Bid Tabulations
Letting of
01/26/2011
LA DOTD Headquarters
| Lead Project: 254-05-0028 | |
| Parish: Livingston, St. Helena | |
| Routes: LA 63, LA 37, LA 449 | |
| Description: East Feliciana Parish Line - Jct. La 448 | |
| Type Const: ASPHALTIC SURFACE TREATMENT AND RELATED WORK | |
| Estimated Construction Cost: $354,923.84 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 01552 | W. R. Core, LLC. | $285,808.55 |
| 2 | 14422 | T. L. Wallace Construction, Inc. | $293,920.93 |
| 3 | 35378 | P.R. Parker Company Inc | $320,997.99 |
| 4 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $389,996.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W. R. Core, LLC. |
- 2 - T. L. Wallace Construction, Inc. |
- 3 - P.R. Parker Company Inc |
- 4 - F.G. Sullivan, Jr. Contractor LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 45,706 | GAL | 3.15 | 143,973.90 | 3.10 | 141,688.60 | 3.04 | 138,946.24 | 3.50 | 159,971.00 |
| 0002 | 507-02-00300 | Aggregate (S3) Crushed Stone Only | 147,442 | SQYD | 0.60 | 88,465.20 | 0.64 | 94,362.88 | 0.65 | 95,837.30 | 1.10 | 162,186.20 |
| 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,900.00 | 6,900.00 | 9,100.00 | 9,100.00 | 15,100.00 | 15,100.00 | 12,400.00 | 12,400.00 |
| 0004 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 2,690 | EACH | 1.50 | 4,035.00 | 1.50 | 4,035.00 | 2.00 | 5,380.00 | 2.00 | 5,380.00 |
| 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 9,000.00 | 9,000.00 | 32,000.00 | 32,000.00 | 10,200.00 | 10,200.00 |
| 0006 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,348 | EACH | 4.50 | 6,066.00 | 4.50 | 6,066.00 | 4.50 | 6,066.00 | 5.50 | 7,414.00 |
| 0007 | 737-01-00100 | Painted Traffic Striping (Solid Line) (4" Width) | 29.27 | MILE | 700.00 | 20,489.00 | 700.00 | 20,489.00 | 700.00 | 20,489.00 | 900.00 | 26,343.00 |
| 0008 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 7.563 | MILE | 350.00 | 2,647.05 | 350.00 | 2,647.05 | 350.00 | 2,647.05 | 500.00 | 3,781.50 |
| 0009 | 737-03-00500 | Painted Traffic Striping (Solid Line) (24" Width) | 36 | LNFT | 0.90 | 32.40 | 0.90 | 32.40 | 0.90 | 32.40 | 1.00 | 36.00 |
| 0010 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,200.00 | 3,200.00 | 6,500.00 | 6,500.00 | 4,500.00 | 4,500.00 | 2,285.00 | 2,285.00 |
| CONTRACTOR TOTAL | 285,808.55 | 293,920.93 | 320,997.99 | 389,996.70 | ||||||||