LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 207-06-0010
Parish: Acadia
Routes: LA 342
Description: LAFAYETTE PH. LINE - LA 35
Type Const: GRADING, COLD PLANING ASPHALTIC PAVEMENT, IN-PLACE CEMENT TREATED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK
Estimated Construction Cost: $447,721.80


RankLicenseBidderConstruction Bid
1 04089 H & S Construction Co., Inc. $318,658.35
2 12487 Diamond B Construction Co., L.L.C. $404,257.08
3 08815 W. E. Mcdonald & Son, LLC. $418,801.48
4 33663 Glenn Lege Construction Inc $422,826.01
5 51821 Elliott Construction, LLC $434,605.38
6 34356 Prairie Contractors Inc. $481,178.29
7 12312 Gilchrist Construction Co. LLC $482,640.20


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
H & S Construction Co., Inc.
- 2 -
Diamond B Construction Co., L.L.C.
- 3 -
W. E. Mcdonald & Son, LLC.
- 4 -
Glenn Lege Construction Inc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-14500 Removal of Guard Rail 288      LNFT 3.00 864.00 4.00 1,152.00 3.00 864.00 7.00 2,016.00
0002 203-03-00100 Embankment 50      CUYD 13.00 650.00 27.00 1,350.00 30.00 1,500.00 12.00 600.00
0003 203-07-00100 Borrow (Vehicular Measurement) 75      CUYD 16.00 1,200.00 35.00 2,625.00 30.00 2,250.00 8.50 637.50
0004 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 50      CUYD 21.00 1,050.00 30.00 1,500.00 30.00 1,500.00 8.50 425.00
0005 204-05-00100 Temporary Sediment Check Dams (Hay) 4      EACH 53.00 212.00 350.00 1,400.00 0.01 0.04 500.00 2,000.00
0006 304-05-00100 Lime Treatment (Type E) 141.75   TON 325.00 46,068.75 420.00 59,535.00 475.00 67,331.25 362.00 51,313.50
0007 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 9,000      SQYD 4.75 42,750.00 8.25 74,250.00 9.40 84,600.00 6.90 62,100.00
0008 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 285      CUYD 30.00 8,550.00 28.50 8,122.50 50.00 14,250.00 27.00 7,695.00
0009 502-01-00100 Superpave Asphaltic Concrete 1,900.8    TON 76.00 144,460.80 78.25 148,737.60 80.00 152,064.00 73.50 139,708.80
0010 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 60.5    TON 100.00 6,050.00 215.00 13,007.50 127.00 7,683.50 163.50 9,891.75
0011 509-01-00100 Cold Planing Asphaltic Pavement 7,825      SQYD 1.40 10,955.00 2.10 16,432.50 4.00 31,300.00 4.00 31,300.00
0012 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -611      CUYD 1.00 -611.00 0.10 -61.10 0.01 -6.11 1.00 -611.00
0013 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 240      LNFT 33.20 7,968.00 24.00 5,760.00 31.00 7,440.00 40.00 9,600.00
0014 704-03-00100 Blocked Out Guard Rail 200      LNFT 18.70 3,740.00 22.00 4,400.00 17.50 3,500.00 21.60 4,320.00
0015 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 54.50 5,450.00 64.00 6,400.00 51.00 5,100.00 74.00 7,400.00
0016 704-11-00200 Guard Rail End Treatment (Tangent) 4      EACH 2,445.00 9,780.00 2,400.00 9,600.00 2,290.00 9,160.00 3,100.00 12,400.00
0017 713-01-00100 Temporary Signs and Barricades 1      LUMP 4,040.00 4,040.00 7,000.00 7,000.00 2,900.00 2,900.00 3,650.00 3,650.00
0018 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.262  MILE 350.00 441.70 190.00 239.78 500.00 631.00 570.00 719.34
0019 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.689  MILE 508.00 350.01 350.00 241.15 400.00 275.60 365.00 251.49
0020 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 4.359  MILE 586.00 2,554.37 350.00 1,525.65 550.00 2,397.45 800.00 3,487.20
0021 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 3,000.00 3,000.00 5,600.00 5,600.00 3,000.00 3,000.00 21,300.00 21,300.00
0022 727-01-00100 Mobilization 1      LUMP 10,500.00 10,500.00 24,000.00 24,000.00 12,000.00 12,000.00 39,000.00 39,000.00
0023 731-02-00100 Reflectorized Raised Pavement Markers 90      EACH 5.65 508.50 4.50 405.00 5.25 472.50 6.00 540.00
0024 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 2.18   MILE 2,670.00 5,820.60 3,200.00 6,976.00 2,500.00 5,450.00 3,125.00 6,812.50
0025 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.345  MILE 895.00 308.78 700.00 241.50 850.00 293.25 800.00 276.00
0026 732-05-00100 Removal of Existing Markings 0.023  MILE 4,645.00 106.84 5,000.00 115.00 5,000.00 115.00 5,910.00 135.93
0027 735-01-00100 Mailboxes 2      EACH 17.50 35.00 1.00 2.00 15.00 30.00 1.00 2.00
0028 735-03-00100 Mailbox Supports (Double) 1      EACH 230.00 230.00 500.00 500.00 200.00 200.00 855.00 855.00
0029 740-01-00100 Construction Layout 1      LUMP 1,625.00 1,625.00 3,200.00 3,200.00 2,500.00 2,500.00 5,000.00 5,000.00
                         
