Bid Tabulations
Letting of
02/24/2010
LA DOTD Headquarters
| Lead Project: 213-05-0039 | |
| Parish: Lafayette | |
| Routes: LA 92 | |
| Description: BONIN RD. AT E. MILTON AVE (LA 92)INTERSECTION IMPROVEMENTS | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $593,789.88 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 33663 | Glenn Lege Construction Inc | $559,792.00 |
| 2 | 04089 | H & S Construction Co., Inc. | $646,967.62 |
| 3 | 51821 | Elliott Construction, LLC | $695,358.51 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $745,123.99 |
| 5 | 13086 | M. Matt Durand, LLC | $835,813.63 |
| 6 | 52550 | Gibbs & Register Inc | $1,350,890.82 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Glenn Lege Construction Inc |
- 2 - H & S Construction Co., Inc. |
- 3 - Elliott Construction, LLC |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 2,200.00 | 2,200.00 | 15,000.00 | 15,000.00 | 3,500.00 | 3,500.00 | 8,000.00 | 8,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,200.00 | 2,200.00 | 12,000.00 | 12,000.00 | 2,000.00 | 2,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 126.81 | SQYD | 20.00 | 2,536.20 | 8.00 | 1,014.48 | 15.00 | 1,902.15 | 11.00 | 1,394.91 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 2,066.16 | SQYD | 5.50 | 11,363.88 | 3.00 | 6,198.48 | 7.00 | 14,463.12 | 6.00 | 12,396.96 |
| 0005 | 203-01-00100 | General Excavation | 738.07 | CUYD | 17.70 | 13,063.84 | 6.00 | 4,428.42 | 8.00 | 5,904.56 | 6.50 | 4,797.46 |
| 0006 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 1,607.5 | CUYD | 10.00 | 16,075.00 | 12.50 | 20,093.75 | 16.00 | 25,720.00 | 23.00 | 36,972.50 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 8 | EACH | 15.00 | 120.00 | 16.00 | 128.00 | 45.00 | 360.00 | 20.00 | 160.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 457.68 | LNFT | 1.75 | 800.94 | 3.00 | 1,373.04 | 2.50 | 1,144.20 | 1.50 | 686.52 |
| 0009 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 3,254.04 | SQYD | 7.10 | 23,103.68 | 8.00 | 26,032.32 | 12.71 | 41,358.85 | 11.00 | 35,794.44 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 1,584.86 | TON | 100.00 | 158,486.00 | 79.00 | 125,203.94 | 118.50 | 187,805.91 | 105.00 | 166,410.30 |
| 0012 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 1,966.25 | GAL | 6.60 | 12,977.25 | 4.00 | 7,865.00 | 3.62 | 7,117.83 | 7.00 | 13,763.75 |
| 0013 | 507-02-00200 | Aggregate (S2) | 6,780.16 | SQYD | 5.10 | 34,578.82 | 1.75 | 11,865.28 | 2.57 | 17,425.01 | 5.40 | 36,612.86 |
| 0014 | 601-01-00900 | Portland Cement Concrete Pavement (12" Thick) | 244.34 | SQYD | 81.00 | 19,791.54 | 90.00 | 21,990.60 | 107.00 | 26,144.38 | 75.00 | 18,325.50 |
| 0015 | 601-02-01500 | Portland Cement Concrete Pavement (12" Thick) (Crossovers & Turnouts) | 216.07 | SQYD | 70.00 | 15,124.90 | 90.00 | 19,446.30 | 90.25 | 19,500.32 | 75.00 | 16,205.25 |
| 0016 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 42.26 | LNFT | 30.00 | 1,267.80 | 70.00 | 2,958.20 | 49.00 | 2,070.74 | 60.00 | 2,535.60 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 168.79 | LNFT | 35.00 | 5,907.65 | 75.00 | 12,659.25 | 50.00 | 8,439.50 | 65.00 | 10,971.35 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 53.75 | LNFT | 47.50 | 2,553.13 | 98.00 | 5,267.50 | 60.00 | 3,225.00 | 120.00 | 6,450.00 |
