Bid Tabulations
Letting of
02/10/2010
LA DOTD Headquarters
| Lead Project: 282-02-0048 | |
| Parish: St. Charles | |
| Routes: LA 48 | |
| Description: TURN LANE IMPROVEMENTS NEAR SCHEXNAYDRE LANE | |
| Type Const: PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE, STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $132,079.96 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $193,622.40 |
| 2 | 06276 | Barriere Construction Co., LLC | $203,143.37 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - Barriere Construction Co., LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 20.00 | 200.00 | 45.00 | 450.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 354.9 | TON | 115.00 | 40,813.50 | 105.00 | 37,264.50 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 35 | TON | 115.00 | 4,025.00 | 140.00 | 4,900.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 3,228 | SQYD | 2.00 | 6,456.00 | 5.00 | 16,140.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | 179.34 | CUYD | 0.00 | 0.00 | -30.00 | -5,380.20 |
| 0006 | 510-02-00100 | Pavement Widening | 1,272.4 | SQYD | 80.00 | 101,792.00 | 72.00 | 91,612.80 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 12,000.00 | 12,000.00 | 25,000.00 | 25,000.00 |
| 0008 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 75 | LNFT | 0.30 | 22.50 | 0.10 | 7.50 |
| 0009 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 212 | LNFT | 1.00 | 212.00 | 1.15 | 243.80 |
| 0010 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.163 | MILE | 500.00 | 81.50 | 405.00 | 66.02 |
| 0011 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1 | MILE | 20.00 | 20.00 | 500.00 | 500.00 |
| 0012 | 717-01-00100 | Seeding | 6 | LB | 30.00 | 180.00 | 100.00 | 600.00 |
| 0013 | 718-01-00100 | Fertilizer | 200 | LB | 1.50 | 300.00 | 5.00 | 1,000.00 |
| 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 19,000.00 | 19,000.00 | 20,000.00 | 20,000.00 |
| 0015 | 731-02-00100 | Reflectorized Raised Pavement Markers | 243 | EACH | 5.50 | 1,336.50 | 6.00 | 1,458.00 |
| 0016 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 75 | LNFT | 1.00 | 75.00 | 1.25 | 93.75 |
| 0017 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 212 | LNFT | 4.00 | 848.00 | 4.50 | 954.00 |
| 0018 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.82 | MILE | 2,900.00 | 2,378.00 | 3,500.00 | 2,870.00 |
| 0019 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 200.00 | 400.00 | 238.00 | 476.00 |
| 0020 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 210.00 | 210.00 | 251.00 | 251.00 |
| 0021 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 4,000.00 | 4,000.00 |
| 0022 | NS-200-00040 | Geotextile Fabric | 1,272.4 | SQYD | 1.00 | 1,272.40 | 0.50 | 636.20 |
| CONTRACTOR TOTAL | 193,622.40 | 203,143.37 | ||||||