAVING, COMBINATION CONCRETE CURB AND GUTTER, PAVEMENT MARKERS, STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $448,253.55 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $467,672.10 |
| 2 | 52550 | Gibbs & Register Inc | $535,686.40 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $589,075.48 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Gibbs & Register Inc |
- 3 - Boh Bros. Construction Co., LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-00010 | Removal of removal of trees and shrubs less than 2.5' in diamter | 21 | EACH | 275.00 | 5,775.00 | 630.00 | 13,230.00 | 300.00 | 6,300.00 |
| 0002 | 202-02-02020 | Removal of Asphalt Pavement | 111 | SQYD | 50.00 | 5,550.00 | 25.00 | 2,775.00 | 20.00 | 2,220.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 1,860 | LNFT | 15.00 | 27,900.00 | 10.00 | 18,600.00 | 10.00 | 18,600.00 |
| 0004 | 202-02-38300 | Removal of Sign and U-Channel Post | 4 | EACH | 55.00 | 220.00 | 150.00 | 600.00 | 40.00 | 160.00 |
| 0005 | 202-03-38000 | Relocation of Sign relocation of signs in the median as directed by project engineer | 7 | EACH | 150.00 | 1,050.00 | 200.00 | 1,400.00 | 140.00 | 980.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 15 | CUYD | 55.00 | 825.00 | 50.00 | 750.00 | 30.00 | 450.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 295.7 | TON | 115.00 | 34,005.50 | 170.00 | 50,269.00 | 175.00 | 51,747.50 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,688 | SQYD | 4.50 | 12,096.00 | 6.95 | 18,681.60 | 2.00 | 5,376.00 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | 149.33 | CUYD | -10.00 | -1,493.30 | 0.00 | 0.00 | 0.00 | 0.00 |
| 0010 | 510-02-00100 | Pavement Widening | 2,020 | SQYD | 54.00 | 109,080.00 | 100.00 | 202,000.00 | 90.00 | 181,800.00 |
| 0011 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 1,540 | SQYD | 33.00 | 50,820.00 | 35.00 | 53,900.00 | 90.00 | 138,600.00 |
| 0012 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,219 | LNFT | 32.00 | 71,008.00 | 33.50 | 74,336.50 | 40.00 | 88,760.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 60,000.00 | 60,000.00 | 6,000.00 | 6,000.00 | 15,000.00 | 15,000.00 |
| 0014 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,760 | LNFT | 0.05 | 188.00 | 0.35 | 1,316.00 | 0.01 | 37.60 |
| 0015 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 746 | LNFT | 0.15 | 111.90 | 1.05 | 783.30 | 0.03 | 22.38 |
| 0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.7 | MILE | 150.00 | 105.00 | 610.00 | 427.00 | 10.00 | 7.00 |
| 0017 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 8 | EACH | 10.00 | 80.00 | 52.00 | 416.00 | 5.00 | 40.00 |
| 0018 | 717-01-00100 | Seeding | 5.1 | LB | 15.00 | 76.50 | 10.50 | 53.55 | 100.00 | 510.00 |
| 0019 | 718-01-00100 | Fertilizer | 170 | LB | 1.00 | 170.00 | 2.10 | 357.00 | 3.00 | 510.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 45,000.00 | 45,000.00 | 49,663.85 | 49,663.85 | 55,000.00 | 55,000.00 |
| 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 601 | EACH | 8.00 | 4,808.00 | 4.55 | 2,734.55 | 5.50 | 3,305.50 |
| 0022 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,880 | LNFT | 1.50 | 2,820.00 | 1.05 | 1,974.00 | 1.50 | 2,820.00 |
| 0023 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 373 | LNFT | 5.50 | 2,051.50 | 4.05 | 1,510.65 | 5.50 | 2,051.50 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.35 | MILE | 3,100.00 | 1,085.00 | 3,600.00 | 1,260.00 | 3,000.00 | 1,050.00 |
| 0025 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 8 | EACH | 250.00 | 2,000.00 | 185.00 | 1,480.00 | 230.00 | 1,840.00 |
| 0026 | 737-04-00001 | Painted Curbs and Islands | 216 | SQYD | 15.00 | 3,240.00 | 3.65 | 788.40 | 5.50 | 1,188.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 11,000.00 | 11,000.00 | 5,000.00 | 5,000.00 |
| 0028 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 22,800 | INLF | 0.75 | 17,100.00 | 0.85 | 19,380.00 | 0.25 | 5,700.00 |
| CONTRACTOR TOTAL | 467,672.10 | 535,686.40 | 589,075.48 | |||||||