LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 218-30-0007
Parish: Lafayette
Routes: LA 724
Description: JCT. LOCAL ROAD (ALTHEA DRIVE) -- JCT. US 90
Type Const: GRADING, COLD PLANING ASPHALTIC PAVEMENT, SUBGRADE LAYER, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALTIC SURFACE TREATMENT (INTERLAYER), SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost: $1,723,889.05


RankLicenseBidderConstruction Bid
1 08815 W. E. Mcdonald & Son, LLC. $1,207,152.70
2 33663 Glenn Lege Construction Inc $1,249,080.85
3 51821 Elliott Construction, LLC $1,355,597.90
4 12487 Diamond B Construction Co., L.L.C. $1,397,951.51
5 34356 Prairie Contractors Inc. $1,416,546.01
6 04089 H & S Construction Co., Inc. $1,538,068.56
7 12312 Gilchrist Construction Co. LLC $1,617,504.41


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
W. E. Mcdonald & Son, LLC.
- 2 -
Glenn Lege Construction Inc
- 3 -
Elliott Construction, LLC
- 4 -
Diamond B Construction Co., L.L.C.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 55      SQYD 20.00 1,100.00 45.00 2,475.00 13.00 715.00 21.00 1,155.00
0002 203-07-00100 Borrow (Vehicular Measurement) 100      CUYD 12.00 1,200.00 10.50 1,050.00 17.25 1,725.00 42.00 4,200.00
0003 204-05-00100 Temporary Sediment Check Dams (Hay) 27      EACH 200.00 5,400.00 175.00 4,725.00 79.00 2,133.00 200.00 5,400.00
0004 303-01-00200 In-Place Cement Stabilized Base Course (8 1/2" Thick) 29,859      SQYD 4.95 147,802.05 4.90 146,309.10 5.82 173,779.38 7.00 209,013.00
0005 305-01-03020 Subgrade Layer (10" Thick) (Treated) 29,394      SQYD 4.75 139,621.50 5.35 157,257.90 4.65 136,682.10 5.75 169,015.50
0006 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 607      CUYD 25.00 15,175.00 25.60 15,539.20 33.00 20,031.00 30.00 18,210.00
0007 502-01-00100 Superpave Asphaltic Concrete 6,818      TON 85.14 580,484.52 75.25 513,054.50 79.80 544,076.40 75.00 511,350.00
0008 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,290      TON 35.00 45,150.00 92.30 119,067.00 130.00 167,700.00 100.00 129,000.00
0009 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 20,847      GAL 3.12 65,042.64 3.34 69,628.98 4.15 86,515.05 4.25 88,599.75
0010 507-02-00200 Aggregate (S2) 30,658      SQYD 1.15 35,256.70 1.53 46,906.74 0.95 29,125.10 1.00 30,658.00
0011 507-02-00300 Aggregate (S3) 30,658      SQYD 1.15 35,256.70 1.33 40,775.14 0.95 29,125.10 1.00 30,658.00
0012 509-01-00100 Cold Planing Asphaltic Pavement 28,467      SQYD 2.40 68,320.80 1.75 49,817.25 1.72 48,963.24 2.25 64,050.75
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -1,725      CUYD 0.01 -17.25 1.00 -1,725.00 0.01 -17.25 0.10 -172.50
0014 713-01-00100 Temporary Signs and Barricades 1      LUMP 4,200.00 4,200.00 8,650.00 8,650.00 15,500.00 15,500.00 9,000.00 9,000.00