| 0019 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 178.17 | LNFT | 41.00 | 7,304.97 | 86.00 | 15,322.62 | 55.50 | 9,888.44 | 65.00 | 11,581.05 |
| 0020 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 395.67 | LNFT | 42.50 | 16,815.98 | 90.00 | 35,610.30 | 57.00 | 22,553.19 | 75.00 | 29,675.25 |
| 0021 | 701-07-00300 | Yard Drain Pipe (8") | 9.4 | LNFT | 16.00 | 150.40 | 23.00 | 216.20 | 75.00 | 705.00 | 55.00 | 517.00 |
| 0022 | 701-15-00100 | Concrete Collar | 2 | EACH | 300.00 | 600.00 | 1,150.00 | 2,300.00 | 1,300.00 | 2,600.00 | 800.00 | 1,600.00 |
| 0023 | 702-03-00400 | Catch Basins (CB-05) | 2 | EACH | 480.00 | 960.00 | 3,450.00 | 6,900.00 | 725.00 | 1,450.00 | 2,500.00 | 5,000.00 |
| 0024 | 702-03-00500 | Catch Basins (CB-06) | 6 | EACH | 2,450.00 | 14,700.00 | 4,600.00 | 27,600.00 | 3,500.00 | 21,000.00 | 4,200.00 | 25,200.00 |
| 0025 | 702-08-00100 | Side Drain Safety End (Type I) | 5 | EACH | 1,960.00 | 9,800.00 | 1,800.00 | 9,000.00 | 1,400.00 | 7,000.00 | 1,800.00 | 9,000.00 |
| 0026 | 707-01-00200 | Concrete Curb (Barrier) | 292.17 | LNFT | 7.00 | 2,045.19 | 26.00 | 7,596.42 | 6.50 | 1,899.11 | 11.00 | 3,213.87 |
| 0027 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,369.69 | LNFT | 20.00 | 47,393.80 | 30.00 | 71,090.70 | 13.50 | 31,990.82 | 25.00 | 59,242.25 |
| 0028 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 330.00 | 2,640.00 | 500.00 | 4,000.00 | 378.00 | 3,024.00 | 600.00 | 4,800.00 |
| 0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,142.00 | 9,142.00 | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 17,081.90 | 17,081.90 | 80,000.00 | 80,000.00 | 60,000.00 | 60,000.00 | 67,000.00 | 67,000.00 |
| 0031 | 729-01-00100 | Sign (Type A) | 56 | SQFT | 22.00 | 1,232.00 | 35.00 | 1,960.00 | 32.40 | 1,814.40 | 115.00 | 6,440.00 |
| 0032 | 729-08-00100 | Mounting (2 1/2" Size Post) | 50 | EACH | 875.00 | 43,750.00 | 104.00 | 5,200.00 | 961.00 | 48,050.00 | 740.00 | 37,000.00 |
| 0033 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 1,640.00 | 1,640.00 | 1,725.00 | 1,725.00 | 1,620.00 | 1,620.00 | 1,500.00 | 1,500.00 |
| 0034 | 729-19-00300 | Dead End Road Installations (Type C) | 2 | EACH | 660.00 | 1,320.00 | 680.00 | 1,360.00 | 637.00 | 1,274.00 | 700.00 | 1,400.00 |
| 0035 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,095 | EACH | 5.60 | 11,732.00 | 5.80 | 12,151.00 | 5.67 | 11,878.65 | 6.00 | 12,570.00 |
| 0036 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,142.96 | LNFT | 0.60 | 1,285.78 | 0.60 | 1,285.78 | 0.54 | 1,157.20 | 0.70 | 1,500.07 |
| 0037 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 954 | LNFT | 1.10 | 1,049.40 | 1.50 | 1,431.00 | 1.46 | 1,392.84 | 1.20 | 1,144.80 |
| 0038 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 12 | LNFT | 1.75 | 21.00 | 2.80 | 33.60 | 2.70 | 32.40 | 1.90 | 22.80 |
| 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 140 | LNFT | 4.00 | 560.00 | 5.10 | 714.00 | 4.86 | 680.40 | 4.20 | 588.00 |
| 0040 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 3 | EACH | 210.00 | 630.00 | 240.00 | 720.00 | 232.00 | 696.00 | 225.00 | 675.00 |
