Bid Tabulations
Letting of
05/25/2011
LA DOTD Headquarters
| Lead Project: 250-01-0046 | |
| Parish: East Baton Rouge | |
| Routes: LA 19 | |
| Description: LA 64 - EAST FELICIANA PARISH LINE | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK | |
| Estimated Construction Cost: $2,594,137.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $2,778,368.70 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $2,825,137.80 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $2,940,279.08 |
| 4 | 55564 | Coastal Industries Llc | $3,148,307.33 |
| 5 | 06276 | Barriere Construction Co., LLC. | $3,352,000.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F.G. Sullivan, Jr. Contractor LLC |
- 2 - Barber Bros. Contracting Co., L.L.C |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Coastal Industries Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 2,774 | LNFT | 3.00 | 8,322.00 | 6.50 | 18,031.00 | 7.00 | 19,418.00 | 4.00 | 11,096.00 |
| 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 1,000.00 | 1,000.00 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 | 30,000.00 | 30,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,540 | CUYD | 1.00 | 1,540.00 | 15.00 | 23,100.00 | 13.00 | 20,020.00 | 5.00 | 7,700.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 112 | EACH | 12.00 | 1,344.00 | 15.00 | 1,680.00 | 14.00 | 1,568.00 | 11.00 | 1,232.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 1,125 | LNFT | 1.75 | 1,968.75 | 1.50 | 1,687.50 | 2.00 | 2,250.00 | 1.60 | 1,800.00 |
| 0006 | 302-02-02080 | Class II Base Course (6" Thick) (Stone) | 5,700 | SQYD | 20.00 | 114,000.00 | 15.00 | 85,500.00 | 18.50 | 105,450.00 | 22.50 | 128,250.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 16,810.1 | TON | 85.00 | 1,428,858.50 | 75.00 | 1,260,757.50 | 77.00 | 1,294,377.70 | 84.00 | 1,412,048.40 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,437.8 | TON | 105.00 | 150,969.00 | 100.00 | 143,780.00 | 190.00 | 273,182.00 | 1.00 | 1,437.80 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 64,330 | SQYD | 2.00 | 128,660.00 | 1.80 | 115,794.00 | 1.50 | 96,495.00 | 3.50 | 225,155.00 |
| 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,787 | CUYD | 0.00 | 0.00 | 0.00 | 0.00 | 1.00 | -1,787.00 | 0.01 | -17.87 |
| 0011 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 950 | SQYD | 20.00 | 19,000.00 | 45.00 | 42,750.00 | 64.00 | 60,800.00 | 45.00 | 42,750.00 |
| 0012 | 510-03-00100 | Pavement Joint Repair | 168.7 | TON | 200.00 | 33,740.00 | 120.00 | 20,244.00 | 185.00 | 31,209.50 | 225.00 | 37,957.50 |
| 0013 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,109 | LNFT | 1.65 | 1,829.85 | 1.50 | 1,663.50 | 1.50 | 1,663.50 | 1.65 | 1,829.85 |
| 0014 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 1,638 | LNFT | 1.65 | 2,702.70 | 1.50 | 2,457.00 | 1.50 | 2,457.00 | 1.85 | 3,030.30 |
| 0015 | 602-03-00100 | Cleaning and Sealing Random cracks | 100 | LNFT | 2.20 | 220.00 | 8.00 | 800.00 | 3.90 | 390.00 | 5.00 | 500.00 |
| 0016 | 602-05-03160 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) | 2,065 | SQYD | 210.00 | 433,650.00 | 200.00 | 413,000.00 | 205.00 | 423,325.00 | 100.00 | 206,500.00 |
| 0017 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 987.6 | LNFT | 31.50 | 31,109.40 | 36.00 | 35,553.60 | 33.00 | 32,590.80 | 40.00 | 39,504.00 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 1,756.5 | LNFT | 19.00 | 33,373.50 | 22.00 | 38,643.00 | 20.00 | 35,130.00 | 20.00 | 35,130.00 |
| 0019 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 54.00 | 16,200.00 | 65.00 | 19,500.00 | 55.00 | 16,500.00 | 65.00 | 19,500.00 |
| 0020 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 14 | EACH | 2,400.00 | 33,600.00 | 2,800.00 | 39,200.00 | 2,500.00 | 35,000.00 | 2,150.00 | 30,100.00 |
| 0021 | 707-04-00100 | Asphaltic Curb | 120 | LNFT | 50.00 | 6,000.00 | 20.00 | 2,400.00 | 18.00 | 2,160.00 | 75.00 | 9,000.00 |
| 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 60,000.00 | 60,000.00 | 80,000.00 | 80,000.00 | 310,000.00 | 310,000.00 |
| 0023 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 108 | LNFT | 0.10 | 10.80 | 0.25 | 27.00 | 1.00 | 108.00 | 0.25 | 27.00 |
