Bid Tabulations
Letting of
09/22/2010
LA DOTD Headquarters
| Lead Project: 197-02-0022 | |
| Parish: Calcasieu | |
| Routes: LA 383 | |
| Description: SECOND ST - UNION PACIFIC RAILROAD | |
| Type Const: GRADING, IN-PLACEMENT CEMENT STABILIZED BASE COURSE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $273,979.76 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 14096 | Bessette Development Corp. | $315,668.00 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $396,238.36 |
| 3 | 36384 | John Bailey, Inc. | $399,716.11 |
| 4 | 34356 | Prairie Contractors Inc. | $451,107.41 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Bessette Development Corp. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - John Bailey, Inc. |
- 4 - Prairie Contractors Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 19,464.00 | 19,464.00 | 9,350.12 | 9,350.12 | 15,000.00 | 15,000.00 | 18,000.00 | 18,000.00 |
| 0002 | 303-01-00400 | In-Place Cement Stabilized Base Course (12" Thick) | 3,129 | SQYD | 16.00 | 50,064.00 | 16.25 | 50,846.25 | 15.00 | 46,935.00 | 18.00 | 56,322.00 |
| 0003 | 303-02-00100 | Removal of Existing Patches | 415 | SQYD | 30.50 | 12,657.50 | 15.87 | 6,586.05 | 20.00 | 8,300.00 | 20.00 | 8,300.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 1,482.6 | TON | 90.75 | 134,545.95 | 133.56 | 198,016.06 | 115.00 | 170,499.00 | 120.00 | 177,912.00 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 27.9 | TON | 150.50 | 4,198.95 | 647.34 | 18,060.79 | 205.00 | 5,719.50 | 350.00 | 9,765.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement (6" THICK) | 3,129 | SQYD | 3.95 | 12,359.55 | 6.79 | 21,245.91 | 7.00 | 21,903.00 | 6.00 | 18,774.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement (2" THICK) | 4,236 | SQYD | 2.75 | 11,649.00 | 3.54 | 14,995.44 | 4.00 | 16,944.00 | 10.00 | 42,360.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -719 | CUYD | 1.00 | -719.00 | 0.10 | -71.90 | 0.01 | -7.19 | 0.01 | -7.19 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 90.75 | 9,075.00 | 147.43 | 14,743.00 | 95.00 | 9,500.00 | 206.00 | 20,600.00 |
| 0010 | 706-04-00100 | Handicapped Curb Ramps | 2 | EACH | 1,785.75 | 3,571.50 | 1,564.94 | 3,129.88 | 1,400.00 | 2,800.00 | 1,500.00 | 3,000.00 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,695.00 | 2,695.00 | 6,038.39 | 6,038.39 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 |
| 0012 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 4,020 | LNFT | 0.25 | 1,005.00 | 0.28 | 1,125.60 | 0.25 | 1,005.00 | 0.01 | 40.20 |
| 0013 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 3,336 | LNFT | 0.80 | 2,668.80 | 1.07 | 3,569.52 | 1.00 | 3,336.00 | 0.01 | 33.36 |
| 0014 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.42 | MILE | 515.00 | 216.30 | 260.83 | 109.55 | 2,640.00 | 1,108.80 | 400.00 | 168.00 |
| 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.74 | MILE | 811.00 | 1,411.14 | 1,067.01 | 1,856.60 | 900.00 | 1,566.00 | 0.01 | 0.02 |
| 0016 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 108.15 | 216.30 | 142.27 | 284.54 | 120.00 | 240.00 | 0.01 | 0.02 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 38,401.74 | 38,401.74 | 26,600.00 | 26,600.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 28 | EACH | 16.25 | 455.00 | 21.34 | 597.52 | 18.00 | 504.00 | 20.00 | 560.00 |
| 0019 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,010 | LNFT | 0.60 | 1,206.00 | 0.74 | 1,487.40 | 0.65 | 1,306.50 | 0.75 | 1,507.50 |
| 0020 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,530 | LNFT | 3.20 | 4,896.00 | 4.20 | 6,426.00 | 3.55 | 5,431.50 | 3.25 | 4,972.50 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 138 | LNFT | 3.35 | 462.30 | 4.41 | 608.58 | 3.75 | 517.50 | 5.00 | 690.00 |
| 0022 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.87 | MILE | 2,919.50 | 2,539.97 | 3,841.22 | 3,341.86 | 3,250.00 | 2,827.50 | 3,000.00 | 2,610.00 |
| 0023 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 435.00 | 435.00 | 569.07 | 569.07 | 480.00 | 480.00 | 500.00 | 500.00 |
| 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,675.00 | 1,675.00 | 1,991.74 | 1,991.74 | 4,600.00 | 4,600.00 | 100.00 | 100.00 |
| 0025 | NS-MSC-00080 | Detectable Warning System Retrofit for Curb Ramps | 7 | EACH | 74.00 | 518.00 | 675.77 | 4,730.39 | 600.00 | 4,200.00 | 700.00 | 4,900.00 |
| CONTRACTOR TOTAL | 315,668.00 | 396,238.36 | 399,716.11 | 451,107.41 | ||||||||