Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 262-07-0026 | |
| Parish: Tangipahoa | |
| Routes: | |
| Description: END OF CONCRETE SECTION ON LA 16 - JCT. U.S. 51 | |
| Type Const: COLD PLANING ASPHALTIC PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $762,611.69 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $520,077.92 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $694,539.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 502-01-00100 | Superpave Asphaltic Concrete | 4,621 | TON | 72.00 | 332,712.00 | 76.25 | 352,351.25 |
| 0002 | 509-01-00100 | Cold Planing Asphaltic Pavement | 42,011 | SQYD | 1.10 | 46,212.10 | 1.15 | 48,312.65 |
| 0003 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,750 | CUYD | 15.00 | -26,250.00 | 0.10 | -175.00 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,500 | SQYD | 30.00 | 75,000.00 | 66.00 | 165,000.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 27,000.00 | 27,000.00 | 15,000.00 | 15,000.00 |
| 0006 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 960 | LNFT | 0.25 | 240.00 | 0.25 | 240.00 |
| 0007 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,132 | LNFT | 0.25 | 283.00 | 1.00 | 1,132.00 |
| 0008 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.24 | MILE | 125.00 | 655.00 | 160.00 | 838.40 |
| 0009 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.04 | MILE | 1.00 | 9.04 | 300.00 | 2,712.00 |
| 0010 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 10.48 | MILE | 1.00 | 10.48 | 680.00 | 7,126.40 |
| 0011 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 36 | EACH | 1.00 | 36.00 | 55.00 | 1,980.00 |
| 0012 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 12 | EACH | 1.00 | 12.00 | 55.00 | 660.00 |
| 0013 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 100.00 | 200.00 | 80.00 | 160.00 |
| 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 24,000.00 | 24,000.00 | 63,000.00 | 63,000.00 |
| 0015 | 731-02-00100 | Reflectorized Raised Pavement Markers | 696 | EACH | 5.30 | 3,688.80 | 5.00 | 3,480.00 |
| 0016 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 480 | LNFT | 1.40 | 672.00 | 1.00 | 480.00 |
| 0017 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 566 | LNFT | 4.75 | 2,688.50 | 3.50 | 1,981.00 |
| 0018 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.24 | MILE | 2,600.00 | 13,624.00 | 2,800.00 | 14,672.00 |
| 0019 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.52 | MILE | 875.00 | 3,955.00 | 700.00 | 3,164.00 |
| 0020 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 220.00 | 440.00 | 200.00 | 400.00 |
| 0021 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 4 | EACH | 270.00 | 1,080.00 | 200.00 | 800.00 |
| 0022 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 220.00 | 2,640.00 | 200.00 | 2,400.00 |
| 0023 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 410.00 | 2,460.00 | 200.00 | 1,200.00 |
| 0024 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 410.00 | 410.00 | 375.00 | 375.00 |
| 0025 | 732-04-19020 | Plastic Pavement Legends and Symbols (SCHOOL ZONE) | 2 | EACH | 400.00 | 800.00 | 375.00 | 750.00 |
| 0026 | 736-09-00100 | Loop Detector | 300 | LNFT | 15.00 | 4,500.00 | 13.00 | 3,900.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 2,600.00 | 2,600.00 |
| CONTRACTOR TOTAL | 520,077.92 | 694,539.70 | ||||||