0015 713-02-00300 Temporary Pavement Markings (8" Width) 190      LNFT 0.20 38.00 0.25 47.50 0.26 49.40 0.25 47.50
0016 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 3.894  MILE 300.00 1,168.20 600.00 2,336.40 420.00 1,635.48 150.00 584.10
0017 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 3.795  MILE 1.00 3.80 333.96 1,267.38 498.75 1,892.76 320.00 1,214.40
0018 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 8.409  MILE 1.00 8.41 667.92 5,616.54 577.50 4,856.20 625.00 5,255.63
0019 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 2      EACH 50.00 100.00 55.66 111.32 52.50 105.00 50.00 100.00
0020 713-05-00200 Temporary Pavement Legends & Symbols (Double Arrow) 2      EACH 50.00 100.00 55.66 111.32 63.00 126.00 50.00 100.00
0021 713-05-00300 Temporary Pavement Legends & Symbols (ONLY) 2      EACH 50.00 100.00 55.66 111.32 52.50 105.00 54.94 109.88
0022 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 515      EACH 1.50 772.50 1.40 721.00 1.58 813.70 2.00 1,030.00
0023 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 2,500.00 2,500.00 5,000.00 5,000.00 5,520.00 5,520.00 10,000.00 10,000.00
0024 727-01-00100 Mobilization 1      LUMP 34,000.00 34,000.00 31,913.72 31,913.72 60,000.00 60,000.00 80,000.00 80,000.00
0025 729-16-00200 Object Marker Assembly (Type 2) 4      EACH 75.00 300.00 50.09 200.36 78.75 315.00 80.00 320.00
0026 731-02-00100 Reflectorized Raised Pavement Markers 258      EACH 4.85 1,251.30 5.40 1,393.20 5.51 1,421.58 5.00 1,290.00
0027 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 95      LNFT 0.95 90.25 1.06 100.70 1.42 134.90 1.00 95.00
0028 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.204  MILE 2,640.00 11,098.56 2,938.85 12,354.93 2,625.00 11,035.50 2,750.00 11,561.00
0029 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.898  MILE 690.00 1,309.62 768.11 1,457.87 892.50 1,693.97 750.00 1,423.50
0030 732-04-01040 Plastic Pavement Legends and Symbols (Arrow - Double) 1      EACH 195.00 195.00 217.07 217.07 278.25 278.25 200.00 200.00
0031 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 1      EACH 185.00 185.00 205.94 205.94 225.75 225.75 200.00 200.00
0032 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 1      EACH 195.00 195.00 217.07 217.07 236.25 236.25 200.00 200.00
0033 735-01-00100 Mailboxes 45      EACH 1.00 45.00 1.00 45.00 1.05 47.25 1.00 45.00
0034 735-02-00100 Mailbox Supports (Single) 37      EACH 115.00 4,255.00 111.32 4,118.84 120.75 4,467.75 125.00 4,625.00
0035 735-03-00100 Mailbox Supports (Double) 4      EACH 170.00 680.00 189.24 756.96 178.50 714.00 175.00 700.00
0036 740-01-00100 Construction Layout 1      LUMP 3,000.00 3,000.00 5,000.00 5,000.00 1,850.00 1,850.00 3,500.00 3,500.00
0037 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 1,604      INLF 1.10 1,764.40 1.40 2,245.60 1.26 2,021.04 3.25 5,213.00
                         