| 0024 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 116 | LNFT | 0.35 | 40.60 | 0.85 | 98.60 | 1.00 | 116.00 | 0.75 | 87.00 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.16 | MILE | 500.00 | 2,080.00 | 460.00 | 1,913.60 | 330.00 | 1,372.80 | 375.00 | 1,560.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.17 | MILE | 10.00 | 91.70 | 500.00 | 4,585.00 | 600.00 | 5,502.00 | 550.00 | 5,043.50 |
| 0027 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 8 | EACH | 10.00 | 80.00 | 55.00 | 440.00 | 50.00 | 400.00 | 45.00 | 360.00 |
| 0028 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 10.00 | 40.00 | 55.00 | 220.00 | 50.00 | 200.00 | 45.00 | 180.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 54,000.00 | 54,000.00 | 250,000.00 | 250,000.00 | 210,000.00 | 210,000.00 | 300,000.00 | 300,000.00 |
| 0030 | 729-16-00200 | Object Marker Assembly (Type 2) | 14 | EACH | 70.00 | 980.00 | 80.00 | 1,120.00 | 75.00 | 1,050.00 | 45.00 | 630.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 75.00 | 1,200.00 | 85.00 | 1,360.00 | 82.00 | 1,312.00 | 75.00 | 1,200.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 696 | EACH | 5.25 | 3,654.00 | 6.00 | 4,176.00 | 5.80 | 4,036.80 | 5.25 | 3,654.00 |
| 0033 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 108 | LNFT | 1.35 | 145.80 | 2.00 | 216.00 | 1.50 | 162.00 | 1.35 | 145.80 |
| 0034 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 68 | LNFT | 4.50 | 306.00 | 6.00 | 408.00 | 5.00 | 340.00 | 4.50 | 306.00 |
| 0035 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 48 | LNFT | 5.00 | 240.00 | 6.00 | 288.00 | 5.50 | 264.00 | 5.00 | 240.00 |
| 0036 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 9.17 | MILE | 2,650.00 | 24,300.50 | 3,000.00 | 27,510.00 | 2,800.00 | 25,676.00 | 2,650.00 | 24,300.50 |
| 0037 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.078 | MILE | 850.00 | 3,466.30 | 1,000.00 | 4,078.00 | 935.00 | 3,812.93 | 850.00 | 3,466.30 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 7 | EACH | 215.00 | 1,505.00 | 250.00 | 1,750.00 | 240.00 | 1,680.00 | 215.00 | 1,505.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 215.00 | 215.00 | 250.00 | 250.00 | 240.00 | 240.00 | 215.00 | 215.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 225.00 | 900.00 | 260.00 | 1,040.00 | 250.00 | 1,000.00 | 225.00 | 900.00 |
| 0041 | 735-01-00100 | Mailboxes | 53 | EACH | 1.00 | 53.00 | 2.00 | 106.00 | 10.00 | 530.00 | 1.00 | 53.00 |
| 0042 | 735-02-00100 | Mailbox Supports (Single) | 33 | EACH | 120.00 | 3,960.00 | 120.00 | 3,960.00 | 125.00 | 4,125.00 | 105.00 | 3,465.00 |
| 0043 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 130.00 | 650.00 | 200.00 | 1,000.00 | 135.00 | 675.00 | 170.00 | 850.00 |
| 0044 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 250.00 | 500.00 | 350.00 | 700.00 | 275.00 | 550.00 | 350.00 | 700.00 |
| 0045 | 739-01-00100 | Hydro-Seeding | 3.59 | ACRE | 1,100.00 | 3,949.00 | 1,500.00 | 5,385.00 | 1,200.00 | 4,308.00 | 1,100.00 | 3,949.00 |
| 0046 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | 14,000.00 | 14,000.00 | 185,000.00 | 185,000.00 |
| 0047 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 9,452 | LNFT | 1.20 | 11,342.40 | 1.50 | 14,178.00 | 1.45 | 13,705.40 | 1.25 | 11,815.00 |
| 0048 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 25,747 | LNFT | 1.20 | 30,896.40 | 1.50 | 38,620.50 | 1.45 | 37,333.15 | 1.25 | 32,183.75 |
| 0049 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 8,550 | LNFT | 0.45 | 3,847.50 | 1.30 | 11,115.00 | 1.25 | 10,687.50 | 0.45 | 3,847.50 |
| 0050 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 125,100 | INLF | 0.47 | 58,797.00 | 0.60 | 75,060.00 | 0.15 | 18,765.00 | 0.01 | 1,251.00 |
| 0051 | NS-700-00240 | Special Guard Rail Anchor Section | 6 | EACH | 1,145.00 | 6,870.00 | 1,500.00 | 9,000.00 | 1,300.00 | 7,800.00 | 625.00 | 3,750.00 |
| 0052 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 8.32 | MILE | 500.00 | 4,160.00 | 600.00 | 4,992.00 | 400.00 | 3,328.00 | 375.00 | 3,120.00 |
| CONTRACTOR TOTAL | 2,778,368.70 | 2,825,137.80 | 2,940,279.08 | 3,148,307.33 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Barriere Construction Co., LLC. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 2,774 | LNFT | 5.50 | 15,257.00 |
