Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 219-02-0024 | |
| Parish: Iberville | |
| Routes: LA 77 | |
| Description: INDIAN VILLAGE - LA 386 | |
| Type Const: IN-PLACE CEMENT TREATED BASE COURSE, COLD PLANING ASPHALTIC PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $3,928,017.21 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00481 | Coastal Bridge Co., L.L.C. | $3,642,955.96 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $3,997,166.45 |
| 3 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $4,225,632.25 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Coastal Bridge Co., L.L.C. |
- 2 - Barber Bros. Contracting Co., L.L.C |
- 3 - F.G. Sullivan, Jr. Contractor LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 71.6 | SQYD | 20.00 | 1,432.00 | 20.00 | 1,432.00 | 10.00 | 716.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 288 | LNFT | 10.00 | 2,880.00 | 12.00 | 3,456.00 | 3.00 | 864.00 |
| 0003 | 202-02-32120 | Removal of Pipe (Side Drain) STATION 54+22 | 3 | LNFT | 100.00 | 300.00 | 150.00 | 450.00 | 3.00 | 9.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,920 | CUYD | 1.00 | 3,920.00 | 15.00 | 58,800.00 | 10.00 | 39,200.00 |
| 0005 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 4,602 | CUYD | 1.00 | 4,602.00 | 15.00 | 69,030.00 | 10.00 | 46,020.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 200 | EACH | 1.00 | 200.00 | 85.00 | 17,000.00 | 90.00 | 18,000.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 38,531 | LNFT | 0.01 | 385.31 | 1.40 | 53,943.40 | 1.40 | 53,943.40 |
| 0008 | 304-01-00100 | Lime | 65.11 | TON | 0.01 | 0.65 | 200.00 | 13,022.00 | 100.00 | 6,511.00 |
| 0009 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 2,759 | SQYD | 0.01 | 27.59 | 2.00 | 5,518.00 | 1.50 | 4,138.50 |
| 0010 | 304-05-00100 | Lime Treatment (Type E) | 78.22 | TON | 0.01 | 0.78 | 200.00 | 15,644.00 | 100.00 | 7,822.00 |
| 0011 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 110,366 | SQYD | 5.70 | 629,086.20 | 7.50 | 827,745.00 | 10.00 | 1,103,660.00 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,657 | CUYD | 1.00 | 1,657.00 | 30.00 | 49,710.00 | 15.00 | 24,855.00 |
| 0013 | 502-01-00100 | Superpave Asphaltic Concrete | 23,675.5 | TON | 69.75 | 1,651,366.13 | 70.00 | 1,657,285.00 | 85.00 | 2,012,417.50 |
| 0014 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 439.8 | TON | 90.00 | 39,582.00 | 125.00 | 54,975.00 | 100.00 | 43,980.00 |
| 0015 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 72,461 | GAL | 3.15 | 228,252.15 | 3.75 | 271,728.75 | 3.00 | 217,383.00 |
| 0016 | 507-02-00200 | Aggregate (S2) | 106,560 | SQYD | 1.00 | 106,560.00 | 1.10 | 117,216.00 | 0.85 | 90,576.00 |
| 0017 | 507-02-00300 | Aggregate (S3) | 106,560 | SQYD | 0.75 | 79,920.00 | 0.80 | 85,248.00 | 0.65 | 69,264.00 |
| 0018 | 509-01-00100 | Cold Planing Asphaltic Pavement | 108,672 | SQYD | 2.65 | 287,980.80 | 2.00 | 217,344.00 | 1.50 | 163,008.00 |
| 0019 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,415 | CUYD | 1.00 | -2,415.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| 0020 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) RCP ONLY | 24 | LNFT | 125.00 | 3,000.00 | 200.00 | 4,800.00 | 125.00 | 3,000.00 |
| 0021 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | 2,500.00 | 2,500.00 |