    CONTRACTOR TOTAL       1,207,152.70   1,249,080.85   1,355,597.90   1,397,951.51



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Prairie Contractors Inc.
- 6 -
H & S Construction Co., Inc.
- 7 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 55      SQYD 20.00 1,100.00 65.00 3,575.00 10.00 550.00
0002 203-07-00100 Borrow (Vehicular Measurement) 100      CUYD 15.00 1,500.00 75.00 7,500.00 30.00 3,000.00
0003 204-05-00100 Temporary Sediment Check Dams (Hay) 27      EACH 200.00 5,400.00 85.00 2,295.00 150.00 4,050.00
0004 303-01-00200 In-Place Cement Stabilized Base Course (8 1/2" Thick) 29,859      SQYD 5.50 164,224.50 7.20 214,984.80 6.80 203,041.20
0005 305-01-03020 Subgrade Layer (10" Thick) (Treated) 29,394      SQYD 5.50 161,667.00 8.00 235,152.00 8.00 235,152.00
0006 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 607      CUYD 58.00 35,206.00 50.00 30,350.00 52.00 31,564.00
0007 502-01-00100 Superpave Asphaltic Concrete 6,818      TON 86.00 586,348.00 82.00 559,076.00 85.00 579,530.00
0008 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,290      TON 40.00 51,600.00 105.00 135,450.00 145.00 187,050.00
0009 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 20,847      GAL 3.50 72,964.50 5.50 114,658.50 4.30 89,642.10
0010 507-02-00200 Aggregate (S2) 30,658      SQYD 1.35 41,388.30 1.50 45,987.00 1.00 30,658.00
0011 507-02-00300 Aggregate (S3) 30,658      SQYD 1.25 38,322.50 1.50 45,987.00 1.00 30,658.00
0012 509-01-00100 Cold Planing Asphaltic Pavement 28,467      SQYD 2.50 71,167.50 1.45 41,277.15 2.45 69,744.15
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -1,725      CUYD 0.01 -17.25 0.01 -17.25 0.50 -862.50
0014 713-01-00100 Temporary Signs and Barricades 1      LUMP 10,000.00 10,000.00 17,000.00 17,000.00 10,000.00 10,000.00
0015 713-02-00300 Temporary Pavement Markings (8" Width) 190      LNFT 0.01 1.90 0.35 66.50 0.25 47.50
0016 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 3.894  MILE 400.00 1,557.60 3.25 12.66 290.00 1,129.26
0017 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 3.795  MILE 1.00 3.80 5.25 19.92 100.00 379.50
0018 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 8.409  MILE 1.00 8.41 6.05 50.87 100.00 840.90
0019 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 2      EACH 1.00 2.00 55.00 110.00 60.00 120.00
0020 713-05-00200 Temporary Pavement Legends & Symbols (Double Arrow) 2      EACH 1.00 2.00 55.00 110.00 65.00 130.00
0021 713-05-00300 Temporary Pavement Legends & Symbols (ONLY) 2      EACH 1.00 2.00 55.00 110.00 55.00 110.00
0022 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 515      EACH 1.75 901.25 1.60 824.00 1.70 875.50
0023 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 4,000.00 4,000.00 6,600.00 6,600.00 4,000.00 4,000.00
0024 727-01-00100 Mobilization 1      LUMP 140,000.00 140,000.00 42,000.00 42,000.00 100,000.00 100,000.00
0025 729-16-00200 Object Marker Assembly (Type 2) 4      EACH 100.00 400.00 65.00 260.00 50.00 200.00
0026 731-02-00100 Reflectorized Raised Pavement Markers 258      EACH 6.00 1,548.00 5.35 1,380.30 5.80 1,496.40
0027 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 95      LNFT 2.00 190.00 1.50 142.50 1.50 142.50
0028 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.204  MILE 3,000.00 12,612.00 2,750.00 11,561.00 2,700.00 11,350.80
0029 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.898  MILE 1,000.00 1,898.00 945.00 1,793.61 950.00 1,803.10
0030 732-04-01040 Plastic Pavement Legends and Symbols (Arrow - Double) 1      EACH 500.00 500.00 295.00 295.00 295.00 295.00
0031 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 1      EACH 500.00 500.00 240.00 240.00 240.00 240.00
0032 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 1      EACH 500.00 500.00 250.00 250.00 250.00 250.00
0033 735-01-00100 Mailboxes 45      EACH 1.00 45.00 10.00 450.00 10.00 450.00
0034 735-02-00100 Mailbox Supports (Single) 37      EACH 135.00 4,995.00 125.00 4,625.00 115.00 4,255.00
0035 735-03-00100 Mailbox Supports (Double) 4      EACH 200.00 800.00 145.00 580.00 200.00 800.00
0036 740-01-00100 Construction Layout 1      LUMP 2,000.00 2,000.00 8,500.00 8,500.00 10,000.00 10,000.00
0037 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 1,604      INLF 2.00 3,208.00 3.00 4,812.00 3.00 4,812.00
                     
    CONTRACTOR TOTAL       1,416,546.01   1,538,068.56   1,617,504.41