| 0041 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 220.00 | 220.00 | 300.00 | 300.00 | 286.00 | 286.00 | 24.00 | 24.00 |
| 0042 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 275.38 | LNFT | 7.20 | 1,982.74 | 7.00 | 1,927.66 | 10.80 | 2,974.10 | 12.00 | 3,304.56 |
| 0043 | 739-01-00100 | Hydro-Seeding | 0.651 | ACRE | 2,200.00 | 1,432.20 | 2,000.00 | 1,302.00 | 2,700.00 | 1,757.70 | 3,000.00 | 1,953.00 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,600.00 | 8,600.00 | 5,000.00 | 5,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 |
| 0045 | 741-01-01040 | Water Main (2" PVC) | 150.39 | LNFT | 11.00 | 1,654.29 | 6.00 | 902.34 | 10.80 | 1,624.21 | 22.00 | 3,308.58 |
| 0046 | 741-03-00100 | Tapping Sleeve and Valve Assembly (2") (Sta. 14+15.00) | 1 | EACH | 1,100.00 | 1,100.00 | 1,200.00 | 1,200.00 | 1,080.00 | 1,080.00 | 1,700.00 | 1,700.00 |
| 0047 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 3,254.04 | SQYD | 8.10 | 26,357.72 | 11.00 | 35,794.44 | 12.00 | 39,048.48 | 9.00 | 29,286.36 |
| 0048 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 4 | EACH | 1,110.00 | 4,440.00 | 200.00 | 800.00 | 1,200.00 | 4,800.00 | 1,100.00 | 4,400.00 |
| CONTRACTOR TOTAL | 559,792.00 | 646,967.62 | 695,358.51 | 745,123.99 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - M. Matt Durand, LLC |
- 6 - Gibbs & Register Inc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 18,000.00 | 18,000.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 126.81 | SQYD | 20.00 | 2,536.20 | 30.00 | 3,804.30 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 2,066.16 | SQYD | 7.00 | 14,463.12 | 10.00 | 20,661.60 |
| 0005 | 203-01-00100 | General Excavation | 738.07 | CUYD | 8.00 | 5,904.56 | 15.00 | 11,071.05 |
| 0006 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 1,607.5 | CUYD | 25.00 | 40,187.50 | 25.00 | 40,187.50 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 8 | EACH | 60.00 | 480.00 | 100.00 | 800.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 457.68 | LNFT | 2.00 | 915.36 | 5.00 | 2,288.40 |
| 0009 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 3,254.04 | SQYD | 8.20 | 26,683.13 | 30.00 | 97,621.20 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 1,584.86 | TON | 128.00 | 202,862.08 | 140.00 | 221,880.40 |
| 0012 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 1,966.25 | GAL | 7.00 | 13,763.75 | 7.40 | 14,550.25 |
| 0013 | 507-02-00200 | Aggregate (S2) | 6,780.16 | SQYD | 5.30 | 35,934.85 | 5.70 | 38,646.91 |
| 0014 | 601-01-00900 | Portland Cement Concrete Pavement (12" Thick) | 244.34 | SQYD | 120.00 | 29,320.80 | 370.00 | 90,405.80 |
| 0015 | 601-02-01500 | Portland Cement Concrete Pavement (12" Thick) (Crossovers & Turnouts) | 216.07 | SQYD | 112.00 | 24,199.84 | 355.00 | 76,704.85 |
| 0016 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 42.26 | LNFT | 47.00 | 1,986.22 | 140.00 | 5,916.40 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 168.79 | LNFT | 62.00 | 10,464.98 | 180.00 | 30,382.20 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 53.75 | LNFT | 77.00 | 4,138.75 | 200.00 | 10,750.00 |
| 0019 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 178.17 | LNFT | 71.00 | 12,650.07 | 140.00 | 24,943.80 |
