Bid Tabulations
Letting of
08/25/2010
LA DOTD Headquarters
| Lead Project: 283-30-0026-R1 | |
| Parish: Jefferson | |
| Routes: LA 49 | |
| Description: WILLIAMS BLVD. (U PASS I-10 - JCT. US 61) | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $1,700,163.07 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,981,191.90 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $3,576,617.95 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 500 | LNFT | 8.00 | 4,000.00 | 30.00 | 15,000.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 12.00 | 2,400.00 | 50.00 | 10,000.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 10,881.8 | TON | 80.00 | 870,544.00 | 120.00 | 1,305,816.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 88,113 | SQYD | 2.00 | 176,226.00 | 3.50 | 308,395.50 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,933 | CUYD | 10.00 | -39,330.00 | 2.00 | -7,866.00 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 200 | SQYD | 50.00 | 10,000.00 | 90.00 | 18,000.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 4,500 | SQYD | 60.00 | 270,000.00 | 130.00 | 585,000.00 |
| 0008 | 510-03-00100 | Pavement Joint Repair | 100 | TON | 175.00 | 17,500.00 | 600.00 | 60,000.00 |
| 0009 | 706-01-00100 | Concrete Walk (4" Thick) | 45 | SQYD | 58.00 | 2,610.00 | 120.00 | 5,400.00 |
| 0010 | 706-04-00100 | Handicapped Curb Ramps | 39 | EACH | 1,600.00 | 62,400.00 | 4,000.00 | 156,000.00 |
| 0011 | 707-03-00100 | Combination Concrete Curb and Gutter | 500 | LNFT | 28.50 | 14,250.00 | 130.00 | 65,000.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 200,000.00 | 200,000.00 | 450,000.00 | 450,000.00 |
| 0013 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 5,000 | LNFT | 0.20 | 1,000.00 | 0.30 | 1,500.00 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 606 | LNFT | 0.75 | 454.50 | 0.80 | 484.80 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 12.394 | MILE | 200.00 | 2,478.80 | 800.00 | 9,915.20 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 12.394 | MILE | 200.00 | 2,478.80 | 500.00 | 6,197.00 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 15.2 | MILE | 250.00 | 3,800.00 | 600.00 | 9,120.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 190,000.00 | 190,000.00 | 330,000.00 | 330,000.00 |
| 0019 | 731-02-00100 | Reflectorized Raised Pavement Markers | 700 | EACH | 5.25 | 3,675.00 | 6.00 | 4,200.00 |
| 0020 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 2,500 | LNFT | 1.50 | 3,750.00 | 2.00 | 5,000.00 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 606 | LNFT | 4.75 | 2,878.50 | 5.00 | 3,030.00 |
| 0022 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.6 | MILE | 2,500.00 | 19,000.00 | 2,500.00 | 19,000.00 |
| 0023 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.197 | MILE | 900.00 | 5,577.30 | 850.00 | 5,267.45 |
| 0024 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 52 | EACH | 225.00 | 11,700.00 | 300.00 | 15,600.00 |
| 0025 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 10 | EACH | 225.00 | 2,250.00 | 300.00 | 3,000.00 |
| 0026 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 5 | EACH | 250.00 | 1,250.00 | 300.00 | 1,500.00 |
| 0027 | 732-04-12020 | Plastic Pavement Legends and Symbols (LANE ENDS) | 4 | EACH | 400.00 | 1,600.00 | 400.00 | 1,600.00 |
| 0028 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 26 | EACH | 230.00 | 5,980.00 | 300.00 | 7,800.00 |
| 0029 | 736-09-00100 | Loop Detector | 600 | LNFT | 13.00 | 7,800.00 | 20.00 | 12,000.00 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 20,000.00 | 20,000.00 |
| 0031 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 12,000 | LNFT | 1.20 | 14,400.00 | 2.00 | 24,000.00 |
| 0032 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 9,600 | LNFT | 1.25 | 12,000.00 | 2.00 | 19,200.00 |
| 0033 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 21,600 | LNFT | 0.95 | 20,520.00 | 0.60 | 12,960.00 |
| 0034 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 46,998 | INLF | 0.50 | 23,499.00 | 1.00 | 46,998.00 |
| 0035 | NS-702-00001 | Cleaning Existing Catch Basin | 55 | EACH | 500.00 | 27,500.00 | 500.00 | 27,500.00 |
| 0036 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 7,500.00 | 15,000.00 | 10,000.00 | 20,000.00 |
| CONTRACTOR TOTAL | 1,981,191.90 | 3,576,617.95 | ||||||