10/27/2010
LA DOTD Headquarters
| Lead Project: 283-08-0198 | |
| Parish: Jefferson, Orleans | |
| Routes: US 90 | |
| Description: FRONTAGE ROAD MINOR OVERLAY AND RAMP REPAIR | |
| Type Const: COLD PLANNING, ASPHALT OVERLAY, RAMP REPAIR AND RELATED WORK | |
| Estimated Construction Cost: $563,523.55 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $578,586.10 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $586,471.56 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 53 | LNFT | 41.00 | 2,173.00 | 38.00 | 2,014.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 688 | LNFT | 5.25 | 3,612.00 | 15.00 | 10,320.00 |
| 0003 | 202-02-26300 | Removal of Median / Island | 70 | SQYD | 19.00 | 1,330.00 | 36.00 | 2,520.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 1,621.4 | TON | 105.00 | 170,247.00 | 120.00 | 194,568.00 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 58.7 | TON | 180.00 | 10,566.00 | 120.00 | 7,044.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement 2" Avg. Cold Planing | 15,008 | SQYD | 4.00 | 60,032.00 | 3.00 | 45,024.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement 8" Avg. Cold Planing | 1,350 | SQYD | 12.00 | 16,200.00 | 3.00 | 4,050.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,133.8 | CUYD | 10.00 | -11,338.00 | 10.00 | -11,338.00 |
| 0009 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 1,350 | SQYD | 72.00 | 97,200.00 | 80.00 | 108,000.00 |
| 0010 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 400.00 | 800.00 | 1,200.00 | 2,400.00 |
| 0011 | 702-04-00200 | Adjusting Catch Basins | 15 | EACH | 1,600.00 | 24,000.00 | 750.00 | 11,250.00 |
| 0012 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 70 | SQYD | 60.00 | 4,200.00 | 75.00 | 5,250.00 |
| 0013 | 706-04-00100 | Handicapped Curb Ramps NEAR STA. 100+00 | 2 | EACH | 2,400.00 | 4,800.00 | 3,300.00 | 6,600.00 |
| 0014 | 706-04-00100 | Handicapped Curb Ramps NEAR STA. 119+50 | 1 | EACH | 2,400.00 | 2,400.00 | 3,300.00 | 3,300.00 |
| 0015 | 707-01-00200 | Concrete Curb (Barrier) | 688 | LNFT | 20.00 | 13,760.00 | 25.00 | 17,200.00 |
| 0016 | 707-03-00100 | Combination Concrete Curb and Gutter | 53 | LNFT | 38.00 | 2,014.00 | 110.00 | 5,830.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 56,000.00 | 56,000.00 | 38,000.00 | 38,000.00 |
| 0018 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 4,470 | LNFT | 0.35 | 1,564.50 | 0.30 | 1,341.00 |
| 0019 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 248 | LNFT | 0.85 | 210.80 | 0.75 | 186.00 |
| 0020 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 126 | LNFT | 1.25 | 157.50 | 1.00 | 126.00 |
| 0021 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.28 | MILE | 300.00 | 684.00 | 650.00 | 1,482.00 |
| 0022 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.28 | MILE | 750.00 | 1,710.00 | 650.00 | 1,482.00 |
| 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 5.826 | MILE | 800.00 | 4,660.80 | 785.00 | 4,573.41 |
| 0024 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 10 | EACH | 76.00 | 760.00 | 75.00 | 750.00 |
| 0025 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 8 | EACH | 76.00 | 608.00 | 75.00 | 600.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 56,000.00 | 56,000.00 | 58,000.00 | 58,000.00 |
| 0027 | 731-02-00100 | Reflectorized Raised Pavement Markers | 567 | EACH | 5.00 | 2,835.00 | 5.00 | 2,835.00 |
| 0028 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,235 | LNFT | 1.10 | 2,458.50 | 1.25 | 2,793.75 |
| 0029 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 124 | LNFT | 3.00 | 372.00 | 3.00 | 372.00 |
| 0030 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 63 | LNFT | 6.00 | 378.00 | 5.00 | 315.00 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.216 | MILE | 3,000.00 | 9,648.00 | 2,400.00 | 7,718.40 |
| 0032 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.14 | MILE | 1,200.00 | 1,368.00 | 1,000.00 | 1,140.00 |
| 0033 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 6 | EACH | 215.00 | 1,290.00 | 175.00 | 1,050.00 |
| 0034 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 215.00 | 215.00 | 175.00 | 175.00 |
| 0035 | 732-05-00100 | Removal of Existing Markings | 0.06 | MILE | 22,000.00 | 1,320.00 | 20,000.00 | 1,200.00 |
| 0036 | 736-09-00100 | Loop Detector | 400 | LNFT | 16.00 | 6,400.00 | 13.00 | 5,200.00 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 32,000.00 | 32,000.00 |
| 0038 | NS-702-00001 | Cleaning Existing Catch Basin | 37 | EACH | 350.00 | 12,950.00 | 300.00 | 11,100.00 |
| CONTRACTOR TOTAL | 578,586.10 | 586,471.56 | ||||||