    CONTRACTOR TOTAL       318,658.35   404,257.08   418,801.48   422,826.01



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Elliott Construction, LLC
- 6 -
Prairie Contractors Inc.
- 7 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-14500 Removal of Guard Rail 288      LNFT 7.00 2,016.00 6.00 1,728.00 15.00 4,320.00
0002 203-03-00100 Embankment 50      CUYD 38.00 1,900.00 109.00 5,450.00 40.00 2,000.00
0003 203-07-00100 Borrow (Vehicular Measurement) 75      CUYD 18.00 1,350.00 109.00 8,175.00 50.00 3,750.00
0004 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 50      CUYD 18.00 900.00 30.00 1,500.00 40.00 2,000.00
0005 204-05-00100 Temporary Sediment Check Dams (Hay) 4      EACH 150.00 600.00 350.00 1,400.00 300.00 1,200.00
0006 304-05-00100 Lime Treatment (Type E) 141.75   TON 200.00 28,350.00 538.00 76,261.50 365.00 51,738.75
0007 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 9,000      SQYD 8.00 72,000.00 10.00 90,000.00 10.00 90,000.00
0008 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 285      CUYD 46.47 13,243.95 80.00 22,800.00 45.00 12,825.00
0009 502-01-00100 Superpave Asphaltic Concrete 1,900.8    TON 85.00 161,568.00 81.00 153,964.80 93.00 176,774.40
0010 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 60.5    TON 194.27 11,753.34 150.00 9,075.00 280.00 16,940.00
0011 509-01-00100 Cold Planing Asphaltic Pavement 7,825      SQYD 2.25 17,606.25 3.00 23,475.00 3.00 23,475.00
0012 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -611      CUYD 0.01 -6.11 0.01 -6.11 0.10 -61.10
0013 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 240      LNFT 31.50 7,560.00 25.00 6,000.00 35.00 8,400.00
0014 704-03-00100 Blocked Out Guard Rail 200      LNFT 18.90 3,780.00 23.00 4,600.00 20.00 4,000.00
0015 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 100      LNFT 63.00 6,300.00 65.00 6,500.00 60.00 6,000.00
0016 704-11-00200 Guard Rail End Treatment (Tangent) 4      EACH 2,362.50 9,450.00 2,500.00 10,000.00 2,700.00 10,800.00
0017 713-01-00100 Temporary Signs and Barricades 1      LUMP 50,000.00 50,000.00 5,100.00 5,100.00 10,000.00 10,000.00
0018 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.262  MILE 496.01 625.96 400.00 504.80 300.00 378.60
0019 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.689  MILE 336.49 231.84 1.00 0.69 100.00 68.90
0020 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 4.359  MILE 724.50 3,158.10 1.00 4.36 100.00 435.90
0021 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 2,932.50 2,932.50 3,000.00 3,000.00 5,000.00 5,000.00
0022 727-01-00100 Mobilization 1      LUMP 30,000.00 30,000.00 44,300.00 44,300.00 40,000.00 40,000.00
0023 731-02-00100 Reflectorized Raised Pavement Markers 90      EACH 5.36 482.40 6.50 585.00 6.00 540.00
0024 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 2.18   MILE 2,887.50 6,294.75 2,500.00 5,450.00 2,900.00 6,322.00
0025 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.345  MILE 735.01 253.58 850.00 293.25 950.00 327.75
0026 732-05-00100 Removal of Existing Markings 0.023  MILE 5,460.00 125.58 5,000.00 115.00 5,000.00 115.00
0027 735-01-00100 Mailboxes 2      EACH 1.05 2.10 1.00 2.00 20.00 40.00
0028 735-03-00100 Mailbox Supports (Double) 1      EACH 787.50 787.50 800.00 800.00 250.00 250.00
0029 740-01-00100 Construction Layout 1      LUMP 1,339.64 1,339.64 100.00 100.00 5,000.00 5,000.00
                     
    CONTRACTOR TOTAL       434,605.38   481,178.29   482,640.20