| 0020 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 395.67 | LNFT | 72.00 | 28,488.24 | 160.00 | 63,307.20 |
| 0021 | 701-07-00300 | Yard Drain Pipe (8") | 9.4 | LNFT | 60.00 | 564.00 | 50.00 | 470.00 |
| 0022 | 701-15-00100 | Concrete Collar | 2 | EACH | 800.00 | 1,600.00 | 1,200.00 | 2,400.00 |
| 0023 | 702-03-00400 | Catch Basins (CB-05) | 2 | EACH | 2,200.00 | 4,400.00 | 1,500.00 | 3,000.00 |
| 0024 | 702-03-00500 | Catch Basins (CB-06) | 6 | EACH | 2,700.00 | 16,200.00 | 4,600.00 | 27,600.00 |
| 0025 | 702-08-00100 | Side Drain Safety End (Type I) | 5 | EACH | 830.00 | 4,150.00 | 2,700.00 | 13,500.00 |
| 0026 | 707-01-00200 | Concrete Curb (Barrier) | 292.17 | LNFT | 20.00 | 5,843.40 | 30.00 | 8,765.10 |
| 0027 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,369.69 | LNFT | 40.00 | 94,787.60 | 45.00 | 106,636.05 |
| 0028 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 160.00 | 1,280.00 | 500.00 | 4,000.00 |
| 0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 77,000.00 | 77,000.00 | 60,000.00 | 60,000.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000.00 | 15,000.00 | 133,000.00 | 133,000.00 |
| 0031 | 729-01-00100 | Sign (Type A) | 56 | SQFT | 25.00 | 1,400.00 | 35.00 | 1,960.00 |
| 0032 | 729-08-00100 | Mounting (2 1/2" Size Post) | 50 | EACH | 980.00 | 49,000.00 | 900.00 | 45,000.00 |
| 0033 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 1,830.00 | 1,830.00 | 1,750.00 | 1,750.00 |
| 0034 | 729-19-00300 | Dead End Road Installations (Type C) | 2 | EACH | 732.00 | 1,464.00 | 750.00 | 1,500.00 |
| 0035 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,095 | EACH | 6.30 | 13,198.50 | 6.00 | 12,570.00 |
| 0036 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,142.96 | LNFT | 0.65 | 1,392.92 | 0.75 | 1,607.22 |
| 0037 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 954 | LNFT | 1.20 | 1,144.80 | 1.50 | 1,431.00 |
| 0038 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 12 | LNFT | 1.95 | 23.40 | 2.00 | 24.00 |
| 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 140 | LNFT | 4.30 | 602.00 | 4.00 | 560.00 |
| 0040 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 3 | EACH | 696.00 | 2,088.00 | 225.00 | 675.00 |
| 0041 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 244.00 | 244.00 | 225.00 | 225.00 |
| 0042 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 275.38 | LNFT | 12.00 | 3,304.56 | 36.00 | 9,913.68 |
| 0043 | 739-01-00100 | Hydro-Seeding | 0.651 | ACRE | 2,500.00 | 1,627.50 | 5,000.00 | 3,255.00 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 37,000.00 | 37,000.00 | 20,000.00 | 20,000.00 |
| 0045 | 741-01-01040 | Water Main (2" PVC) | 150.39 | LNFT | 12.25 | 1,842.28 | 25.00 | 3,759.75 |
| 0046 | 741-03-00100 | Tapping Sleeve and Valve Assembly (2") (Sta. 14+15.00) | 1 | EACH | 3,050.00 | 3,050.00 | 2,000.00 | 2,000.00 |
| 0047 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 3,254.04 | SQYD | 5.50 | 17,897.22 | 29.00 | 94,367.16 |
| 0048 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 4 | EACH | 1,350.00 | 5,400.00 | 1,000.00 | 4,000.00 |
| CONTRACTOR TOTAL | 835,813.63 | 1,350,890.82 | ||||||