| 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 50,025.15 | 50,025.15 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,540 | CUYD | 15.00 | 23,100.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 112 | EACH | 13.00 | 1,456.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 1,125 | LNFT | 2.00 | 2,250.00 |
| 0006 | 302-02-02080 | Class II Base Course (6" Thick) (Stone) | 5,700 | SQYD | 22.00 | 125,400.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 16,810.1 | TON | 88.00 | 1,479,288.80 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,437.8 | TON | 88.00 | 126,526.40 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 64,330 | SQYD | 4.00 | 257,320.00 |
| 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,787 | CUYD | 5.00 | -8,935.00 |
| 0011 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 950 | SQYD | 40.00 | 38,000.00 |
| 0012 | 510-03-00100 | Pavement Joint Repair | 168.7 | TON | 150.00 | 25,305.00 |
| 0013 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,109 | LNFT | 1.65 | 1,829.85 |
| 0014 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 1,638 | LNFT | 1.65 | 2,702.70 |
| 0015 | 602-03-00100 | Cleaning and Sealing Random cracks | 100 | LNFT | 5.00 | 500.00 |
| 0016 | 602-05-03160 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) | 2,065 | SQYD | 170.00 | 351,050.00 |
| 0017 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 987.6 | LNFT | 33.00 | 32,590.80 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 1,756.5 | LNFT | 22.00 | 38,643.00 |
| 0019 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 70.00 | 21,000.00 |
| 0020 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 14 | EACH | 2,500.00 | 35,000.00 |
| 0021 | 707-04-00100 | Asphaltic Curb | 120 | LNFT | 65.00 | 7,800.00 |
| 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 |
| 0023 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 108 | LNFT | 1.00 | 108.00 |
| 0024 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 116 | LNFT | 1.00 | 116.00 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.16 | MILE | 500.00 | 2,080.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.17 | MILE | 1,200.00 | 11,004.00 |
| 0027 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 8 | EACH | 50.00 | 400.00 |
| 0028 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 50.00 | 200.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 320,000.00 | 320,000.00 |
| 0030 | 729-16-00200 | Object Marker Assembly (Type 2) | 14 | EACH | 74.00 | 1,036.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 90.00 | 1,440.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 696 | EACH | 6.00 | 4,176.00 |
| 0033 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 108 | LNFT | 1.50 | 162.00 |
| 0034 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 68 | LNFT | 5.00 | 340.00 |
| 0035 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 48 | LNFT | 6.00 | 288.00 |
| 0036 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 9.17 | MILE | 3,000.00 | 27,510.00 |
| 0037 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.078 | MILE | 1,000.00 | 4,078.00 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 7 | EACH | 250.00 | 1,750.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 250.00 | 250.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 250.00 | 1,000.00 |
| 0041 | 735-01-00100 | Mailboxes | 53 | EACH | 1.00 | 53.00 |
| 0042 | 735-02-00100 | Mailbox Supports (Single) | 33 | EACH | 120.00 | 3,960.00 |
| 0043 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 190.00 | 950.00 |
| 0044 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 400.00 | 800.00 |
| 0045 | 739-01-00100 | Hydro-Seeding | 3.59 | ACRE | 1,200.00 | 4,308.00 |
| 0046 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 |
| 0047 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 9,452 | LNFT | 1.60 | 15,123.20 |
| 0048 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 25,747 | LNFT | 1.30 | 33,471.10 |
| 0049 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 8,550 | LNFT | 1.10 | 9,405.00 |
| 0050 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 125,100 | INLF | 1.10 | 137,610.00 |
| 0051 | NS-700-00240 | Special Guard Rail Anchor Section | 6 | EACH | 1,200.00 | 7,200.00 |
| 0052 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 8.32 | MILE | 850.00 | 7,072.00 |
| CONTRACTOR TOTAL | 3,352,000.00 | |||||