Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 247-02-0035-R1 | |
| Parish: Terrebonne | |
| Routes: LA 56 | |
| Description: LA 56 (N. END OF BOUDREAUX CANAL BRIDGE - JCT LA 58), etc. | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK | |
| Estimated Construction Cost: $1,514,319.53 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,327,345.40 |
| 2 | 06487 | Huey Stockstill, Inc. | $1,449,091.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Huey Stockstill, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 830 | CUYD | 5.00 | 4,150.00 | 5.00 | 4,150.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 10,153.4 | TON | 72.00 | 731,044.80 | 75.00 | 761,505.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,500 | TON | 72.00 | 108,000.00 | 75.00 | 112,500.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 92,686 | SQYD | 0.50 | 46,343.00 | 1.20 | 111,223.20 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,862 | CUYD | 5.00 | -19,310.00 | 20.00 | -77,240.00 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 144 | SQYD | 40.00 | 5,760.00 | 85.00 | 12,240.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 310 | SQYD | 80.00 | 24,800.00 | 135.00 | 41,850.00 |
| 0008 | 510-02-00100 | Pavement Widening | 1,086 | SQYD | 54.00 | 58,644.00 | 82.00 | 89,052.00 |
| 0009 | 701-14-00100 | Cleaning Existing Pipes | 1,650 | LNFT | 8.50 | 14,025.00 | 13.00 | 21,450.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 130,000.00 | 130,000.00 |
| 0011 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 75 | LNFT | 0.01 | 0.75 | 0.30 | 22.50 |
| 0012 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 156 | LNFT | 0.01 | 1.56 | 1.00 | 156.00 |
| 0013 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.14 | MILE | 300.00 | 2,742.00 | 300.00 | 2,742.00 |
| 0014 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.84 | MILE | 0.01 | 0.10 | 10.00 | 98.40 |
| 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 34 | MILE | 0.01 | 0.34 | 10.00 | 340.00 |
| 0016 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 1 | EACH | 45.00 | 45.00 | 10.00 | 10.00 |
| 0017 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 1 | EACH | 45.00 | 45.00 | 10.00 | 10.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 130,000.00 | 130,000.00 | 145,000.00 | 145,000.00 |
| 0019 | 731-02-00100 | Reflectorized Raised Pavement Markers | 813 | EACH | 5.25 | 4,268.25 | 5.00 | 4,065.00 |
| 0020 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 0.3 | MILE | 2,000.00 | 600.00 | 3,000.00 | 900.00 |
| 0021 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.85 | MILE | 2,500.00 | 42,125.00 | 3,000.00 | 50,550.00 |
| 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.94 | MILE | 850.00 | 4,199.00 | 900.00 | 4,446.00 |
| 0023 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 215.00 | 215.00 | 225.00 | 225.00 |
| 0024 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 225.00 | 225.00 | 225.00 | 225.00 |
| 0025 | 735-01-00100 | Mailboxes | 282 | EACH | 1.00 | 282.00 | 1.00 | 282.00 |
| 0026 | 735-02-00100 | Mailbox Supports (Single) | 228 | EACH | 100.00 | 22,800.00 | 105.00 | 23,940.00 |
| 0027 | 735-03-00100 | Mailbox Supports (Double) | 18 | EACH | 125.00 | 2,250.00 | 170.00 | 3,060.00 |
| 0028 | 735-04-00100 | Mailbox Supports (Multiple) | 6 | EACH | 200.00 | 1,200.00 | 400.00 | 2,400.00 |
| 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 1,000.00 | 1,000.00 |
| 0030 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 28,896 | INLF | 0.10 | 2,889.60 | 0.10 | 2,889.60 |
| CONTRACTOR TOTAL | 1,327,345.40 | 1,449,091.70 | ||||||