| 0022 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 1,500.00 | 1,500.00 | 1,000.00 | 1,000.00 | 1,200.00 | 1,200.00 |
| 0023 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 200 | LNFT | 30.00 | 6,000.00 | 40.00 | 8,000.00 | 29.00 | 5,800.00 |
| 0024 | 704-03-00100 | Blocked Out Guard Rail | 176.7 | LNFT | 20.00 | 3,534.00 | 25.00 | 4,417.50 | 18.00 | 3,180.60 |
| 0025 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 65.00 | 6,500.00 | 70.00 | 7,000.00 | 65.00 | 6,500.00 |
| 0026 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 2 | EACH | 2,100.00 | 4,200.00 | 3,000.00 | 6,000.00 | 2,100.00 | 4,200.00 |
| 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 170,000.00 | 170,000.00 | 40,000.00 | 40,000.00 | 60,000.00 | 60,000.00 |
| 0028 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 48 | LNFT | 0.75 | 36.00 | 1.00 | 48.00 | 0.25 | 12.00 |
| 0029 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 29.424 | MILE | 1.00 | 29.42 | 225.00 | 6,620.40 | 400.00 | 11,769.60 |
| 0030 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 12.66 | MILE | 1.00 | 12.66 | 500.00 | 6,330.00 | 50.00 | 633.00 |
| 0031 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 100.068 | MILE | 1.00 | 100.07 | 350.00 | 35,023.80 | 50.00 | 5,003.40 |
| 0032 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 8,500.00 | 8,500.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 |
| 0033 | 726-01-00100 | Bedding Material | 7.5 | CUYD | 150.00 | 1,125.00 | 50.00 | 375.00 | 50.00 | 375.00 |
| 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 325,000.00 | 325,000.00 | 175,000.00 | 175,000.00 | 50,000.00 | 50,000.00 |
| 0035 | 729-16-00200 | Object Marker Assembly (Type 2) | 56 | EACH | 50.00 | 2,800.00 | 65.00 | 3,640.00 | 45.00 | 2,520.00 |
| 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 65.00 | 260.00 | 100.00 | 400.00 | 65.00 | 260.00 |
| 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,285 | EACH | 5.25 | 6,746.25 | 6.00 | 7,710.00 | 5.25 | 6,746.25 |
| 0038 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 48 | LNFT | 5.00 | 240.00 | 6.00 | 288.00 | 5.00 | 240.00 |
| 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 33.356 | MILE | 1.00 | 33.36 | 2,850.00 | 95,064.60 | 2,500.00 | 83,390.00 |
| 0040 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.22 | MILE | 1,100.00 | 4,642.00 | 1,000.00 | 4,220.00 | 850.00 | 3,587.00 |
| 0041 | 735-01-00100 | Mailboxes | 18 | EACH | 10.00 | 180.00 | 7.00 | 126.00 | 1.00 | 18.00 |
| 0042 | 735-02-00100 | Mailbox Supports (Single) | 18 | EACH | 130.00 | 2,340.00 | 150.00 | 2,700.00 | 125.00 | 2,250.00 |
| 0043 | 739-01-00100 | Hydro-Seeding | 23.59 | ACRE | 1.00 | 23.59 | 1,200.00 | 28,308.00 | 1,000.00 | 23,590.00 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 | 24,800.00 | 24,800.00 |
| 0045 | NS-200-00020 | Cleaning Existing Ditches | 1,000 | LNFT | 5.00 | 5,000.00 | 8.00 | 8,000.00 | 10.00 | 10,000.00 |
| 0046 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 516 | INLF | 1.00 | 516.00 | 3.00 | 1,548.00 | 2.50 | 1,290.00 |
| 0047 | NS-700-00240 | Special Guard Rail Anchor Section | 2 | EACH | 1,200.00 | 2,400.00 | 1,500.00 | 3,000.00 | 1,200.00 | 2,400.00 |
| CONTRACTOR TOTAL | 3,642,955.96 | 3,997,166.45 | 4,225,632.25 | |||||||